TIDAL TURBINE FOUNDATION OPTIMISATION RAMBOLL ENERGY MOJO MARITIME Alternative title slide.

Slides:



Advertisements
Similar presentations
Wave Power Potential An energy Scenario for the UK
Advertisements

Forth Estuary Forum 28th Nov 2013
A Bridge to a Sustainable Energy Future A B RIDGE TO U NIVERSAL E NERGY A CCESS 1 Reflections on Achieving Universal Access to Electricity in Myanmar Q1:
Self Installing Wind Turbine (SIWT) Mark Riemers – Managing Director.
Energy Policy and Scotland’s Constitutional Future Setting the Scene John Paterson University of Aberdeen.
Optimising Site Investigations for Offshore Wind Farm Projects Mark Finch Geotechnical Engineering Manager Hydrosearch Associates, Aberdeen UK Offshore.
The Energy Technology Partnership Dr Simon Puttock Executive Director, ETP KT Scotland Conference, 2010.
Ilinca Julian, Heikki Ojanen, Juha - Matti Lukkari.
Louisiana Offshore Wind Energy Wind Energy Systems Technologies, LLC New Iberia, Louisiana, USA Presented By: Herman J. Schellstede W.E.S.T.
ARENA & Ocean Energy Clean Energy Week 2014 Louise Vickery General Manager, Renewable Futures ARENA 23 July 2014.
NNMREC National Marine Renewable Energy Centers Hawaii National Marine Renewable Energy Center (HINMREC) University of Hawaii Wave, OTEC Southeast National.
Service and Training. Our engineers and Instructors are all highly qualified and possess many years of experience with top manufacturers. Surveys Studies.
THE MONOPOD BUCKET FOUNDATION Recent experience and challenges ahead Christian LeBlanc1, Kim Ahle1, Søren A. Nielsen 2, Lars B. Ibsen 3 1) DONG Energy,
Show guidelines, which are useful when placing elements and photos: 1. Rightclick on the slide and choose ’Grid and Guides’ 2. Check ’Display drawing guides.
Insider’s Guide to Renewable Energy: Careers Event Katie Wray Teaching Fellow for Enterprise Faculty of Science, Agriculture and Engineering 29 th February.
© Siemens AG 2011 Hull Offshore Wind Workshop Siemens Wind Power A/S, Thomas Mousten, Offshore Wind Americas.
The Wider Offshore Industry - Introduction. Why Renewables? Mb/doe Gas Nuclear Oil Renewables Coal Incremental.
DHL, A leader in logistics Faysal Elhajjami Business Development Manager, Chemicals Industry Eastern Europe, Middle East and Africa NOT AN OFFICIAL UNCTAD.
© ABB-EWEC 2006 ATHENS /03/06 EWEC 2006 Athens The Challenges of Offshore Power System Construction Peter Jones Lars Stendius ABB.
Physics: Concepts and Connections, 4 th ed., Art Hobson Chapter 17 – Energy Challenge.
Deep Water Offshore Wind Energy By Paul D. Sclavounos Horns Rev Wind Farm (Denmark) - Rated Power 160 MW – Water Depth 10-15m.
Environmental issues faced across the project lifecycle Sue Barr Open Hydro.
What are 5 ways you use energy? Brainstorm! What are 5 ways you use energy?
1 Challenge the future Ocean Energy – Tidal Energy Antonio Jarquin-Laguna Challenge the future.
Greta’s Grand Valley Wind Farm Contributing to Ontario’s Energy Future March, 2012 Greta Energy Inc.
©2015 Energy Technologies Institute LLP - Subject to notes on page 1 ©2015 Energy Technologies Institute LLP The information in this document is the property.
Planning and Policies for Offshore Renewables: Drawing Lessons after two of decades of global experience. Dr. Brendan Flynn School of Political Science.
Wave Energy Kate Riley Energy Alternatives Spring 2007.
Maine Wind and Ocean Energy Industry Initiative An Overview Jeff Thaler Visiting Professor, University of Maine Co-Chair, E2Tech November 15, 2011.
The Economics of Marine Renewable Energy Peter McGregor Fraser of Allander Institute, Department of Economics, University of Strathclyde Second Forum on.
NAVITAS Techno-financial Project software for renewable energy Michael O’Connor HMRC.
© Offshore Wind A big opportunity? GA-EMA Conferences 22 October 2014.
Potential hazards and risks in the offshore wind park development process in Poland Stefan Simon, CEO Green Energy World.
Prof. R. Shanthini 02 Feb 2013 Module 06 Renewable Energy (RE) Technologies & Impacts (continued) - Use of RE sources in electricity generation, in transport,
National Ocean Test Facility Hydraulics & Maritime Research Centre hmrc.ucc.ie Ray Alcorn Executive Director Current Commercial Projects in HMRC.
Cost trends for Offshore Wind - and a look at the resources David Milborrow
Regions for Economic Change Conference, Brussels, 7-8 March 07 The POWER project: Creating a North Sea Competence Network for Offshore.
DOE Peer Review May 10, 2006 Golden, CO Walt Musial Leader-Offshore Projects National Renewable Energy Laboratory Offshore Wind.
TU Delft Delft University of Technology 1BWEA Offshore Wind Conference London – Apr ‘02 Concerted Action on Offshore Wind Energy in Europe with acknowledgements.
SUPPLY CHAIN EVENT GLENOUTHER RENEWABLE ENERGY PARK FENWICK HOTEL, 10 TH SEPT 2015.
Dan Finch Moray Offshore Renewables Ltd. DELIVERING ROUND 3 Inverness 2nd February 2010 MORAY FIRTH OFFSHORE RENEWABLES Ltd.
258 Q: Where does tourism rank on the Scottish export list? A: 4th 257 Q: How much of Europe‘s offshore wind resources does Scotland have? A: 25% 256 Q:
Offshore Wind Farms An overview… UE VISION FOR % energetic efficiency -20 % greenhouse gas emissions 20 % of energy from renewable.
Wood Group – an overview A global market leader in: - services for the oil & gas and power generation markets - deepwater engineering - enhancement.
FOSSIL energies Coal, oil and natural gas take part to the French consumption of energy, as in the other developed countries.
To start… Recap questions. Why is wood considered only semi-renewable as a resource? If you cut it down faster than it grows stops being renewable. Where.
commercial in confidence tidal solutions company Nova Innovation Tidal Solutions Company SME Instrument Case Study 23 June 2015.
Building Offshore Wind in England: Centres of Offshore Renewable Engineering (C.O.R.E) British Embassy, Lisbon, 25th October 2012.
By Ryan Collins  Largest offshore wind farm is in Denmark  Dong Energy and Siemens Renewable Energy Provided the 91 turbines  Combined capacity.
Challenges for Wind Farm Development in Bulgaria: The Environmental Aspect Case study: Saint Nikola Wind Farm, Kavarna April 2009.
World Offshore Maintenance, Modifications & Operations Market Forecast World Offshore Maintenance, Modifications & Operations Market Forecast.
Powering Ahead Wind & Marine Power in the UK Institution of Civil Engineers | 2nd March, 2015 Maria McCaffery BSc (Jt. Hons), MBA, FRSA, MBE.
IMPROVED SEABED ANCHORING TECHNOLOGY Innovation Opportunity Identified at PROTTEC Retreat 26/28 October 2010 Jonathan Williams, Marine South East.
The Future Of Offshore Wind Power? Presentation By David Campbell.
H2020 Proposals LIFES 50 PLUS James Battensby – Technical Bid Manager 23 rd June 2015.
SME opportunities in the drive towards 2030 targets
Cathie Associates Offshore geoscience and geotechnical engineering consultancy An Introduction.
Wind technology: R&I perspective
1. INTRODUCTION TO LCA LCA METHODOLOGY
Renewables Capability Presentation All Energy May 2017
What are 5 ways you use energy? Brainstorm! What are 5 ways you use energy?
Transmission and Sub-Transmission Network India – Present and Future Rajesh Suri GE (T&D) India Ltd 8 November 2018.
Innovation and Offshore Renewables
DG MARE Study to support Impact Assessment on the Marine Knowledge 2020 Interim report Michael Munk Sørensen 11 december 2012 COWI POWERPOINT PRESENTATION.
Introduction Life cycle impacts to be considered for several LEANWIND innovations, including: foundation design vessel design novel O&M methods Initial.
NWF & Offshore Wind Power
INFRASTRUCTURE GAP ANALYSIS
Accelerating the Deployment of Offshore Renewable Energy Technologies - Project Proposal - Michael Paunescu Renewable and Electrical Energy Division.
Socio-economic impacts of Offshore Wind Farm (OWF)
Stakeholder Engagement
Presentation transcript:

TIDAL TURBINE FOUNDATION OPTIMISATION RAMBOLL ENERGY MOJO MARITIME Alternative title slide

INTRODUCING RAMBOLL Content slide, two columns with image Ramboll is a leading engineering, design and consultancy company founded in Denmark in 1945 Today, we employ more than 10,000 ambitious experts. Ramboll has a significant presence in Northern Europe, India, Russia and the Middle East With close to 200 offices in 20 countries we emphasise local expertise combined with a global knowledge-base.

INTRODUCING MOJO MARITIME Mojo provide Marine Operations Management and Consultancy Services to the Offshore Renewable Energy Sector. WINDWAVETIDE Content slide, two columns with image

TIDAL FOUNDATIONS Tidal foundations have huge challenges: uneven rocky seabeds, high current speeds, water turbulence and limited access. At present foundations are trials and so are not suitable for mass production. The next stage is a repeatable structure. Ramboll and mojomaritime are drawing on considerable experence in marine engineering from both oil and gas and offshore wind sectors to derive a solution. Content slide, two columns with image

CONTEXT OF PRESENTATION - FOUNDATION DESIGN AND INSTALLATION STUDY Working on a 10MW array in NE Scotland. Concept phase leading to reduction to 4 concepts. Review of each concept leading to elimination two (Gravity base and Duopod) and development of two (Monopile and Tripod). Tripod selected for detail design. Modelled and analysed ULS, ALS, FLS, SLS. Content slide, two columns with image

FOUNDATION DESIGN AND INSTALLATION “INTER-TWINED”

Must be considered together, foundation design impacts installation – a major project cost driver. It goes beyond installation - the design of foundation also impacts the cost of other interventions: Decommissioning · Cable connection · Turbine O&M Content slide, two columns with image

FOUNDATION OPTIONS Gravity Bases Moored Seabed Engagement Content slide, two columns with image Note that all of these require gravity at some stage!

GRAVITY BASES

GRAVITY BASE– STRUCTURAL CONSIDERATIONS 1 of 2 Option 1 Floating Gravity Base Option 2a Streamlined Modular GBA Option 2b Tripod Modular GBA Modular Gravity Sensitive to seabed slope, limit <10° Less technical risk than floating GB Lower potential for cost reduction at array scale More expensive vessels required Floating Gravity Sensitive to seabed slope, limit <10° Novel Concept = High Risk Minimal Vessel Requirements High CapEx investment Investment recovered for large array deployment

GRAVITY BASE– STRUCTURAL CONSIDERATIONS 2 of 2 Content slide, two columns with image Conclusion Substantial mass required - expensive Highest risk option Minimal vessel requirements

GRAVITY BASES – INSTALLATION CONSIDERATIONS Content slide, two columns with image Monoblock GBA –Attractive solution, marine operations simple and quick –Ideal for smaller scale devices and prototype deployment –BUT… unlikely to be long term foundation solution: –Limited in scalability –Little opportunity for cost reduction –Not applicable at sites with significant seabed slopes –Carbon footprint large for big lumps of steel/concrete –Long term reliability concerns Modular GBA Floating GBA 12

MOORED

MOORED – INSTALLATION CONSIDERATIONS Still requires fixation by GBA or seabed engagement Potential application at some sites Obvious O&M benefits But introduces some additional considerations: Dynamic export cable Mooring spread vs. array layout Dynamic platform Failure modes Needs Naval Architecture Content slide, two columns with image Hydra tidal moored device

SEABED ENGAGEMENT

MONOPILE – STRUCTURAL CONSIDERATIONS Design Conclusions Pile Diameter at upper limit of drilling capability Simple design and proven construction Fatigue governs so ULS utilisation ratios are low Content slide, two columns with image Feasible and well researched concept Material thickness / diameters governed by fatigue Low ULS/fatigue life ratios Simple Fabrication, weld automation No fatigue sensitive joints

DUOPOD – STRUCTURAL CONSIDERATIONS The Duopod benefits from bi- directional flow, resulting in more axial load path rather than bending in a monopile. Reduction in pile diameter. Can have problems with alignment to flow. Content slide, two columns with image

TRIPOD–STRUCTURAL CONSIDERATIONS Content slide, two columns with image Similar to Duopod in the manner that axial load paths are set up. Smaller pile diameter than monopile. Additional leg reduces flow direction problem presented by the Duopod. Weight reductions compared to monopile. Angles dependant on turbine rotor exclusion zone.

JACKET–STRUCTURAL CONSIDERATIONS Content slide, two columns with image Additional weight savings over monopile. Use in larger water depths. Majority of forces in axial manner. Reduction in pile diameter however multiple piles leading to installation complexity. Angles dependant on turbine rotor exclusion zone.

JACKUPS AND TOPSIDE DRILLING 1 of 2 Content slide, two columns with image –Topside drilling requires stable platform such as a Jack up barge. –BUT... successful application of Jack ups in tidal races is limited.

JACKUPS AND TOPSIDE DRILLING 2 of 2 Content slide, two columns with image –Jack ups in tidal races Out of class operation Possible stability/VIV issues Susceptible to weather downtime Depth limited Expensive day rates Restricted availability Topside drilling from a DP vessel or moored barge? Not likely. Bottom line: If “no” to jackups  it’s “no” to topside drilling.

SUBSEA DRILLING 1 of 3 Content slide, two columns with image Post-install piles Drilling within foot sleeves of jacket held temporarily in place under gravity. Smaller diameter percussive drilling demonstrated by TGL Pre-install pile(s) Drilling through template placed temporarily on seabed Monopile, Duopod, Tripod, Quadrapod etc. (or anchor piles for moored solutions) 22

SUBSEA DRILLING 2 of 3 Content slide, two columns with image 23

SUBSEA DRILLING 3 of 3 Content slide, two columns with image CONCEPT t = 0 DESIGN t = 3 months BUILT & TESTED t = 6 months

CONCLUSIONS

CONCEPT ELIMINATION PROCESS More detailed study of risk, cost and schedule for 4 options

TIDAL FOUNDATIONS Every tidal foundation is unique due to site requirements and device needs. For an optimum foundation which is cost effective and efficient, every aspect has to be individually analyised. Content slide, two columns with image

CONCLUSIONS – INSTALLATION 1 of 4 No “one size fits all” solution when considering various sites and devices: Content slide, two columns with image SITE DEPTHmay preclude the use of jackups SEABED CONDITIONSoverburden, voids and other drilling challenges SLOPEon bottom stability by gravity, levelling for drilling CURRENT VELOCITIESdon’t forget forces~v 2, best DP OCVs max 6kn WAVE EXPOSUREimpacts design and marine ops ENVIRONMENTALnever under-estimate these factors LOGISTICS/VESSEL AVAILABILITYmuddle through with a barge?

CONCLUSIONS – INSTALLATION 2 of 4 The cost (and technical ability) of intervention is the tidal energy sticking point Content slide, two columns with image

CONCLUSIONS – INSTALLATION 3 of 4 Content slide, two columns with image

CONCLUSIONS – INSTALLATION 4 of 4 Fit-for-purpose vessels are required if the tidal energy industry is to be economically viable. Not just lower day rates on: Charter Fuel Required crew Also compound savings from increased capability and shortened ops time: Fuel Personnel ROV/equipment hire Reduced weather exposure Content slide, two columns with image FUTURE VESSEL EXISTING DP OCV

THANK YOU Endslide.