Commercial in Confidence. © 2008 OHM Ltd Rockall Margin Multi-client Campaign Project Planning Preliminary Survey Design August 2008
Commercial in Confidence. © 2008 OHM Ltd Introduction 2009 Rockall Licensing Round –Acreage in the Rockall Basin is to be offered by the PAD –The round will open Q and close Q The Rockall Basin is extremely under explored, but offers significant prospectivity, within a vast area open for licensing OHM and Hannon Westwood are offering the opportunity to significantly reduce the risk of the identified prospectivity ahead of the license round 2
Commercial in Confidence. © 2008 OHM Ltd Survey design OHM have again teamed up with a company that can provide local geological information and defined prospects This ensure that OHM’s multi-client surveys are: –Correctly positioned for key prospectivity –Technically designed for the survey specific challenges. 3 Hannon Westwood is an Oil and Gas intelligence and consulting company, established in the UKCS for 15 years. Through Hannon Westwood’s Gmatrix Ireland product, and Atlantic Margin knowledge, OHM have been able to target the key areas of prospectivity for the license round.
Commercial in Confidence. © 2008 OHM Ltd Overview of survey locations and identified prospectivity 4 Corrib Triassic Rockall Basin Porcupine Basin Burren L. Cretaceous Spanish Point U. Jurassic Connemara U. Jurassic Slyne Basin Erris Basin Donegal Basin Dooish M. Jurassic Prospect/ Lead outlines Area of 2008 Rockall Licensing Round Survey A Survey B Survey C Survey D Survey E
Commercial in Confidence. © 2008 OHM Ltd 5 65km 55.5km Survey A 3km Receiver Spacing 1.5km
Commercial in Confidence. © 2008 OHM Ltd 6 Survey B 3km Receiver Spacing 1.5km 65km 55.5km
Commercial in Confidence. © 2008 OHM Ltd 7 Survey C 3km Receiver Spacing 1.5km 65km 55.5km
Commercial in Confidence. © 2008 OHM Ltd 8 Survey D 3km Receiver Spacing 1.5km 65km 55.5km
Commercial in Confidence. © 2008 OHM Ltd 9 Survey E 3km Receiver Spacing 1.5km 65km 55.5km
Commercial in Confidence. © 2008 OHM Ltd Timing 10 In order for OHM to deliver results in time for the license round, OHM would need a suitable level of pre-commitment by the end of August ‘08 Acquisition will commence in September ‘08 Results delivered early Q 70% will be invoiced upon agreement, with 30% upon delivery Horizontal electric field survey data Processed CSEM horizontal electric field data Acquisition report Processing and interpretation report Sub-surface resistivity interpretation –Delivered in SEGY –Processed and interpreted in OHM 3D centre of excellence, KL Deliverables