TC meeting 21.11.2014. 21/11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.

Slides:



Advertisements
Similar presentations
Far side Near side -Z End +Z End 5m Wed Dec 7 ECAL CMXZEC CSC REDT+ RBTK FPIXSurvey HCAL TE-VSCEN Dept SL CP Availability.
Advertisements

1 Installation of Delphi Frame  ITS Installation.
TB Peter Glässel, Heidelberg1 TPC Status.
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
TC meeting P2 planning wks 7&8 A.Tauro
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
DCS - general Unscheduled power cut Wed. morning ( , human error) –DCS (and HLT) off, due to UPS on bypass –In the middle of DB migration, had.
1 Responsibilities & Planning DCS WS L.Jirdén.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
LHC (and ATLAS) Status and Plans
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
SU ACTIVITIES PENDANT LS1 CMS ALICE. Antje Behrens | SU pendant LS1 day| | EDMS | page 2 CMS Quoi (quelles activités prévues pendant.
Alice overview New detector and chamber ALICE TC.
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
TS4 preparatory meeting TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.
 YE+4 disks = 2 Nos. (12 Sectors each)  Support Structures = 2Nos.  AISI 1045 steel bar = 1 No. for checking dimension of 680 mm (0/-0.5)  Fasteners.
1st LTEX 22 June 2009D.LACARRERE1 Protection of UX85 EDMS No IP8 Current Status & Plans  UX85 Expt Area  RB84 (8-7 sector)  RB86 (8-1 sector)
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
ALICE TC meeting – Plans for the next technical stop A. Tauro.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
winter shutdown planning A.Tauro
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
TC meeting P2 planning wks 9&10 A.Tauro
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
Central vacuum valve in ALICE Pros and Cons ALICE TC –
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
Review of MGs involvement in SRA process MG meeting 24 th January 2007 Brussels.
TS3 preparatory meeting A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.
TC meeting P2 planning wks 3&4 A.Tauro
André Augustinus P2 events & perturbations 07 May 2010 ALICE Technical Coordination Meeting.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
Rad. Shield 2 Feb. 06D.LACARRERE1 IP8 POINT 8 – RADIATION SHIELD – UX85 Introduction  History (in brief)  Conceptual Design  Why installation shifted.
ELENA installation progress F. Butin / ELENA collaboration.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
EYETS planning A.Tauro.
ALICE 5 o’clock meeting Wk 51.
TS2 preparatory meeting
LS1 planning meeting - A.Tauro
Technical Coordination Parallel Session November 2011, FNAL
LS1 planning meeting
Status of LHC installation & New Installation Schedule
Helium spill in LHC tunnel
LHC Experimental Vacuum Systems Status October ‘07
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
SPS Planning for the EYETS Meeting 8 (07/12/2016)
SPS Planning for the EYETS Meeting 9 (14/12/2016)
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
Upgrade Strategy for the Experimental Vacuum Systems
ALICE 5 o’clock meeting Wk
TRD GAS SYSTEM PRR Gas System Integration Gas building
Proposed Strategic Planning Process for FY 2013/14 thru FY 2015/16
Presentation transcript:

TC meeting

21/11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47 Remove TRD infrastructure and install TRD1748 Close L3 doors and put ventilation, pump down central beampipe, ADA49 Miniframe shielding, TPC RCU250 Miniframe and PX24 shielding, ADC (RB26)51 CERN EOY closure52-1 PX24 shielding (contingency), L3 + Dipole re-commissioning with field2 L3 OFF, move PMD to final position (Fri)3 L3 on4 L3 on – stable conditions (kr run)5 L3 on, LHC sector test (P2) – weekend – stable conditions (kr run)6 L3 on7 L3 on, LHC sector test (P8) -- weekend8 L3 on, LHC cold checkout9 10 NO VISITS ALICE plan till March Nov Dec Jan Feb NO ACCESS UX25 NO ACCESS UX25 when L3 ON and during LHC tests

Lifting beampipe flange by 2mm Intervention planned for next Tuesday – Are we ready? – Shall we inform the VSC people? – Re-alignment of last section in the miniframe after intervention? 21/11/14TC meeting3

Update on BCAM measurement after TRD top installation C-side centre: Oct 3 rd  -2.09, Before TRD5  2.11, After TRD5  -2.07, After CW extraction  no change After TRD4  no change 21/11/14TC meeting4

Known cavern interventions in Jan-Feb PMD: 2 weeks commissioning before moving to final position – Intervention in w2 outside magnets commissioning periods. L3 will stay OFF in w3 – PMD to final position on Fri 16.1 latest MTG: install 1 RPC with new FEE  1 day (Feb?) – Proposed w3, not sure they have the HW ready MCH: not clear how long they nee to complete ST4-5 – Alberto asks whether they can work with the B field in January 21/11/14TC meeting5

AD last minute request ADA: JP asks to drill holes in the (green) beam which supports the beampipe. What to do? 21/11/14TC meeting6

AD last minute request 21/11/14TC meeting7

GHG reply to HSE See attachment 21/11/14TC meeting8

Andre Strategy for the EOY closure ‘Test secours’ from 06h00 to 06h10 – Replacement of DSS UPS batteries in the shadow? 21/11/14TC meeting9

AOB Viktor and Nail goodbye drink: at 16:30 in the P2 cafeteria P2 lunch: at 12:30 in 3294 R /11/14TC meeting10