Buffalo Lake Dam Project Update date Meeting June 30, 2012.

Slides:



Advertisements
Similar presentations
Presentation Developed Prior to Input From 12/17/03 Adobe Collaborative Meeting Adobe Upper Reach 5 Conceptual Plan Issues December 9, 2003 Workshop.
Advertisements

County of Fairfax, Virginia Department of Transportation Board Four Year Transportation Plan 2012 to 2015 Board Transportation Committee November 29, 2011.
Fairfax County Board of Supervisors Transportation Sub-Committee Briefing Federal Highway Administration Eastern Federal Lands Highway Division Robert.
11 Inova Fair Oaks Hospital Master Facility Plan Zoning Applications Presentation March 2011.
I-95/Route 630 Interchange, Alternative E FUNDING (Cumulative) SCHEDULE JULY 2007 JULY 2008 JULY 2009 JULY 2010 JULY 2011 JULY 2012 JULY 2013 JULY 2007.
DEL-71 Project at the US 36/SR37 Interchange Round Table Meeting Ferzan M. Ahmed, P.E.- District 6 Deputy Director Steve Fellenger, P.E. – Project Manager.
Aubrey Green Community Meeting Issues and Opportunities Vandalism Safety Community Image Community Opportunities and Renewal Who is here and Why PW - Parks.
Fleurieu Regional Aquatic Centre Project summary October 2013 council meetings.
Rezoning Study -Community Forum- Thompson Middle School February 15, :30 – 7:30pm.
Neighborhood Meeting No.2 Golden Gate Bridge, Highway and Transportation Districts San Francisco Mid-Day Bus Parking Facility Contract No BT-1 March.
City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting November 19, 2012.
City of Olympia | Capital of Washington State Percival Landing Update Land Use Committee Meeting March 27, 2014.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER 1.
Grade Separation (GS-16) Project. Project Location - Bensenville N.
18 October 2012 WATERSHED Science & Engineering WEST Consultants Chehalis River Basin Hydraulic Modeling and Flood Relief Alternatives Evaluation.
Southside Flood Protection Red River Channel Extension Clay County Courthouse September 8, 2008.
Scoping Meeting Yuba Goldfields 200-Year Flood Protection Project Environmental Impact Report June 23, 2014.
NYS Department of Environmental Conservation Update on the Niagara River U.S. RAP Niagara River Remedial Action Plan Implementers Session April 10, 2013.
New N. Atlanta High School 4111 Northside Parkway Project Overview March 25, 2010 Facilities Services Department September 20, 2011.
Paula J. Trigg, County Engineer Public Works and Transportation Committee April 2, 2014 OVERVIEW | SOURCE OF PROJECTS PROPOSED HIGHWAY IMPROVEMENT.
Summary of Conceptual Design Site 3 Causeway Landfill Culvert Stabilization Marine Corps Recruit Depot Parris Island (CTO JM38) 19 August 2014.
John H. Kerr Dam and Reservoir John H. Kerr Dam and Reservoir U.S. Army Corps of Engineers Wilmington District.
1 Wastewater Capital Improvement Program (CIP) Large Users Meeting March 15, 2010.
West Contra Costa Unified School District Facilities Subcommittee Meeting March 11, 2014 State School Facility Program Seismic Funding Update.
Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee October 9, 2012.
City of St Helena Upper York Creek Ecosystem Restoration Project April 28, 2015 St. Helena City Council Meeting.
Borough of Madison Samson Avenue Reconstruction Engineering CY2012 Existing Conditions Underground Infrastructure Federal Aid SRTS Application Reconstruction.
JANUARY 9, 2002 SCAJAQUADA CORRIDOR STUDY Grant Street to Parkside Avenue City of Buffalo Fisher Associates Joseph Passonneau & Partners In Association.
U.S. 421 Bridge DES# Thursday, July 17, :30 p.m. Frankfort Community Public Library 208 West Clinton Street, Frankfort, IN.
US Army Corps of Engineers BUILDING STRONG ® FOLSOM DAM MODIFICATIONS APPROACH CHANNEL EIS/EIR Major Robert Dion and Cameron Sessions Project Managers.
South Side Red River Bridge Corridor Study Phase III Preliminary Geotechnical Study Phase IV New Alignment Alternatives Evaluation.
2 Lakeside Drive, Pawling NY 12564
Clinton Street Bridge over the Maumee River ODOT Project DEF April 1, 2015 Stakeholder’s Meeting.
Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011.
Lake Como Rehabilitation City of Bloomer Joseph M. Dorava, PE - Vierbicher Associates Bloomer Community Lake Association and Bloomer Rod and Gun Club Public.
Clinton Street Bridge over the Maumee River ODOT Project DEF May 14, 2015 Public Meeting.
Gaviota Beach Road – Transportation Division County Project Summer Crossing – Pre 1997 Located west of Highway 101 Access to Gaviota Beach and Hollister.
Alameda Creek Bridge Replacement Scoping Meeting March 4, 2014.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
Chapter 33 Dam Construction. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Give reasons why.
WELCOME! July 31, 2012 ODOT District July 31, 2012 PURPOSE OF TONIGHT’S MEETING Introduce the project –Reconstruct I-75.
Heath Delzell – Engineering Bureau IDNR Engineering Progress to Date and Timeline for Project Completion Design and Construction Obstacles.
Bijou Erosion Control Project Project Kickoff TAC Meeting May 4, 2007 City of South Lake Tahoe ENTRIX, Inc. California Tahoe Conservancy.
Riverside County Flood Control and Water Conservation District Murrieta Creek Flood Control, Environmental Restoration and Recreation Project June 2006.
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Public Information Meeting.
US Army Corps of Engineers BUILDING STRONG ® Understanding Sedimentation and Land Use Cover Relationships in the Lake Sidney Lanier Watershed Russell A.
Millbrook Dam Environmental Assessment Study Dan Marinigh CAO/Secretary-Treasurer Otonabee Region Conservation Authority October 20, 2015 Otonabee Conservation.
December 3, 2015 TOWN OF MILLBURY DPW, MA Robert McNeil, P.E., Director PARE CORPORATION, FOXBORO, MA Allen R. Orsi, P.E., Managing Engineer This project.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
South/West Corridor Transit Improvements ZARZAMORA AND MILITARY PRIMO BRT PROJECTS ENVIRONMENTAL AND PRELIMINARY DESIGN PHASE September 9, 2014 VIA Community.
APPLICATION NO LEVEE DISTRICT No. 1 Of SUTTER COUNTY STAR BEND SETBACK LEVEE SUTTER COUNTY April 17, 2009.
Update to Proposition 1E – Early Implementation Project (EIP) Application and Local Share Reclamation Board Sub-Committee Meeting September 11, 2007.
Harbor Walk Project Phase 1 Includes: Seawall Replacement Pedestrian Promenade Sidewalk Connection Small Boat Launch Parking Restroom Facility FDOT Funding.
Alameda Creek Watershed San Francisco Public Utilities Commission October 27, 2009.
PORT OF TACOMA. Contract Increase & Award Pier 7 Structural Repairs Request authorization to expand the scope of existing A/E Contract No and.
Wastewater Treatment Plant No. 2 Construction Contract City Council Workshop February 9, 2016.
West Sacramento Area Flood Control Agency November 10, 2011 Update on Current Levee Construction Projects and on the Southport Sacramento River Levee Early.
Carolina North Carolina North Annual Report for Chapel Hill Town Hall September 29, 2010.
PAC Meeting July 2, Agenda  Introductions and thanks  Project to date  Next steps  Questions.
Technical Issues Design Status Due Diligence Materials Tony DeVito, Project Director Jan. 28, 2016 I-70 East Project.
Big Cypress Basin Capital Project Update Jeffrey Kivett, P.E., Director Operations, Engineering and Construction Division Jeffrey Kivett, P.E., Director.
MASON PUBLIC SCHOOLS Bond Committee Meeting #1 August 9, 2016.
Potholes Supplemental Feed Route Project
Issaquah-Fall City Road
SE 12th Street Roadway Improvements February 8, 2005.
2040 Long Range Transportation Plan Update
Facilities Projects Update
Walker Street Reconstruction Project 25% Design Public Hearing
Sacramento Environmental Commission January 2019.
2015 January February March April May June July August September
Presentation transcript:

Buffalo Lake Dam Project Update date Meeting June 30, 2012

Purpose of this Meeting Provide update on status of the project Describe the timeline for the project Questions and Answers

SITE OVERVIEW North Buffalo Lake Existing Primary Spillway Existing Lock and Gates Existing Boat Launch and Parking Existing Embankment

How Did We Get here Primary cause - Flood of June 2008 and re- routing of traffic over the “Dredge Bank”. DNR orders the road closed and to fix, replace or remove dam by The “Dredge Bank “ was constructed in 1855

How Did We Get Here alternatives evaluation - AECOM study January 22, 2011 public presentation State Bldg. Commission Approval - April 2011 Included in state FY Budget Mead and Hunt contracted June 2012

Condition of Existing Structures and Embankment Present Conceptual Alternatives and Range of Costs Conceptual Public Use and Recreation Improvements Discuss Buffalo Lake Drawdown and Potential Construction Impacts Questions January 22, 2011 Meeting Summary

Condition of Lock and Sluice Gates The lock’s stone walls are generally in good condition. Voids in the lock floor were observed by the diver. Upstream face of sluice gates. Gates are in fair condition. Corrosion and some pitting is present.

Condition of Primary Spillway Downstream surface of concrete capped spillway. Generally in good condition. Note additional flash boards placed for dive inspection. Left Abutment Wall - Downstream Constructed of stone masonry. Stonework is failing. Wall is in poor condition.

Condition of Primary Spillway Right Abutment Wall Better condition than left wall. Note steel tieback whalers. Tuck pointing of masonry joints. Right Abutment Wall Erosion of lower joints.

Condition of Embankment South Portion of Embankment Looking West Upstream slope very steep Rip rap cover is sparse with no bedding to prevent erosion. North Portion of Embankment Looking South Rip rap cover is sparse with no bedding to prevent erosion.

Condition of Embankment Downstream Slope of Embankment in South Portion. Steel probe pushed in 4 feet by hand. Upper zone of embankment is very loose. South Portion of Embankment Large sinkhole repaired in 2008.

WDNR Conclusions and Preferred Options Montello Dam FeaturePreferred OptionRange of Costs Sluice Gates and Lock Chamber Replace Existing Gates at Current Location (B) $400,000 - $450,000 Primary SpillwayReplace Entire Spillway and Include a Fish Passage Structure (B) $2.5 - $3.0 Million EmbankmentOption D: Two-way Road and Walking Path from North End to Existing Boat Launch Location Pedestrian / Bike Path on South Half (D) $5.0 - $6.0 Million Public Use and Recreation Enhancements Launch, Piers, Wharfs, Benches, Lights, Portage $350,000 - $400,000 Project Total $ Million The preferred options identified below may change based on funding, public input, and final design.

WDNR Conclusions and Preferred Options (Continued) What to Expect: Most Likely Need Full Drawdown and a Partial Breech of the Primary Spillway Best Case – Begin Drawdown After Labor Day – Finish Construction the Following Summer or Fall Best Case – Begin in 2012 – Could be 2013 Selected Options Should Allow Concurrent Construction of Gates, Spillway, and Embankment

Project Components Install Slurry Cutoff Wall Embankment Stabilization Spillway Replacement Replace Sluice Gates Fish Passage Boat Landing Public Use Facilities

Projected Schedule – per Mead & Hunt and DNR Contract Signed - June 2012 Begin Drawdown – September 4, 2012 Provide Review Documents – September 2012 Provide Final Design Documents – January 2013 Advertise for Bid – February 2013 Bid Date – March 2013 Contract Award & Construction Start - May 2013 Drawdown Dependent Construction Complete, Refill Buffalo Lake – May 2014 Substantial Completion – November 2014 Project Close Out – December 2014

Next Steps June 30, public update meeting August 18 - meet with Lake District and EA comment period on drawdown Late September - public meeting on proposed final design