CONSTRUCTION DEFECT RECOVERY FROM SURETY: THE SINKING BUILDING TALE PRESENTATION AT DES CLIENT WORKSHOP OCTOBER 8, 2014 BOB BOURG, DES CLAIMS AND DISPUTES.

Slides:



Advertisements
Similar presentations
Installation Law Briefing
Advertisements

The Unit Owners Association of the Madison, A Condominium Building Revitalization (Work Completed & Upcoming Work)
Home with an Underground Heating Oil Tank (UST) Solutions for your Leaking Heating Oil Tank.
CASTING A CONCRETE WALL
Summary of Conceptual Design Site 3 Causeway Landfill Culvert Stabilization Marine Corps Recruit Depot Parris Island (CTO JM38) 19 August 2014.
Chp12- Footings.
MNM Fatal Falling Material Accident Falling Material Accident August 17, 2012 (Florida) August 17, 2012 (Florida) Victim Recovered September 4,
Click to continue…. Railroad Track wetland Image Date: December 2003.
Christchurch Town Hall for Performing Arts
EDT Foundation Plan Design1 Weekend Cabin Retreat Project Foundations Sacramento City College EDT 300.
Failure Case Study of Construction at a Solid Waste Site K. Madhavan, Ph.D., P.E., Dept. of Civil & Env. Engineering Christian Brothers University Memphis,
Part1: Shollow foundations
Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee October 9, 2012.
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
Christchurch Town Hall November 27th, Introduction What happened –Settlement –Lateral Spread –Measurements Analysis –Current capacity Repair and.
Foundation Systems.
Foundations. Foundation supports weight of structure –Includes soil and rock under foundation –Building construction described by foundation type Slab.
The Good, the Bad, and the Ugly 2 May 2008 Sacramento, CA Alan Macnab
 Embankment Construction – LOTs  What is the maximum length of a LOT? Mainline pavement lanes, turn lanes, ramps, parking lots, concrete box.
SOIL, GEOTECHNICAL ENGINEERING AND FOUNDATION ENGINEERING
Floor Systems and Foundation Support
Chapter 18 Foundations.
Foundation Engineering CE 483
TRENCHLESS TECHNOLOGY
Chapter 2b Foundations Shallow & Deep Foundations.
1Furmanite Confidential - 1/9/04 Motor and Pump Base Foundational Repair.
1 August 12, 2014 Surety Risk Assessment Utility Pipeline Failure Case History – Tyndall, SD Presented by: American Concrete Pipe Association Scott Hofer.
Construction Defect Mitigation Construction Cost Recovery Construction Litigation Consultants, LLC Jerry Peck Slide 1 of 12 slides / Total.
Roof Terms Span –Distance across the building. Roof Terms Run –1/2 the distance across the building (1/2 span distance)
Residential Construction Unit 2- Site Work and Concrete Mr. Todzia.
STATE WIDE SIGN GUIDE This guide will demonstrate various sign mounting products and procedures for construction and maintenance.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Earls Mill Road Retaining Wall Ground Anchors and Strengthening.
Chapter 32 Floor Systems and Foundation Support. 2 Links for Chapter 32 Slab Construction Reinforcing Concrete Crawl Spaces.
Specification & Quantities Estimating Lecturer Maha Muhaisen College of Applied Engineering& Urban Planning.
FRAMING SEMINARS 2012 PRESENTED BY KW ENGINEERING 1.
Roof Terms Span –Distance across the building. Roof Terms Run –1/2 the distance across the building (1/2 span distance)
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Geotechnical Conditions Tom Joos Civil/Structural Engineer BNL Plant Engineering.
Foundation Loads Dead Load Live Load Wind Load
Engineering Presentation. Basic Soil Mechanics Soil type classification Gravel, sand, silt, clay Soil strength classification Granular soils (sand and.
COFFERDAMS.
SANKALCHAND PATEL COLLEGE OF ENGINEERING,
Foundation Failure. Foundation movement may result from a wide range of factors, which can include: Shrinking or swelling of clays caused by changes in.
Mahatma Gandhi Institute of Technical Education & Research Centre
Understand foundation design and construction
Foundation types and uses
CONREPNET Performance based rehabilitation of reinforced concrete structures Members workshop – London – 24 & 25 April 2006 CE marking of concrete repair.
Floor Systems and Foundation Support
Riprap Installation Construction Inspection for Field Office Activities Will use Riprap Gradation and Riprap Subgrade Problems from Class Problem Section.
Footings & Foundation Prepared By: (Vanani Sanket) Department of Civil Engineering B.H.Gardi College of Engineering & Technology.
GEOTECHNICAL CONSIDERATIONS IN CONSTRUCTION DEFECT LITIGATION
Leads Institute of Technology & Engineering
P3 (Preventive Pile Protection)
CAD-Architecture Inst: Mr. Johnston Logan High School
Foundation – jay Desai.
FOOTING AND FOUNDATION
City of San Jacinto 7th Street Pavement Repairs
Construction/Renovation/Maintenance
SOIL, GEOTECHNICAL ENGINEERING AND FOUNDATION ENGINEERING
Design of Reinforced Concrete Foundations
Arch205 Materials and building construction 1 foundation
Foundations in Low-Rise Construction (up to 3 floors)
CONSTRUCTION METHODS & TECHNOLOGY
4th Annual Construction Law Summit
Arch205 building construction foundation
Building Construction I Sofia Sebastian 1
Component or parts of a building
What to Expect When You’re Inspected
Chapter 7 Foundation Systems.
Steps To Prepare Site For Site Work Construction Calhoun GA.
Presentation transcript:

CONSTRUCTION DEFECT RECOVERY FROM SURETY: THE SINKING BUILDING TALE PRESENTATION AT DES CLIENT WORKSHOP OCTOBER 8, 2014 BOB BOURG, DES CLAIMS AND DISPUTES MANAGER LINDA SULLIVAN-COLGLAZIER, ASSISTANT ATTORNEY GENERAL

BACKGROUND – PROBLEM DISCOVERED $3,345,000 for Building Replacement Project Final Acceptance October 2007 Early 2009, the building had a major sanitary sewer line blockage – cleared April 2010 another major sanitary sewer line blockage Video camera inspection – shows break in line Arrangements made to repair the break in the sewer line during the college’s June break

BACKGROUND – BIG PROBLEM DISCOVERED June when sewer line exposed the magnitude of the problem was fully determined To uncover the sewer pipe for repair the existing slab ‑ on ‑ grade was cut open and removed After the slab ‑ on ‑ grade was removed, it was evident that the concrete slab ‑ on ‑ grade had separated from the gravel sub ‑ grade.

REALLY BIG PROBLEM DISCOVERED There had been significant soil settling in the area surrounding two footings of the building and the broken sewer line Reinforced concrete pad footing had differentially settled Non ‑ shrink grout pad on top of the concrete footings measured up to 4 inches thick (should be only 1.5 inches) Concrete when poured had spread into void between slab ‑ on ‑ grade and gravel sub ‑ grade several inches.

AREA OF SETTLEMENT (IN RED)

OPINION OF THE STRUCTURAL ENGINEERING AND GEOTECHNICAL CONSULTANTS: Pipe failure and footing settling was the result of: non ‑ consolidated, loose gravel fill material in the area beneath the footings majority of the settling occurred during construction sometime between the pouring of the footings and when the slab ‑ on ‑ grade was placed, probably when the steel superstructure was erected Footings needed to be stabilized with helical anchors before the repair work could be done

THE FIX To remediate the problems and stabilize the building, the structural engineering consultant recommended: Stabilize the existing footing supporting the steel tube columns with helical anchors; Fill the voids below the bottom of the existing slab ‑ on ‑ grade with URETEC soil stabilization; and Stabilize the non ‑ consolidated material to prevent further settling below the bottom of the existing sewer pipe by injecting URETEC along the length of the exposed pipe.

THE DEMAND “The state is seeking to recover its costs and expenses for investigation, design, and construction related to repairs on Joan Stout Hall on the Clark College campus. The repairs were necessary to fix damage to a sewer pipe and prevent further settling under two footings due to defective construction during the original building construction. The amount the state is seeking to recover is $484, for the repairs, plus any additional costs incurred.”

SO WHAT THE HECK HAPPENED? AND WHEN? What we first thought What we found out What the experts were able to show

WHAT SHOULD HAVE HAPPENED - CONSTRUCTION DOCUMENTS Original construction documents called for removal of existing columns and footings down to solid original ground Had the contractor constructed the building according to the original construction documents, the original columns and footing would have been removed and all soil down to the solid original ground would have been removed Specifications required excavated area to be backfilled with structural fill Area directly beneath the two footings would have been compacted structural fill on top of solid original ground Settlement would not have been a problem.

WHAT COULD HAVE HAPPENED - MODIFICATION During the excavation of the footings, GC requested modification of requirement to remove the entire existing column and footing Instead GC requested approval to cut the existing column off and leave the footing and remaining column in place Approval with specific direction on how this was to be done was given to GC by architect in an “Existing foundation must be removed to a point minimum 6’-0” below the bottom of the new footing and backfilled with structural fill.” If built per the modified specifications, area directly beneath the two footings would have been more than 6’ of compacted structural fill. This would have minimized settlement and it would not have been a problem.

WHAT HAPPENED All of the evidence clearly demonstrated that GC and sub did not construct the building according to the modification directive given by the architect: Visual inspections and subsurface testing showed loose fill, not the required compacted structural fill beneath the footings GC and the excavation subcontractor stated there was no excavation below grade during the building construction in the area where the two footings settled (They stated there were no old columns or footings there) GC did not properly construct the building and as a result the footings settled breaking sewer pipe and threatening building’s structural integrity

HERE ARE THE COLUMNS INSIDE OLD BUILDING

WHAT WERE THE RISKS OF LITIGATION?

END RESULT OF MEDIATION WITH SURETY Settlement between the State and Contractor. As consideration for the mutual promises contained herein, Contractor, through various insurance carriers (“Participating Insurers”), shall pay to the State the sum of : Three Hundred Fifty Thousand and No/100 Dollars ($350,000.00), made payable to “Clark College.”

THE END Any questions?