M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.

Slides:



Advertisements
Similar presentations
Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Duke Production Status.
Advertisements

The ATLAS Pixel Detector
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012.
MINER A NuMI MINER A DAQ Review 12 September 2005 D. Casper UC Irvine WBS7: Electronics and Data Acquisition  Overview (this talk): D. Casper  Front-end.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
M. Gilchriese Mechanics Labor and Disk Sectors US Pixel Meeting November 2001.
Sensor overview Ulrich Heintz Brown University, Providence, RI 6/18/2015U. Heintz - Sensor Overview 1.
ATLAS Pixel Detector July 2003 ETC ‘04 E. Anderssen LBNL BPSS and Service Panels Santa Cruz, CA E Anderssen LBNL.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
M. Gilchriese Status Report Sectors, Rings, Frame December 2002.
U.S. ATLAS Executive Meeting Upgrade R&D August 3, 2005Toronto, Canada A. Seiden UC Santa Cruz.
DOE/NSF Review of U.S. ATLAS /March 2001 WBS 1.1 Silicon Subsystem M. G. D. Gilchriese Lawrence Berkeley Laboratory.
K.K. GanUS ATLAS Pixel Meeting1 Opto-Board K.K. Gan The Ohio State University WBS
HFT project Overview and Status October 14, 2010 F.Videbaek BNL.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
1 Jim Thomas - LBL 4.2 Meters ~ 1 Meter The SSD: March Face to Face Meeting Jim Thomas Lawrence Berkeley Laboratory March 14 th, 2012 The SSD.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
1 US Pixel Mechanics Role Global support structureIntermediate support structureLocal support structure Stave SectorDisk Barrel x (9-11) x5 x (22,40,56)
LIGO-G M Planning and Implementation Strategy for Advanced LIGO Gary Sanders LSC Meeting Hanford, August 14, 2001.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
M. Gilchriese Overview of Production Plan for Pixel Global Support and Disk Support Rings M. G. D. Gilchriese Lawrence Berkeley National Laboratory February.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
2 Silicon pixel part Done and to be written Written! Under way To be done Introduction 1.Hybrid Pixel Assembly Concept 2.Silicon sensor 1.First thinned.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
M. Gilchriese ATLAS Pixel Upgrade Thoughts on US Role.
1 US CMS DOE/NSF Review: May 8-10, WBS 4.0 The Electromagnetic Calorimeter Roger Rusack The University of Minnesota US-CMS L2 ECAL Manager.
M. Gilchriese - November 14, Module Decision - To Do List By pixel meetings associated with February 22-26, 1999 ATLAS week Beyond making and testing.
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
M. Gilchriese Stave Prototype Status Summary July 5, 2006.
ATLAS Pixel Detector July 2003 SC Pixel Meeting N. Hartman LBNL 1 Pixel Support Tube WBS Santa Cruz Cost Workshop July 9, 2003.
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 W. N. Johnson Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem.
IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 o IBL kick off meeting summary and issues ATLAS Upgrade Project Office.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
SNuMI 1 Outline Action Items PP2 Progress [Nancy/Elaine] –Org Chart Update –FY07 Budget/Plans Discussion –FY08 Summer Shutdown –Overall cost Reduction.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
PHENIX Vertex Detector with Conventional Strip Sensors Abhay Deshpande Stony Brook University.
PS Module Ron Lipton, Feb A bit of History During much of the conceptual design phase of the outer tracker we had focused on the “long barrel”
Vertex detector R&D Work Plan in /3/11 Y. Sugimoto for KEK-Tohoku-TohokuGakuin-Niigata- ToyamaCMT Collaboration.
M. Gilchriese WBS Pixel System DoE/NSF Review May 2003.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
Time to resolve Design Issues 1. Disclamer Due to the engineering meeting last week I have not had time to coordinate this material with Tim or the L3.
SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.
ITOP Quartz Procurement Status James Fast Pacific Northwest National Laboratory PNNL-SA
CMS Phase 2 Tracker R&D R. Lipton 2/27/2014
Jim Fast Pacific Northwest National Laboratory
HFT Overview Flemming Videbæk BNL 3/14/12 F2F LBNL.
P. Morettini Towards Pixel TDR PM - ITk Italia - Introduction 8/2/2017.
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
TileCal upgrade EVO meeting Demonstrator tesks
PXD Summary Tests PXD9 Pilot Production ASICs Components Plans:
TK Upgrade report.
Presentation transcript:

M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz

M. Gilchriese 2 Meeting Agenda July Introduction - Gil, Abe 0930 WBS Electronics - Kevin 10:30 Break 11:00 WBS Sensors - Sally 11:30 WBS Optical hybrids - KK 12:15 Lunch 1;15 WBS Flex Hybrids – Rusty, Pat 2:15 WBS Modules - Maurice 3:00 WBS Mechanics(I) - Gil 3:30 Break 4:00 WBS Mechanics(II) – Neal, Eric 5:30 Contingency 6:00 Adjourn July 19 09:00 WBS Beam Tests - Kevin 09:45 WBS System Tests - Maurice 10:30 Break 11:00 More on system testing 11:30 Contingency 12:00 Lunch

M. Gilchriese 3 Overall Cost increases in a number of areas were identified and a few cost decreases. It’s too early to have bottom line, but the overall cost relative to ETC02 is projected to increase. The next step is to take the information presented and enter into the ETC03 database. Gil Significant delays in most sub-elements were projected relative to the ETC02 schedule of only 8 months ago. As a result, the schedule is now extremely tight, assuming the pixel system is to be ready for installation in the pit by the end of The schedule for Management Contingency decisions is also delayed.

M. Gilchriese 4 Current Milestones

M. Gilchriese 5 MC Milestones

M. Gilchriese Mechanics Substantial delays in sector fabrication, laser welding not yet established. Mitigate cost increase by better phasing with other mechanics tasks to optimally utilize manpower and/or drop some fabrication so that only 2-hit system is possible. Gil PST schedule does not have much float. Production must start early 2003 to meet schedule. Eric, Neal, Gil Responsibilities for PST heater power supplies and DCS not clear. US cannot take on this design responsibility. Gil, Kevin Schedule for delivery of beam pipe support needs clarification. Currently delivered with rest of US items in early Eric Scrub cost estimate shown for beam pipe support. Request FY03 design funds by August ’02. Plan on review of design, leading to go ahead for full prototype construction, in December ’02. Gil, Eric Cost of service panels, particularly soldering of wires, has apparently increased significantly. There are also uncertainties in responsibilities for internal piping. Can the cost be reduced? Maurice, Eric Need overview of manpower by major task by quarter. Does the bottoms up estimate fit with constant manpower? Gil

M. Gilchriese Sensors CIS yield has become zero for unknown reasons. Tesla by far not yet qualified. Delay. Tesla proposed delivery schedule of 75 weeks after go ahead for production is too long. Earliest go ahead is October ’02. This puts end of testing into May ’04 at the earliest, too late. Either Tesla delivery rate increased or cut Tesla order. Limit US contribution to sensor procurement to FY03. None in FY04. This has implications for 2 vs 3 hits. Gil Using production sensors to jump start module program, means more sensors needed. Estimate. Maurice, Sally Update US costs with current exchange rate, and re-estimate contingencies. Sally Testing likely to continue into 1 st quarter FY04.

M. Gilchriese Electronics Clear plan to proceed to FE-I2. MCC plan is not as clear. SEU fixes? System implications? Concerns about SEU in PINs. Measure in August? KK No time for changing design to have B-layer chip and meet end 2005 ready-for-installation deadline. B-layer chip is upgrade, need funding for this in FY04. Abe, Gil, Kevin FE production start by September ’03 is only feasible if changes from FE-I2 are none or “minimal”. Does this imply we plan to use FE-I2 for starting production, even if only as spares for losses during sector and stave assembly? Implications for flex production, module assembly? What are we going to do with 48 FE-I2 wafers? Implications for MCC? Maurice, Rusty, Einsweiler.

M. Gilchriese Flex Hybrids Change flex design to decouple bias grid connection? All concerned How to structure flex fabrication contract given that flexes are ahead of electronics(unless FE-I2 is “production”)? Rusty How to pay for flex PCB? Gil Assume Dyconex for production? Will we know by August? Send Dyconex to LBL for quick irradiation.

M. Gilchriese Optical Hybrids Data shown on VCSEL lifetimes after irradiation are worrying. Radiation tests are very high priority. Higher priority than moving to BeO boards. Gan Unless radiation tests this test beam cycle are definitive, will need more next summer, which means delay of PRR to September ’03 and production in FY04. Also neutron and gamma irradiation, what? Optical responsibilities not clear. What is total cost of all optoboards, update. Gan. What is BOC cost? Kevin What is logical division? All optoboards in US? Wuppertal BOC and related? What does Siegen do? Need proposal for October pixel week. KK, Kevin, Gil Addition of 100kchf for fibers from US requested. Already looking at cost increases in this area without this addition.

M. Gilchriese Modules Model has evolved to only disk modules in US. Schedule for assembling disk modules for 2-hit system works assuming parts delivered, particularly bare modules. Drop bare module probing in US in production. Must be done in EU to meet schedule and if chip replacement is to be done on bare modules. AMS wafer thinning not yet in hand. HV operation confidence not in hand. Impact on flex PRR? Maurice, Rusty. Start work on burn-in system already in FY03 with FE-I1 and later FE-I2 modules.

M. Gilchriese Test Beam/System Test Test beam costs in FY02 exceeded funds available. Required off-base manpower to meet schedule, box more complicated. DAQ problems this year remain to be solved. Test beam in 2003 desires RODs. Implications for pixel ROD schedule? Kevin, Abe Break out system test costs here. This will be considerable increase above ETC02 estimate. System test in FY03 to be done at LBL in time to verify production readiness of FE. Scope of system test in FY04 not clear. Interaction with disk testing, preparations for testing at CERN, test beam... Maurice, Kevin, John R.

M. Gilchriese 13 Bottom Line? Take some risks to meet installation date in pit of early Assume FE-I2 is production quality, proceed with module fabrication and testing as soon as FE-I2 wafers are probed successfully. Emphasis on disk module production. Parallel path to verify FE-I2 design and submit rest of production by September Take the other 40 some wafers and begin real production, with production flex, module assembly and test processes. If lucky, then FE-I3 order is rest of production, about 85% If not lucky, then have brought flex and module assembly to real readiness. Problems: Is MCC ready from FE-I2(same issue as FE-I2). Using production sensors, may need more. Bump bonding costs.