NTS Exit Capacity - Amending the DN Adjustment Window Transmission Workstream, 1 April 2010
2010 DN Adjustment Window – Brief Overview 31 July-Annual Application Window Closes 15 Sept-National Grid NTS - provides Indicative OCS/OPS Statements DNO Users - have 5 Business Days to seek clarification and resubmit applications for NTS Exit (Flexibility) Capacity, Assured Pressures and NTS Exit (Flat) Capacity 22 Sept-Final date for DNO Users to submit requests 30 Sept-National Grid NTS issues the final Offtake Capacity Statement (OCS) and Offtake Pressure Statement (OPS) and allocate requests for NTS Exit (Flat) Capacity
Proposed Changes National Grid NTS is proposing to amend the date that the indicative OCS/OPS will be issued from the 15 th September to the 1 st September DNO Users to be then given [10] Business Days to clarify and/or resubmit applications for NTS Exit (Flexibility) Capacity/Assured Pressures, and submit revised applications for NTS Exit (Flat) Capacity (n.b. only where request for NTS Exit (Flexibility) Capacity/Assured Pressure have been rejected)
2010 Adjustment Window – Current UNC
2010 Adjustment Window – Proposed Changes