Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd
Date: 11/03/20092 Overview of Presentation Vault 9 Design Current Status
Date: 11/03/20093 Vault 9 Vault 9 Design
Date: 11/03/20094 Plan Overview Scheme ANDY – Can you insert the base site plan that you are using to show the new material facility plan – Showing the Current infrastructure
Date: 11/03/20095 Proposed Development
Vault 9 Liner Details
Date: 11/03/20097 Vault 9 Current Status
Date: 11/03/20098 Bulk Excavation – 100% Complete
Date: 11/03/20099 Rail Deliveries – Aggregate, Reinforcement & Ancillaries
Date: 11/03/ Rail Deliveries – Port of Workington
Date: 11/03/ Rail Deliveries – Millom Main Line Loading
Date: 11/03/ West Outer Wall Construction - 95% Complete
Date: 11/03/ Secant Pile Wall – 100% Complete
Date: 11/03/ BES Bottom Layer - 80% Complete
Date: 11/03/ Geomembrane, Geotextile & Drainage Layer – 45% Complete
Date: 11/03/ Vault 9 Floor Slab - 22% Complete
Date: 11/03/ West Inner Wall - 60% Complete
Date: 11/03/ Partial Handover – 21 st July 2009
Date: 11/03/ Delivery Schedule Partial Turnover to Operations – July 2009 Operational Safety Case Approved First HHISO –July 2009 Contract Completion – January 2010
Date: 11/03/ Vault 9 Questions