Funding UKLink Process changes (User Pays). 2 Purpose of Presentation  Review of User Pays  Principles  Application to date  National Grid NTS observations.

Slides:



Advertisements
Similar presentations
UK Gas Entry Regime – Review of existing Interruptible Arrangements & Potential Reforms for this Winter.
Advertisements

Code Governance Review: WWU views on potential changes to UNC and the Modification Panel Simon Trivella – 30 th March 2010 Governance Workstream.
Review of NTS entry charge setting arrangements - IA 1 July 2010.
Third Energy Package for Change of Supplier 2009/73/EC.
Non-code User Pays. 2 What we will cover Background Current Services Governance Arrangements What is working well What is not working as well.
Project Nexus Next Steps Xoserve/Large GT View – 6 December 2011.
Mod 232 Anna Taylor Pricing Manager. 1 Mod 232 An alternative methodology for allocating unidentified energy Currently allocated by RbD entirely in SSP.
Commercial Arrangements For Gas Quality Service – Process UNC Transmission Workstream 23 rd April 2007.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Long Term Entry Capacity & User Commitment Transmission Workstream 7 th August 2008.
UNC Modification Proposal 0116 Reform of the NTS Offtake Arrangements Transmission Workstream 5 th October 2006.
ADD PRESENTATION TITLE HERE (GO TO: VIEW / MASTER / SLIDE MASTER TO AMEND) ADD PRESENTER’S NAME HERE / ADD DATE HERE © Copyright EDF Energy. All rights.
Entry Capacity Release Methodology Statement Transmission Workstream, 4 th May 2006.
Capacity trade and transfer mechanism and the next AMSEC auction Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 9 May 2007.
Industry Dialogue on xoserve Services Progress Report for Ofgem 5 th December 2006.
UNC Modification Proposal Daily Metered Elective Action 005: User Pays Proposal Simon Trivella – 4 th November 2008 Development Work Group 0224.
Review of the UNC Post-emergency Arrangements Workshop 1 March 2009.
UNC Modification 0213 – User Pays Governance Arrangements Simon Trivella – 19 th June 2008 Governance Workstream.
Transfers and Trades Transmission Workstream
Mod 0333: Update of default System Marginal Prices Review Group August 2010 Transmission Workstream 07/10/2010.
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Overview Gemini 2008 Release (Summer). Gemini Release 2008 (Summer) In response to a request from National Grid Transmission a number of changes have.
Assignment of NTS Entry Capacity Transmission Workstream 06 November 2008.
Delivering Connections and Capacity RIIO-T1 and associated commercial changes - Summary June 7th 2012.
Governance and Charging Methodology for User Pays Services 10 th January 2007.
ROM and DCA. Scene setting Our house Our aspiration for our house Our project manager Us.
Force Majeure - Capacity Transmission Workstream 2 July 2009.
Modification proposal 0073 ‘Revision to the Notice Period regarding the implementation of changes to Transportation charges’ Transmission Workstream, 2.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Open letter on Development of the regime ahead of winter 2007/8 Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 28 June 2007.
Proposed DN Pensions Deficit Charge Transmission Workstream 2 November 2006.
Moving the QSEC and AMSEC Auctions Update. 2  Presented proposal at October Workstream  Questions / suggestions received, mainly around  Over & Under.
Initial Thoughts on the Release of Non Obligated NTS System Entry Capacity Transmission Workstream 3 rd April 2008.
Références, date, lieu Xoserve Service Model – Shipper’s View Total Gas and Power Ltd Gaz de France ESS.
11 User Pays User Committee 14th September Agenda  Minutes & Actions from previous meeting  Agency Charging Statement Update  Change Management.
Assignment of NTS Entry Capacity Transmission Workstream 02 July 2009.
11 User Pays User Committee 16th February Agenda  Minutes & Actions from previous meeting  Agency Charging Statement Update  Change Management.
Emergency Cashout Prices and Emergency Curtailment Quantity (ECQ) Adjustment Ritchard Hewitt Gas Code Development Manager.
Code Governance Review UNC Modification Proposals Beverley Viney - National Grid NTS.
Transmission workstream 6 April Overview of TPCR Third Consultation UNC transmission workstream – 6 April Mark Feather.
Agency Charging Statement Overview of Consultation 11 th February 2008.
Facilitating Release of Non-obligated Entry Capacity Draft – for discussion purposes only 22 November 2007.
Project Nexus : Funding Arrangements Joel Martin - 30 April 2009.
UNC0376A - Increased Choice when applying for NTS Exit Capacity – User Pays initial thoughts Review Group August 2010 Transmission Workstream 01.
Mod Entry Capacity Transfers Transmission Work Stream, 5 April 2007.
Assignment of NTS Entry Capacity Review Group 221, 10th December 2008.
MOD Proposal 0224 Facilitating the use of AMR in the Daily Metered Elective Regime 28 May 2009 Code User Pays Services.
ADD PRESENTATION TITLE HERE (GO TO: VIEW / MASTER / SLIDE MASTER TO AMEND) ADD PRESENTER’S NAME HERE / ADD DATE HERE © Copyright EDF Energy. All rights.
Industry Dialogue on xoserve Services 14 th September 2007.
PN UNC Workgroup Invoicing 10 th January Objectives of the Workgroups To determine business principles for future Invoicing processes –Consider/review.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Development Modification Proposal: Introduction of an Inter-day Linepack Product Review Group August 2010 Transmission Workstream 07/10/2010.
DN Interruption Reform Transmission Workstream Mark Freeman 5 th April 2007.
User Pays User Committee 12th November 2013
User Pays Funding – Potential Licence Mechanism
Code Governance Review UNC Modification Proposals
Transmission Planning Code
Introduction of Code Contingency Guidelines Document
UNC Trader User – Licence obligations
Assignment Workshop 2 16th September 09, Solihull.
Exit Capacity Substitution and Revision
Topic raised at July 2009 Distribution Workstream
UNC Modification Proposal 0385 Inclusion of DNOs as Users in User Pays Arrangements Phil Lucas 7 June 2011.
Introduction of Code Contingency Guidelines Document
Options for the Development of a Demand Side Response Mechanism
User Pays Principles and Governance
CAM: Next Steps UNC Transmission Workgroup Lisa Martin 9 January 2014.
Commercial Arrangements For Gas Quality Service – Introduction
Transmission Workstream 05 November 2009
Presentation transcript:

Funding UKLink Process changes (User Pays)

2 Purpose of Presentation  Review of User Pays  Principles  Application to date  National Grid NTS observations for discussion  Views on next steps

3 User Pays - the story so far NTS PCRGDPCRACSMod 0213 The concept of “User Pays” applies solely to those services provided by xoserve (i.e. UK Link systems incl. Gemini), the Transporters Agent  Concept was first discussed in October 2006  User Pays principles developed over a number of years and its application is based on a number of key developments

4 NTS Price Control Review – Costs of ongoing Industry Framework Changes  Transmission Price Control Review (TPCR) process  Ofgem set NGG Transmission’s price control allowance for xoserve funding for 2007/08 only.  GDPCR  Ofgem set funding from 1 April 2008 until 31 Mar 2012 and divided costs in to two categories.  Ofgem suggested future Gemini system development costs should be paid for by parties that value the change the greatest (8.14 GDPCR) Exit Reform and Entry Capacity Arrangements Fixed allowance provided Future developments Funded by those who value it most xoserve Funding

5 Gas Distribution Price Control Review (GDPCR)  User Pays Implementation Group (UPIG) set up in Sept  Examined how to implement the Ofgem GDPCR proposals to introduce "User Pays" arrangements for defined services (not future change)  The User Pays arrangements proposed that xoserve's services be split between:  “Core” / PCR proposed services, to be funded through the Transporters’ price control, and  "user pays" services which would be funded by those users who most value them, shippers, transporters or both.  User pays services were further classified  “Code" services, those already detailed within the UNC - continue to be governed by the existing UNC arrangements  “Non-code" services - provided via a contract between xoserve and the customer and not detailed in the UNC. Users are charged for the non-code services they use by xoserve

6 Agency Charging Statement (ACS)  GDPCR introduced changes to SSC A15 (“Agency”) of the Transporters' licence  Obliges Transporters to produce and publish an Agency Charging Statement (ACS)  ACS  Contains the scope of core and user pays services, the charging methodology for user pays services and the charges themselves  Proposed changes to the ACS must be sent to Ofgem for a minimum period of 28 days in accordance with A15  Charges ‘as far as reasonably practicable, reflect the costs of providing the service’ charges can include xoserve margin (6%)  Mod 0188 introduced concept of ACS into UNC

7 UNC Modification Proposal 0213V: “Introduction of User Pays Governance Arrangements into the UNC” EDF Energy raised UNC Modification Proposal 0213V as a means of revising the UNC Mod Process, so that a Mod must state if it contains a User Pays element All proposals to say whether User Pays or not if Users Pay it should state:  Who should fund the xoserve costs, e.g. transporters or shippers, and in what proportion, e.g. transporters 50%, shippers 50%  How costs should be apportioned - transactional basis, or by market share, or per new report etc. When a User Pays proposal is sent to Consultation  GTs should provide a high level cost estimate (ROM) with the draft Mod report A more robust cost estimate can be requested by the Modification Panel Assumption is that all User Pays modifications will have a ROM unless the Panel determine otherwise. (Business Rule 9 of 0213V)  User Pays costs should be included in the FMR and an accompanying revised ACS A direction from the Authority to implement the Modification Proposal would also be deemed to be a non-veto of the ACS amendment.

8 Detailed Cost Analysis (DCA) Who can request a DCA?  Modification Panel  Gas & Electricity Markets Authority  Workstream All DCA requests are required to be submitted to xoserve via a GT Cost recovery DCA are chargeable and would be defined in the ACS and recovered accordingly. Non implemented proposals which have had DCA are also chargeable and would be defined in the ACS and recovered accordingly Therefore consideration should be given to the economic implications of requesting numerous DCAs

9 Observations for discussion Although user pays is still in its infancy, National Grid NTS suggests a discussion on the following;  Rough Order of Magnitudes (ROM) and Detailed Cost Analysis (DCA)  Production of the IS scoping document(s) Who, where, when, who pays?  Timing and timeframe  Impact of Modification Proposals with multiple Alternatives  Roles and Responsibilities  Modification Panel  UK Link Committee Change to UNC Governance Rules?

10 ROMs & DCAs: Timescales Implications Timescales are potentially longer and the industry should be mindful of this when raising Modification Proposals. Steps may include;  Workstream – development of business rules  ROM required  DCA required  UK Link committee

11 Roles and Responsibilities How effective is the Modification Panel in judging, prior to consultation, that Business Rules (BR) are sufficiently detailed to enable system development costs to be accurately determined?  Does the Modification Panel have this skills set?  Is the UK Link Committee better placed to judge this/

12 User Pays - Application to date User Pays PrincipleMod 0246Mod 0224 Proposal a core service funded through PCR? No Proposal User Pays?Yes Proposal a Non-Code Service (ASA)? No Proposal a Code Service (UNC)? Yes Who should fund proposal? 100% Shippers – rationale provided (no benefit to GTs) 100% Shippers How should costs be apportioned? All shippers with QSEC capacity - based on their proportion of the overall value of capacity Y2- Y16 on implementation Development cost - all shippers, based on eligible Meter Points. Ongoing services – all participating meter points pay a daily charge + transactional charge for Cons. Adj.

13 National Grid NTS’ observations Observations  Lack of clarity with efficiency on multiple DCAs for the same modification proposals.  Role of Panel and User Pays Modifications  Role of UK Link committee  Timescales  Potential need for governance scheduling discussions