Marin Community College District CIP Briefing – Citizen’s Oversight Committee September 13, 2005
Kentfield Campus Tentative Project List Modernization of Learning Resource Center – 66,000 gsf Modernization of Harlan Center – 25,651 gsf Modernization of Fusselman Hall – 14,717 gsf Modernization of Science Center – 50,837 gsf Modernization of Fine Arts Center – 79,636 gsf Modernization of Student Center – 36,227 gsf Modernization of Diamond Physical Ed Center – 36,392 gsf Multi-purpose, Child Care & Support Facility – 75,000 gsf – New Construction Liberal Arts Complex or Science Building - 75,000 gsf – New Construction Facilities Maintenance Center 30,000 gsf – New Construction Gateway Entrance Plaza – New Construction
Indian Valley Campus Tentative Projects List Modernization of Pomo Center - 47,494 gsf Modernization of Administrative & Children’s Center - 19,588 gsf Capital Renewal & Expansion of Central Plant - 2,000 gsf Capital Renewal of Library – 14,280 gsf Capital Renewal of Miwok Cluster – 28,410 gsf Capital Renewal of Ohlone Cluster – 20,543 Pedestrian Bridges
Bolinas Marine Biology Center Modernization or New Construction – 3,333 gsf
District-Wide Tentative Projects List Telecommunications Infrastructure Site Parking & Roadways Utilities (Sanitary, Storm, Electrical, Gas) Fire Alarm Replacement Access Controls ADA Accessibility Improvements Signage
District Design Team
District Architect Campus Master Planning Design & Drafting Guidelines Interior & Exterior Finish Standards Furniture, Fixtures & Equipment Standards
District Landscape Architect Services Master Planning District Standards Design Guidelines
District Civil Engineering Update all Surveys (Topographic & Boundary) Locate, map, Identify, Inspect & Analyze all Utilities Identify all Easements & Encumbrances on District Property Create Accurate Electronic “As-Built” / Record Drawings that Record all Above Information Develop District Standards and Design Guidelines
District Geotechnical Engineering Collect and Synthesize all Existing Soils Testing and Analysis Information Recommend and/or Perform Additional Soils Testing & Analysis Perform Fault Analysis Provide Design parameters for Building and Infrastructure Design
Mechanical and Plumbing Engineering Chilled Water Systems Heating Hot Water Systems Co-Generation / Central Plant Systems Water Distribution Systems Building and Site Mechanical Systems Savings by Design Building and Site Control Systems
Electrical Engineering Substations Co-Generation Electrical Distribution Systems Lighting Savings by Design Control Systems MCC
California Environmental Quality Act (CEQA) Provides review, analysis & studies to assess the District’s development plan and its impact on the environment in accordance with the California Environmental Quality Act. Prepares & Produces Required Documentation Negative Declaration Mitigated Negative Declaration Environmental Impact Report(s)
Next Steps Educational Master Plan – Road map to future District Consultants Design Guidelines Building Standards FF & E Standards District Assessments and Surveys Program Definition Scope / Schedule / Budget
Next Steps Board of Trustee Retreats September 20 th – Facilities Master Planning October 11 th – Program Controls Green Summit on Sustainability – Facilities September 30, 2005 – 9 A. M. to 3 P. M. (Initial Sustainability Summit Held September 9 th )
Next Steps Projects in Design Kentfield Roof Repairs – Harlan Center and LRC Partial Roof Replacement – Physical Education Building Tree Trimming and Removal Demolition of Larkspur Annex IVC Wildfire Mitigation Partial Gas Main Replacement Tree Trimming and Removal Stream Erosion Mitigation
Other Issues Kentfield Title 9 Compliance (PE Complex) IVC Bridge Load Testing Bolinas Fault Study
Questions & Answers Dave Kirn Program Manager (415) José D. Nuñez Director of Modernization (650)