Edward Downer Elementary School Playfield Renovation Status Update 10/14/14
Construction Manager:Gabriel Fortich (SGI) Inspector of Record:Man Wah Cheng Architect of Record:BCA Architects General Contractor: Maggiora & Ghilotti, Inc.
Fine grading to commence 10/20/14 -11/24/14 Sod Installation to commence on 10/27/14 – 10/31/14 Irrigation booster pump 11/6/14 – 11/13/14 Field complete 11/15/14
Project Duration:180 (Calendar Days) Notice To Proceed Date: May 19, 2014 Completion Date:Nov 15, 2014 Percent Complete: 90% Base Contract Amount:$563, Change Order to date:.1%