Rajasthan State Road Development & Construction Corporation Ltd. Unit-II, Bikaner C-72, Sadul Ganj, Bikaner
ORGANISATIONAL CHART OF RSRDCC UNIT-II BIKANER Resident Engineer Sh. R. K.Mathur A. A. O. Sh. B. L. Darak ARE Sh. S. M. Swami ARE Sh. Sunil Gahlot ARE Sh. Sanjay Golwal ARE Sh. S. P. Mathur ARE Sh. M.G. Shrimali
Financial Work Load in Unit-II, Bikaner S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – I Sh. S. M. Swami 1 Laying Sewer Line for Police Qtrs. Police Dept. 38.16 Lacs 4.02 Lacs 34.14 Lacs 2 Water Supply arrangement for Police Qtrs. 53.18 Lacs 24.74 Lacs 28.44 Lacs 3 Const. of LSQ-II Police Line, Bikaner 142.72 Lacs 103.13 Lacs 18.87 Lacs 4 Const of LSQ-IV Police Line, Bikaner 220.24 Lacs 138.87 Lacs 48.33 Lacs 5 Const. of 40 Nos. LSQ X RAC, Bikaner 124.24 Lacs 91.91 Lacs 13.69 Lacs ARE – II Sh Sunil Gahlot Const. of LSQ & USQ at X RAC, Bikaner 469.22 Lacs 353.18 Lacs 45.66 Lacs ARE – III Sh. Sanjay Golwal Const. of LSQ III Police Line, Bikaner 191.94 Lacs 137.58 Lacs 25.56 Lacs Protection work on New Bikaner Bye Pass BOT Project 45.69 Lacs 24.81 Lacs 20.88 Lacs Const. of retaining wall on New Bikaner Bye Pass 34.65 Lacs ARE – III Sh. S. P. Mathur Const. of LSQ & USQ at PMDS & JNV Bikaner 123.10 Lacs 103.10 Lacs 7.00 Lacs Const. of 2 Nos. LSQ at JNV & 8 Nos. LSQ at PMDS 29.48 Lacs 23.16 Lacs 6.32 Lacs Const. of Bye Pass Zone I km 0/0 to 13/0 496.83 Lacs 477.08 Lacs 19.75 ARE – V Sh. M.G. Shrimali Const. Bikaner Bye Pass km 13/0 to 26/0 Zone II 496.92 Lacs 460.38 Lacs 36.54 Lacs Supply of Grit to Hot Mix Plant for Bye Pass 186.00 Lacs 164.00 Lacs 22.00 Lacs Transportation of Bitumen of Bikaner Bye Pass 52.00 Lacs 48.00 Lacs 4.00 Lacs 4. Road Furniture work 86.00 Lacs 00.00
Proposed new works RSRDCC Unit-II, bikaner S. No. Name of work Client Department Mode Actual/Tender Estimated Cost Remarks 1. Construction of Library Block, Academic Block (Science) & Compound Wall in University of Bikaner Maharaja Gangasingh University, Actual Plus 467.00 Lacs MOU Signed Drawings Submitted for Approval 2. Building of Kendriya Shakari Bank at Hanumangarh, Junction Co-operative Bank 325.00 Client department has principally agreed & further negotiations are in process.
Important Works Completed by RSRDCC Unit-II, Bikaner During last 5 Year’s 1 Construction of Married accommodation Project For OR’s & JCO’s at Sriganganagar & Suratgarh. [Tendered work.] Completion Cost Rs. 2814.00 Lacs. 2 Stregthening & improvement of Hanumangarh Pillibanga Suratgarh road including ROB at LC 71 A at Hanumangarh Junction. Completion Cost Rs. 2736.43 Lacs. 3 Construction of V.C. Secretariat, Examination Block, Administrative Block and Guest Housing Buildings in University of Bikaner. Completion Cost Rs. 564.00 Lacs. 4 Construction of Internal road, Entrance Plaza, Compound Wall, Water Supply arrangements and External Electrification Work in the premises of University of Bikaner. Completion Cost Rs. 179.00 Lacs. 5 Construction of 5000 MT Godown, Office building, Compound Wall, Internal road for RAJFED at Sriganganagar. Completion Cost Rs. 121.00 Lacs. 6 Widening and Strengthening of Sriganganagar Hanumangarh road km 0/500 to 56/0 [BOT Project ] Tendered Work. Completion Cost Rs. 1594.50 Lacs.
198 OR’s MAP Package III At Sri-Ganganagar Completion Cost Rs. 1081.79 Lacs.
ROB at LC 71A at Hanumangarh Junction Completion Cost Rs. 475.00 Lacs Foundation Stone laid by Hon’ble PWM on 27.5.2005 Inaugurated by Hon’le Ex-Minister on 20.9.2008
V.C. Secreterait & Guest House, UOB, Bikaner Completion Cost Rs. 195.93 Lacs Foundation Stone laid by Hon’ble Governor on 24.4.2005 Inaugurated by Hon’ble Chief Minister on 14.8.2008
Entrance Plaza & Devlopment Works in the premises of University of Bikaner Completion Cost Rs. 179.00 Lacs
Godown 5000 MT Capacity for RAJFED at RIICO Sriganganagar. Completion Cost Rs. 121.00 Lacs
POLICE HOUSING SCHEME No. of Quarter : LSQ 156 nos., USQ 3 nos. Total Cost : 737.76 Lacs Location : Xth RAC, Bikaner Date of Start : 3.3.2008 Stipulated Date of Completion : 2.2.2009 Expenditure till Date : 611.19 Lacs Likely Completion Date : December, 2009
POLICE HOUSING SCHEME No. of Quarter : 40 nos. LSQ Total Cost : 185.60 Lacs Location : Xth RAC, Bikaner Date of Start : 13.05.2008 Stipulated Date of Completion : 12.04.2009 Expenditure till Date : 156.68 Lacs Likely Completion Date : December, 2009
POLICE HOUSING SCHEME No. of Quarter : 34nos. LSQ & 6nos. USQ Total Cost : 185.60 Lacs Location : PMDS and JNV Police Station Date of Start : 03.03.2008 Stipulated Date of Completion : 02.02.2009 Expenditure till Date : 172.77 Lacs Likely Completion Date : December, 2009
POLICE HOUSING SCHEME No. of Quarter : 10 Nos. LSQ Total Cost : 46.40 Lacs Location : PMDS and JNV Police Station Date of Start : 11.10.2008 Stipulated Date of Completion : 10.07.2009 Expenditure till Date : 39.38 Lacs Likely Completion Date : December, 2009
POLICE HOUSING SCHEME No. of Quarter : 48 Nos. LSQ Total Cost : 222.72 Lacs Location : Police Line, Bikaner Date of Start : 19.04.2008 Stipulated Date of Completion : 18.03.2009 Expenditure till Date : 179.68 Lacs Likely Completion Date : December, 2009
POLICE HOUSING SCHEME No. of Quarter : 60 Nos. LSQ Total Cost : 278.40 Lacs Location : Police Line, Bikaner Date of Start : 11.10.2008 Stipulated Date of Completion : 10.07.2009 Expenditure till Date : 234.70 Lacs Likely Completion Date : Jan., 2009
POLICE HOUSING SCHEME No. of Quarter : 72 Nos. LSQ Total Cost : 334.08 Lacs Location : Police Line, Bikaner Date of Start : 13.05.2008 Stipulated Date of Completion : 12.04.2009 Expenditure till Date : 251.05 Lacs Likely Completion Date : Jan., 2009
POLICE HOUSING SCHEME No. of Quarter : P&L&J of Sewer Line for Police Housing Project Total Cost : 38.17 Lacs Location : Police Housing Premises, Bikaner Date of Start : 07.06.2009 Stipulated Date of Completion : 06.10.2009 Expenditure till Date : 4.39 Lacs Likely Completion Date : Dec., 2009 Bottlenecks if Any : Permission to Lay Line and connect with the existing sewer system of Karni Nagar Colony was accorded in Sept. 2009 by Nagar Nigam after great pursuance.
POLICE HOUSING SCHEME No. of Quarter : Const. of OHSR, CWR & P&L&J of Distribution System Total Cost : 53.19 Lacs Location : Police Housing Premises, Bikaner Date of Start : 07.06.2009 Stipulated Date of Completion : 06.12.2009 Expenditure till Date : 26.98 Lacs Likely Completion Date : Dec., 2009 Bottlenecks if Any : PHED department has not yet approved the scheme of Rs.81.55 Lacs for providing water supply to the Police Housing Premises.
Const. of New Bikaner Bye Pass BOT Project Name of Work : Const. of New Bikaner Bye-Pass connecting NH-15 Bikaner-Jaisalmer Road to NH-15 Bikaner- Sriganganagar road Km 0/0 to 26/0. Total Cost : 4169.93 Lacs. Off Take Point : Km 0/0 of Bye Pass is at NH-15 Bikaner- Jaisalmer road in km 17/500 End Point : Km 26/0 of Bye Pass meets NH-15 Bikaner- Sri –Ganganagar road in km 14/600 Date of Start : 28.7.2009 Stipulated Date of Completion : 31.3.2010 Expenditure till Date : Rs.2211.61 Lacs. Likely Completion date : 15.1.2009
Bituminous Concrete work in Progress in km 0/0 to 1/0 of Bye Pass
Rotary at SH-03 Chhattargarh Road Km 10/775 of Bye Pass
Bikaner Bye Pass Km 1/0
Toll Plaza in Km 0/0 to 1/0 of Bikaner Bye Pass