G1400551-v1System Integration Status and Challenges1 System Integration Status and Challenges, Post Project Commissioning Plans to Meet Science Goals May.

Slides:



Advertisements
Similar presentations
September 21, 2005Virgo Status – ESF Workshop1 Status of Virgo B. Mours.
Advertisements

G v1 H1 Squeezer Experiment Update L-V Meeting, Caltech, March 18, 2009 ANU, AEI, MIT, CIT and LHO Ping Koy Lam, Nergis Mavalvala, David McClelland,
LIGO-G D Comments: Staged implementation of Advanced LIGO Adv LIGO Systems 17 may02 dhs Nifty idea: a way to soften the shock, spread cost, allow.
G R LIGO Laboratory1 Advanced LIGO Research and Development David Shoemaker LHO LSC 11 November 2003.
G v1Squeezed Light Interferometry1 Squeezed Light Techniques for Gravitational Wave Detection July 6, 2012 Daniel Sigg LIGO Hanford Observatory.
Stefan Hild and A.Freise Advanced Virgo meeting, December 2008 Preliminary Thoughts on the optimal Arm Cavity Finesse of Advanced Virgo.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
LIGO-G0200XX-00-M LIGO Laboratory1 Pre-Isolation Dennis Coyne LIGO Laboratory NSF LIGO Annual Review, at MIT 23 October 2002.
G M Advanced R&D1 Seismic Isolation Retrofit Plan for the LIGO Livingston Observatory Dennis Coyne 29 Nov 2001.
rd ILIAS-GW annual general meeting 1 VIRGO Commissioning progress J. Marque (EGO)
LIGO-G D 1 Requirements Environment and constraints Performance requirements Functional requirements.
LIGO-G D partial ADVANCED LIGO1 Development Plan R&D including Design through Final Design Review »for all long lead or high risk subsystems »LIGO.
Laser Interferometer Gravitational-wave Observatory1 Characterization of LIGO Input Optics University of Florida Thomas Delker Guido Mueller Malik Rakhmanov.
TeV Particle Astrophysics August 2006 Caltech Australian National University Universitat Hannover/AEI LIGO Scientific Collaboration MIT Corbitt, Goda,
Advanced LIGO Commissioning Overview Stanford LVC Meeting, August 27, 2014 Peter Fritschel.
GWADW 2010 in Kyoto, May 19, Development for Observation and Reduction of Radiation Pressure Noise T. Mori, S. Ballmer, K. Agatsuma, S. Sakata,
LIGO-G D Commissioning PAC11, 2001 Daniel Sigg, LIGO Hanford Observatory.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
Design of Stable Power-Recycling Cavities University of Florida 10/05/2005 Volker Quetschke, Guido Mueller.
Optical Configuration Advanced Virgo Review Andreas Freise for the OSD subsystem.
LIGO-G M May 31-June 2, 2006 Input Optics (IO) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project David Reitze UF.
1 1.ISC scope and activities 2.Initial Virgo status 3.Design requirements 4.Reference solution and design status 5.Plans toward completion 6.Technical.
LIGO-G M Management of the LIGO Project Gary Sanders California Institute of Technology Presented to the Committee on Programs and Plans of the.
LIGO-G M 1 Conceptual Design Review: Initial LIGO Seismic Isolation System Upgrade Development, Implementation Plan & Schedule Dennis Coyne April.
LIGO-G D Enhanced LIGO Kate Dooley University of Florida On behalf of the LIGO Scientific Collaboration SESAPS Nov. 1, 2008.
LIGO- G D Status of LIGO Stan Whitcomb ACIGA Workshop 21 April 2004.
G Amaldi Meeting 2015, Gwangju, South Korea1 Status of LIGO June 22, 2015 Daniel Sigg LIGO Hanford Observatory (on behalf of the LIGO Scientific.
LIGO- G D The LIGO Instruments Stan Whitcomb NSB Meeting LIGO Livingston Observatory 4 February 2004.
Enhanced LIGO with squeezing: Lessons Learned for Advanced LIGO and beyond.
Advanced Virgo Optical Configuration ILIAS-GW, Tübingen Andreas Freise - Conceptual Design -
G R 1 Advanced LIGO Update David Shoemaker LSC LHO March 2006.
LSC-March  LIGO End to End simulation  Lock acquisition design »How to increase the threshold velocity under realistic condition »Hanford 2k simulation.
LIGO-G D What can we Expect for the “Upper Limit” Run Stan Whitcomb LSC Meeting 13 August 2001 LIGO Hanford Observatory A Personal Reading of.
RedGreenBlue Discussion topics LIGO-G v1 Benno Willke, David Shoemaker.
Advanced LIGO Simulation, 6/1/06 Elba G E 1 ✦ LIGO I experience ✦ FP cavity : LIGO I vs AdvLIGO ✦ Simulation tools ✦ Time domain model Advanced.
LIGO-G D 1 Status of Detector Commissioning LSC Meeting, March 2001 Nergis Mavalvala California Institute of Technology.
Paolo La Penna ILIAS N5-WP1 meeting Commissioning Progress Hannover, July 2004 VIRGO commissioning progress report.
LSC Meeting at LHO LIGO-G E 1August. 21, 2002 SimLIGO : A New LIGO Simulation Package 1. e2e : overview 2. SimLIGO 3. software, documentations.
LIGO-G M LIGO Status Gary Sanders GWIC Meeting Perth July 2001.
Status of Virgo GWDAW12 Status of Virgo GWDAW Dec Leone B. Bosi INFN and University of Perugia (Italy) On behalf of the Virgo Collaboration.
LIGO-G D Commissioning at Hanford Stan Whitcomb Program Advisory Committee 12 December 2000 LIGO Livingston Observatory.
Monica VarvellaIEEE - GW Workshop Roma, October 21, M.Varvella Virgo LAL Orsay / LIGO CalTech Time-domain model for AdvLIGO Interferometer Gravitational.
ALIGO 0.45 Gpc 2014 iLIGO 35 Mpc 2007 Future Range to Neutron Star Coalescence Better Seismic Isolation Increased Laser Power and Signal Recycling Reduced.
The Proposed Holographic Noise Experiment Rainer Weiss, MIT On behalf of the proposing group Fermi Lab Proposal Review November 3, 2009.
LIGO-G D Advanced LIGO Systems & Interferometer Sensing & Control (ISC) Peter Fritschel, LIGO MIT PAC 12 Meeting, 27 June 2002.
G R 2004 Plan Update LIGO Systems meeting 22 Jan 04 dhs.
H1 Squeezing Experiment: the path to an Advanced Squeezer
A look at interferometer topologies that use reflection gratings
Next Generation Low Frequency Control Systems
Quantum noise reduction using squeezed states in LIGO
Reaching the Advanced LIGO Detector Design Sensitivity
First Lessons from the Advanced LIGO Integration Testing
Progress toward squeeze injection in Enhanced LIGO
Nergis Mavalvala Aspen January 2005
Is there a future for LIGO underground?
Commissioning Progress and Plans
Nergis Mavalvala MIT IAU214, August 2002
nicolas smith-lefebvre MIT GWDAW 2011
Design of Stable Power-Recycling Cavities
Commissioning the LIGO detectors
Squeezed states in GW interferometers
Workshop on Gravitational Wave Detectors, IEEE, Rome, October 21, 2004
Status of the LIGO Detectors
Status of LIGO Installation and Commissioning
Summary of Issues for KAGRA+
P Fritschel LSC Meeting LLO, 22 March 2005
Improving LIGO’s stability and sensitivity: commissioning examples
Squeezed Light Techniques for Gravitational Wave Detection
Lessons Learned from Commissioning of Advanced Detectors
Arm Length Stabilization at LHO
Presentation transcript:

G v1System Integration Status and Challenges1 System Integration Status and Challenges, Post Project Commissioning Plans to Meet Science Goals May 27, 2014 Daniel Sigg

G v1System Integration Status and Challenges2 What’s left to install LIGO Hanford LIGO Livingston Complete

G v1System Integration Status and Challenges3 Current Timeline

G v1System Integration Status and Challenges4 Achievements  Pre-Stabilized Laser (PSL) was commissioned and works as designed at both at LHO and LLO  Input Mode Cleaner (IMC) has been fully commissioned  All seismic isolators (SEI) work as designed and are fully automated  All suspensions (SUS) work as designed and are fully automated  Dual Recycled Michelson (DRMI) has been fully commissioned at LLO  Arm Length Stabilization (ALS) has been commissioned at both LHO and LLO

G v1System Integration Status and Challenges5 Suspensions work as advertized

G v1System Integration Status and Challenges6 Past Commissioning Periods  One arm test (OAT)  First arm cavity locked at LHO in summer  Input Mode Cleaner Test  IMC locked at LLO in fall 2012, and spring 2013 at LHO.  HIFO-Y  Commissioning the first ALS at LHO in summer  Now also completed for H1 HIFO-X, L1 HIFO-X and HIFO-Y.  DRMI  Locked at LLO in summer  Also completed LHO PRMI (without AS port) in winter 2013.

G v1System Integration Status and Challenges7 Current Commissioning Period  HIFO-XY  First look at arm cavity difference at both sites in spring  Corner station ALS fully commissioned at both sites.  Green coating issue resulted in schedule delay.  Interferometer locking  Full lock attempt at LLO on-going.  Common mode lock attempt at LHO on-going.

G v1System Integration Status and Challenges8 Top Level Summary  Initial integration testing has progressed quickly  All major systems have performed as planned.  No show-stoppers found.  No true low noise test so far.  The only significant delay was due to the green coating issue.  Pace may not be sustainable.  Green coating issue  Will not prevent the ALS from working.  Additional resources had to be allocated.  Robustness will suffer.  The locking procedure is close to being validated

G v1System Integration Status and Challenges9 Automation  Complexity has been a problem  Too many variables  Hard to know everything  Too many steps to achieve simple tasks  Too many things can go wrong  Great strides are being made to improve automation  Script approach (Guardian) and some ALS locking code (TwinCAT PLC)  Still substantial work needed to recognize, diagnose and rectify problems, as well as user interfaces  Keeping everything under configuration control is a problem  How to make sure everything is in the right state?  Control room tools are not always well integrated  Sometimes tedious and repetitive tasks are holding us back  Need to make existing tools more useful and efficient  Clear-text information/instructions for operators still only rudimentary

G v1System Integration Status and Challenges10 Arm Length Stabilization

G v1System Integration Status and Challenges11 Locking Process

G v1System Integration Status and Challenges12 ALS Noise Alignment couplings Acoustics Cavity filtering

G v1System Integration Status and Challenges13 Differential Mode ALS Suppressed Commissioned and meets requirements

G v1System Integration Status and Challenges14 Current Effort Arm power Reflected power  LLO succeeded in reducing the CARM offset to 30 pm. (all five DOFs were locked by IR signals.)  Close to the fully locked interferometer

G v1System Integration Status and Challenges15 Post Project Plans for Commissioning

G v1System Integration Status and Challenges16 Post Project Plans for Commissioning  Commissioning is the process of bringing each interferometer to its design sensitivity  Noise characterization & noise hunting  Achieving stable, low-noise operation  Tuning of controls systems  Gradual increase of injected laser power  Robust operation  Implementation of new technologies and ideas to continually improve detector performance  Commissioning is interleaved with engineering & science data collection runs

G v1System Integration Status and Challenges17 The challenge of commissioning  Everything is operating near fundamental limits, and many effects cannot be tested on small scale setups  Requirements are often set as a compromise between feasibility and design margin: some may turn out to be inadequate  Many noise mechanisms arise from the interplay among several subsystems or interferometer characteristics

G v1System Integration Status and Challenges18 Starting Point: Advanced LIGO Project Acceptance  Subsystems meet their acceptance criteria  Design documentation  Test results and requirements verification  User’s manuals, procedures, parts lists, etc.  Each interferometer locks for an extended time (2 hours)  Locking: acquire and maintain interferometer resonance under automated control  Functional prerequisite for sensitivity studies and improvements  Locking tests basic functional requirements; commissioning tests deeper performance requirements

G v1System Integration Status and Challenges19 Advanced LIGO: anticipated timeline 2015: ~1+ yr after acceptance mid-2016 end-2017 Full sensitivity (200 Mpc): end-2018 Initial LIGO: Overall, 4-5 years from locking to design sensitivity

G v1System Integration Status and Challenges20 How we expect to speed commissioning effort in aLIGO  There is much more upfront subsystem testing in aLIGO, including …  Enhanced LIGO, a full scale test bed for several aLIGO technologies. Alignment of the output mode cleaner Diagnosis and mitigation of beam jitter noise HAM ISI Output Mode Cleaner Commissioning advances:

G v1System Integration Status and Challenges21 Much greater seismic isolation in the control band Motion input to the test mass suspensions 1000x aLIGO target aLIGO so far iLIGO

G v1System Integration Status and Challenges22 Speedier commissioning  Better teams on hand  More people and with more experience  Observatory staff, including operators, involved from the beginning  Better support structure in place  Software tools in place  Online web tools in place  Having been there before helps a lot!  Lock acquisition strategy designed in from the start, including a new Arm Length Stabilization system  Long arm cavities are controlled independently using a different wavelength laser 4 km arm

G v1System Integration Status and Challenges23 On the other hand: Principal Technical Risks  High power operations  Absorption & thermal compensation; parametric instability potential  Required displacement noise levels not verified directly  Essentially impossible to test in subscale setups  Thermal noises (suspension and mirror coating): rely on design calculations; material parameter measurements; scaled noise tests  Technical noises (magnetic field coupling, e.g.!): design calculations & best practices  Increased complexity  Number of control loops an order of magnitude larger than in iLIGO  Mechanical systems have many more degrees-of-freedom; e.g., Test Mass Quad suspension has 48 DOF, vs. 6 in iLIGO  Reliable and robust controls of interferometer

G v1System Integration Status and Challenges24 Challenges  Operational and logistical aspects must be addressed from the beginning; greater complexity of aLIGO demands more investment in:  Configuration control  Operator training  Maintainability  Simplification of operations  Must anticipate that some components may need to be re- designed or upgraded with new features  Nature of a new and complex scientific instrument that not all requirements are adequately known beforehand  A number of such examples from initial LIGO enforce the lessons:  Initiate & maintain R&D in supporting technologies  Identify deficiencies early and commit resources to dealing with them

G v1System Integration Status and Challenges25 Commissioning strategy for early discovery  Frequency range of Hz is the most important for NS-NS inspiral range  Laser power  Operation at full laser power will take significant commissioning time, but is not necessary to achieve very good inspiral range  We’ve targeted 25 W as the input power level for the first stages of operation (approximately the level achieved in Enhanced LIGO)  Technical noise sources  For many noise contributors, ultimate performance at 10 Hz can be deferred, with ~20 Hz as an intermediate goal, with no effect on NS-NS inspiral range

G v1System Integration Status and Challenges26 Design for performance at lower power  Recycling cavities designed so that little or no compensation of thermal lensing will be needed  Implementation/optimization of thermal compensation was a big time sink in iLIGO/eLIGO  Signal recycling optimized for lower power BH-BH Range (Gpc) SRM transmission 35%

G v1System Integration Status and Challenges27 Steps to get to Low-Noise Operation  Acquisition  All steps to bring an uncontrolled interferometer to its operating point  All cavities on resonance; alignment close to optimal  Locked  All steps between acquisition mode and low-noise mode  Low-noise or Science mode  Science data is collected There are many steps in getting to a functional GW detector – these are split into 3 phases

G v1System Integration Status and Challenges28 Locked Phase Steps  Transition to low-noise sensors for global control  Initial locking achieved with more robust, but lower SNR sensors  aLIGO innovation: all low-noise sensors are located in vacuum, on isolated platforms  Increase laser power  Initial locking done at low power, one-to-several Watts  Typically increased in multiple steps  Full implementation of alignment control system  Initial acquisition mode, with a simple sensing matrix but relatively poor performance  Science mode, with more complex sensing, tuned control bandwidths and noise cut-off filters

G v1System Integration Status and Challenges29 Locked phase steps, cont’d  Global length controls optimization  Tuning of the GW channel loop for stable, low-noise performance  Reducing noise contribution from auxiliary loops via bandwidth tuning; filter design; on-line correction paths  Low-noise mode for suspension and seismic systems  Optimization of suspension local damping filters  Engagement of low-noise mode for suspension actuator drivers  Thermal compensation activation  First level of compensation achieved with the ITM ring heaters  Greater levels of compensation using the CO2 laser projector beams  Preceding steps aren’t entirely sequential Establishing and optimizing the Locked Phase sequence is one of the two main tasks of commissioning

G v1System Integration Status and Challenges30 Potential Component Upgrades  Non-essential design element may not have been ready for baseline  Example: input beam mode-matching control  New analysis may indicate less margin in the design, or uncertainty in the original design margin  Example: squeezed-film damping in the End Reaction Masses  Example: improved suspensions for output beam steering optics  New developments since the design was frozen  Example: output beam mode-matching control Why are we talking about upgrades at this stage? Paper design might not cut it, and we need to be prepared to rectify it

G v1System Integration Status and Challenges31 Resources  Commissioning teams comprised of observatory- based personnel, plus students, post-docs, scientists and engineers from the MIT and Caltech groups  Equipment budget of $8M over five years  Covers modifications required to the basic aLIGO design  Engineering estimate using aLIGO design/procurement data, and comparison with analogous iLIGO activities Increased observing Requested budgeted is at the low end of this range

G v1System Integration Status and Challenges32 Summary  Commissioning Advanced LIGO is the biggest challenge for the Lab  We have a well defined plan for where we want to be and how to get there  Improvements in technology, test plans, and overall experience and personnel should result in faster commissioning  Faster to get close to design sensitivity: Within a factor of 2 of the design goal in 2 years of commissioning

G v1System Integration Status and Challenges33 Squeezer Effort  First upgrade to aLIGO  Goal 10dB, minimum 6dB  Proposal: TBD  R&D effort at MIT/ANU  Filter cavity experiment (with H1 squeezer)  In-vacuum OPO: Prototype at ANU  Fiber-coupling: UHV feedthroughs, drift, noise, etc.  Other efforts  Syracuse: adaptive mode matching at AS port  Florida: Low loss Faraday