Project Management Lecture 16 Project management involves estimating the length of time to complete a project Once a project has been undertaken then a.

Slides:



Advertisements
Similar presentations
McGraw-Hill/Irwin Copyright © 2013 by The McGraw-Hill Companies, Inc. All rights reserved. A PowerPoint Presentation Package to Accompany Applied Statistics.
Advertisements

SADC Course in Statistics Excel for statistics Module B2, Session 11.
1 Bus 1040 Project Management Week 5 Bus 1040 Project Management Week 5 Agenda: Web presentations A Student handout Scheduling lecture, Network Diagrams,
Credit Risk Plus November 15, 2010 By: A V Vedpuriswar.
Systems Eng. Lecture 2 Begin Reading Chapter , Problems 1, 3, 5 by Wednesday, January 24, 2001.
CP Chapter 4 Schedule Planning.
Chapter 17 Project Management McGraw-Hill/Irwin
Advanced Project Schedule Risk Analysis
Simulation - An Introduction Simulation:- The technique of imitating the behaviour of some situation or system (economic, military, mechanical, etc.) by.
Modeling and Simulation By Lecturer: Nada Ahmed. Introduction to simulation and Modeling.
1 Random Sampling - Random Samples. 2 Why do we need Random Samples? Many business applications -We will have a random variable X such that the probability.
Spreadsheets in Finance and Forecasting Week 4: Using Formulae.
Brief Review –Forecasting for 3 weeks –Simulation Motivation for building simulation models Steps for developing simulation models Stochastic variables.
ICS 442 Software Project Management
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
Materials for Lecture 11 Chapters 3 and 6 Chapter 16 Section 4.0 and 5.0 Lecture 11 Pseudo Random LHC.xls Lecture 11 Validation Tests.xls Next 4 slides.
SW Project Management Project Schedule and Budget
©2001 Plan B Systems Inc. PBSi Quantitative Cost/Schedule Risk Analysis.
Outline/Coverage Terms for reference Introduction
Engineering Economic Analysis Canadian Edition
Project Risk Management
Contemporary Engineering Economics, 4 th edition, © 2007 Risk Simulation Lecture No. 49 Chapter 12 Contemporary Engineering Economics Copyright, © 2006.
Chapter 14 Simulation. Monte Carlo Process Statistical Analysis of Simulation Results Verification of the Simulation Model Computer Simulation with Excel.
Project Time Management
AGEC 622 Mission is prepare you for a job in business Have you ever made a price forecast? How much confidence did you place on your forecast? Was it correct?
Monté Carlo Simulation MGS 3100 – Chapter 9. Simulation Defined A computer-based model used to run experiments on a real system.  Typically done on a.
ERT461 BIOSYSTEMS ENGINEERING DESIGN 1 ERT424 BIOPROCESS PLANT DESIGN 1.
University of Sunderland CIFM02 Unit 3 COMM02 Project Evaluation Unit 3.
Introduction to Monte-carlo Analysis for software development
S.Cholette, based on McGraw-Hill/Irwin Managing Risk.
The AIE Monte Carlo Tool The AIE Monte Carlo tool is an Excel spreadsheet and a set of supporting macros. It is the main tool used in AIE analysis of a.
© 2007 Pearson Education Simulation Supplement B.
About the Exam No cheat sheet Bring a calculator.
Materials for Lecture 08 Chapters 4 and 5 Chapter 16 Sections Lecture 08 Bernoulli & Empirical.xls Lecture 08 Normality Test.xls Lecture 08 Parameter.
Engineering Economic Analysis Canadian Edition
“WHY ARE PROJECTS ALWAYS LATE?” (“and what can the Project Manager DO about that?) Craig Henderson, MBA, PMP ARVEST Bank Operations.
AMERICA’S ARMY: THE STRENGTH OF THE NATION Mort Anvari 1 Cost Risk and Uncertainty Analysis MORS Special Meeting | September.
Materials for Lecture 08 Chapters 4 and 5 Chapter 16 Sections Lecture 08 Bernoulli.xlsx Lecture 08 Normality Test.xls Lecture 08 Simulation Model.
Outline of Chapter 9: Using Simulation to Solve Decision Problems Real world decisions are often too complex to be analyzed effectively using influence.
Calculating Project Schedule Risk Using Monte Carlo Simulation Curt Blair, PMP.
Value at Risk Chapter 16. The Question Being Asked in VaR “What loss level is such that we are X % confident it will not be exceeded in N business days?”
VMcG 2/11/02 Critical Chain as an Extension to CPM Vincent McGevna, PMP February 11, 2002
Chapter 7 PERT Project Management for Business, Engineering, and Technology.
FIN 614: Financial Management Larry Schrenk, Instructor.
Project Management Lecture 22 Readings Chapter 14 Lecture 22 Short Project Management.XLSX Lecture 22 Project Management.XLSX Lecture 22 Event Management.XLSX.
Change management control Sources of Change  Project scope changes  Implementation of contingency plans  Improvement changes ISE Ch. 6 1.
DECISION MODELING WITH MICROSOFT EXCEL Chapter 14 Copyright 2001 Prentice Hall Publishers and Ardith E. Baker Part 3 andand PERT CPM.
 Delay in project implementation invariably results in cost- overrun.  Delayed project implementation means delay in getting return on investments made.
Materials for Lecture 19 Readings Chapter 14
Simulations. Simulations – What’s That? Simulations are used to solve probability problems when it is difficult to calculate the answer theoretically.
Genetic Algorithm Dr. Md. Al-amin Bhuiyan Professor, Dept. of CSE Jahangirnagar University.
Unit 2 Time Management Prepared by: Prof. Seemaah Keddar.
Orlando Critical Chain as an Extension to C P M Orlando A. Moreno, PMP February,
Project Management Lecture 22 Readings Chapter 14 Lecture 22 Short Project Management.XLSX Lecture 22 Project Management.XLSX Lecture 22 Event Management.XLSX.
Uncertainty and Retirement Planning Lecture for FIN 352 Professor Dow CSUN 2016.
AGB 260: Agribusiness Data Literacy
Expanded Short multiplication How it should look (for 45 X 6)
PROJECT MANAGEMENT.
Project Management Lecture 22
Monte Carlo Simulation Random Number Generation
ANALYTICAL METHODS IN MAINTENANCE
Prepared by Lloyd R. Jaisingh
2nd Task of Your Project „All you have to decide, is what to do with the time that is given to you.“ J.R.R. Tollkin Prof. Dr. Christian Bleis 1 Interaktionskompetenz.
ENGINEERING MANAGEMENT (GE 404)
Final Grade Averages Weighted Averages.
ENGINEERING MANAGEMENT (GE 404)
By Harsh Tiwari.
Performing the Runs Test Using SPSS
Agile Project Management and Quantitative Risk Analysis
Simulation Supplement B.
Presentation transcript:

Project Management Lecture 16 Project management involves estimating the length of time to complete a project Once a project has been undertaken then a project manager is responsible for carrying out the project on the assigned time table How do the managers establish a time schedule –Generally based on average length of time for each component –Average length of time based on past experience Length of time to complete each step is a random variable

Materials for Lecture 16 Readings Chapter 14 Lecture 16 Short Project Management.XLSX Lecture 16 Project Management.XLSX Lecture 16 Event Management.XLSX Lecture 16 Have Some Fun.XLSX

Project Management Who does project management? –Engineers, managers, accountants –They calculate number of days to completion Generally do not incorporate risk Benefits of incorporating risk into project management analysis –Assign a probability to number of days until project completion –Assign a probability to getting a project done in a fixed timeframe

Project Management KOV for a project management problem is: How long will it take? There is no final answer until project is completed Answer is an unknown PDF of days, weeks, or months to completion Simulation provides a methodology for estimating unknown PDFs Formulate the problem as a Monte Carlo simulation problem

Project Management Model formulation –KOV is “Number of Days” to completion –Identify each task (step) for project –Specify order of each task for the project Identify bottlenecks where tasks will wait on precious stages –Determine the PDFs for number of days (or weeks, months, etc.) to complete each task Rely on experience from past jobs Depend on experts for time to complete each task PDF may be dependent on resources available

Project Management Critical to identify the order of the tasks and their linkages (dependencies), for example: –Task 10 starts after Tasks 5 and 8 are completed –Task 11 starts after Task 10 is completed Thus, Task 5 or 8 could hold up the whole project –If analysis shows 5 is the bottleneck is it worth investing more resources in Task 5 to get the project completed earlier?

Project Management Create a simple Project Network Diagram to summarize the order of tasks Drawn it in Excel with simple arrows and boxes Network diagram shows potential bottlenecks

Project Management Tasks 1-6, 2 and 3 wait on 1, 4 waits on 2, 5 waits on 3 and 4, last task (6) waits on 5 Assumes next task starts day after it predecessor ends Days in column C are GRKS() stochastic

Project Management Finite limit to complete the project is 45 days P(Days>45)=?

Spreadsheet of a Project Management Analysis

Project Management Expanded I like to add a second KOV – Cost We know cost of a project is stochastic So project management model can simulate PDFs for days and cost In the example $/day costs for each task are multiplied by stochastic days

Event Planner Event planner KOVs –Number of days ahead to start planning an event –Cost of the event Research application KOVs –Time to complete a research project –Cost of project Wedding planner –Probability of being ready on time –Cost of the event Banquet planner

Event Planner