February 10, 2010 Sarasota Memorial Health Care System Management Council February 10, 2010
February 10, 2010 Construction Milestone Schedule
February 10, 2010 Preparation for Structural Steel Close Arlington Street Capture Site Set up Crane for Structural Steel Open Arlington Street Project Milestones – Surgery Vertical Expansion: Target Start – 2/22/10 Target Start – 4/12/10 Target Start - 12/31/10
February 10, 2010 Site Phasing Diagram – Surgery Vertical Expansion Construction Zone for Crane, Material Deliveries, etc. Ambulance Access to be Maintained at All Times
February 10, 2010 Wound Care Renovations CEP Equipment Removal Construct Temporary Waldemere Garage Entrance After Garage Entrance is complete construct Interim Main Entrance Old Central Energy Plant Structure Demolition Construct Temporary ECC Canopy & Drop off Open Temporary Canopy & Drop Off / Close Hawthorne in Front of ECC / Construct New ECC Drop Off Install New & Relocate Site Utilities / Construct New Loop Road Open New Loop Road / New Drop Offs / Close Hawthorne / Capture Site for Bed Tower Demolition / Construct Stair & Elevator Tower & Bridge Connector New Bed Tower Construction Project Milestones – New Bed Tower: Target Completion - 7/1/10 Target Start - 3/8/10 Target Start - 3/29/10 Target Start - 5/17/10 Target Start - 3/29/10 Target Start - 5/3/10 Target - 6/7/10 Target Start - 5/3/10 Target Start - 9/20/10 Target Start - 12/28/10
February 10, 2010 Site Phasing Diagram - 1 Demolish Old CEP Interim Moves for Surgery Support & Pathology Remove Equipment from CEP Create Temporary Garage Entry/Exit onto Waldemere St
February 10, 2010 Site Phasing Diagram - 2 Create Temporary ECC Entry Drop-Off Temporary ECC Entry Canopy
February 10, 2010 Site Phasing Diagram - 3 Open Temporary ECC Entry Canopy & Drop-off Build Temp Main Entrance Canopy, Drop-off & Vestibule Close Hawthorne Street Construct New Loop Road and Associated Utilities Temporary Route to ECC Construct New ECC Vestibule, Canopy & Drop-off Open New Entry/Exit at Waldemere Garage
February 10, 2010 Site Phasing Diagram - 4 Open Temporary Main Entry Canopy & Drop-off Demolish Existing Main Entry Canopy Open ECC Vestibule, Canopy & Drop-off Open New Loop Road Demolish Northeast Tower Demolish Portion of Critical Care Tower for New Bridge
February 10, 2010 Site Phasing Diagram - 5 Construct New Bed Tower and Bridge