1 MICE Project Board Schedule and risk discussion Introduction Project Management comment Schedule considerations Adapting the schedule/reacting to circumstances.

Slides:



Advertisements
Similar presentations
Report from MICE project teams Proposed MICE organogram: revised Revised request for resources for financial year 2003/04 Review of iMICE schedules – status.
Advertisements

1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 APRP Meeting MICE UK work packages Costs and schedules Organisation and monitoring Schedule summaries Cost summaries Andy Nichols, STFC, 15/8/11.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
An updated Baseline Design for MICE From proposal to technical reference Paul Drumm, Dec 2003.
Development and Quality Plans
Project Managers Report Video Conference 172 Roy Preece 11 th December 2014.
© 2005 Prentice Hall14-1 Stumpf and Teague Object-Oriented Systems Analysis and Design with UML.
1 MICE CM28 STEP III or STEP IV? – some practicalities Andy Nichols/Tim Hayler, STFC 4 th October 2010 Considerations Step II Step III Step IV Conclusions.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
What’s a Project? AD642. Why the Emphasis on Project Management? Copyright 2011 John Wiley & Sons, Inc. 1-2  Many tasks do not fit neatly into business-as-usual.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
1 MICE CM28 Schedule & Risk Comment Schedule reconstruction and management The ‘straight to Step IV’ discussion How a schedule meeting can work Risks (and.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
U.S. Muon Accelerator Program: MICE Milestones & Resource-Loaded Schedule M. A. Palmer, Director October 31, 2012.
Spokesmouse’s News Agenda: o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May o VC 17th June o CM27 (RAL)
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE PM Report Outcome of Reviews held at CM22 –Motivation for holding them –Outcomes & actions –Observations & follow-ups MICE Video Conference, 20.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
MICE Spectrometer Solenoid Review A summary of P.Fabbricatore on behalf the review board Amalia Ballarino, Elwyn Baynham, Tom Bradshaw, Mike Courthold,
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 MICE CM27 Engineering integration Andy Nichols, STFC 9 th July, 2010.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Finance Roy Preece STFC RAL Oversight Committee Meeting 27 th November 2015.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
Status of the MICE Construction Project
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE Project Board Schedule and risk discussion Introduction Project Management comment Schedule considerations Adapting the schedule/reacting to circumstances The difficult bit Project risks Managing the Risk/Schedule aspects Andy Nichols, STFC, 23 rd September, 2010

Introduction Some difficult slides to make – far easier to do a ‘show and tell’ Do not intend to show highly detailed.mpp files or Excel tables But more to describe how we do things, some of which have been proven by existing project experience The top-level MICE schedule is dominated by only two or three dates for major subsystems Understanding and managing these dates is our (my) job Once we have done that, the rest of the schedule can hang around them. 2

Project Management comment With relevance to schedule and risk: –MICE Project management is a UK deliverable –Emphasis at first on: Construction schedule Technical integration/interfaces Documentation Quality Assurance Safety management & responsibility –PM reports to/interacts with EB, Spokespeople and Collaboration Board in all matters, especially planning and scheduling MICE WBS and scheduling detail (for UK project) can be found at: (Too much detail to show here, and not quite up to date This is the main topic that needs to be transferred to MICE) 3

Project Management Comment Significant additional manpower is required to integrate the whole MICE project into a unified schedule A schedule framework exists Much detail and largely up to date for UK project Team has recently been reinforced: Chris Bulloch – Temporary project planning Roy Preece – will take over from Chris full time Jason Tarrant – Project integration But much still to do 4

Schedule considerations The MICE Project is configured in six discrete R&D phases, Steps I to VI The completion of MICE, i.e. demonstration of cooling, is driven by the international physics timetable The individual steps have value in their own right, but some may be skipped (Step II for example) Historically, the top-level schedule is defined by single-page graphical description – see over – easily readable by all collaborators Milestones are reviewed each Technical Board meeting monthly, and the whole schedule at each Collaboration meeting (3/year) We are presently working to that which was agreed in March 2010, but with a very important qualification, see later 5

6 Present top-level MICE schedule Agreed by MICE – reviewed at Collaboration Meetings This version – March, 2010 See notes next slide For comment re Steps III & IV

Schedule considerations The post MICE Step I schedule is now largely driven by the spectrometer solenoid delivery – see magnet talk The problems with solenoids are being understood: A repair plan is being worked on It will be reviewed and hopefully agreed October 2010 Points to review: thermal model, safety margin, quality control, manpower and scheduling, engineering implementation AT THAT POINT, detailed MICE project schedules and milestones will be re-baselined December 2010 should be taken as the likely date for complete acceptance of the recovery plan We will keep the MPB informed of the developments. It’s conceivable that MICE Steps II&III can be skipped to go directly to Step IV in Q and save time, but physics and AFC practicalities then also comes into the argument – see later. Physics and practical constraints for this will be explored in CM28 (October 2010) 7

Adapting the schedule 8 This is where we have to get to: MICE Step VI (  2013)

Adapting the schedule 9 Step IV Liquid Hydrogen delivery system Given the uncertainty of the spectrometer solenoid, UK is concentrating on Liquid hydrogen and RF this FY We are investigating the possibility to perform magnetic survey at vendor instead of Fermilab, thus saving time (2-3months) and risks Added bonus: same team/device could be measuring AFC and Coupling coils (so far unsolved issue)......But to stand the best chance of making it, we probably have to change the plan

Going straight to Step IV Some points to consider: –FC magnet delivery is early 2011 –UK is endeavouring to get hydrogen delivery system done in FY 10/11 –Does going straight to Step IV preclude scientific work unique to Step III? –What are the run plans for steps III & IV – they compete directly with ‘building’ time and have to be balanced –Time taken with dismantling the intermediate configurations –And the risk of damaging delicate equipment needlessly 10

Adapting the schedule The reasoning goes something like this: –The delivery dates to RAL of both spectrometer solenoids is uncertain, but first one is unlikely before mid-2011 –There is a several month integration period to build and commission and equip each solenoid – this cannot be avoided, but could be mitigated by more people –We need to include/optimize magnetic survey steps –The UK has rearranged itself to build a complete LH2 delivery system in FY10/11 –And we need some project ‘float’ – vital, as we have not done this before –Step III & III.1 vs directly step IV -- will be reviewed at CM28 –A significant input to this is the time taken to dismantle and re- assemble the step III configuration, or to mount and dismount the AFC module (weeks rather than days?). detailed plan will be presented at above discussion. 11

Task DescriptionDate Complete EM, thermal and mechanical analysesmid-Sept. Complete the design modification planearly-Oct. Presentation to review committee(s)end-Oct. The nominal reassembly time for the magnets is expected to be approximately four months Important note: this cannot be decided until the plan, including its detailed schedule is reviewed Actual assembly time will depend on the degree of modification required The second magnet will follow the first by 2 to 3 months This date also cannot be predicted in detail right now Very provisional Spectrometer solenoid plan – courtesy Steve Virostek

The main jobs we have to do on the first spectrometer solenoid when it arrives: customs etc unwrapping installation in place mounting and connections install controls cool down power up test installation of diffuser installation of shielding plate quench tests measurements in situ of magnetic field (subject to discussion) disconnections displacement in park position for tracker assembly installation of tracker connections of tracker etc etc… re-installation of diffuser and of plate move to beam position, geometry again install TOF1 and TOF1 cage This is presently ‘under construction’ as the final details are unknown and some points still being discussed UK integration schedule is only for FY 10/11 at present but this represents around four months’ work schedule is provisional only, based on Jan 2010 knowledge Some of the integration steps

The difficult bit Most of MICE’s activities are (many) relatively straightforward mechanical and electrical tasks – why so difficult? They can be lined up and expressed as Gannt charts easily enough, but: The schedule to be realistic must include explicitly defined and understood ‘float’ to make allowances for risky/unforeseen tasks that might take more time Resource loading (of competent and available manpower) should also be called out properly and given suitable headroom – this is becoming one of our major worries resulting delays w.r.t. expectations are damaging for MICE collaborators as well as to our credibility to the outside. 14

Project Risks Tend to separate into three types: –Technical RF, liquid hydrogen, mechanical, electrical Probably the easiest to manage, as MICE is in control to large extent –Financial Funding difficulties Stretching the schedule –Personnel Skills balance Finding the right staff Also connected with finance Project flexibility – reacting to change quickly Both the above difficult to manage, as usually significant outside influence, ie competition with other projects, recruitment bans, etc 15

Managing the schedule/risk aspects Quite understandably from 2007 we first focused on the UK project The UK project undertook a number of cost and schedule reviews This established a framework Now have weekly progress meetings that monitor: Earned value Review the risk register(s) Review the project schedule Spend against allocation UK project is broken into work packages Each WP manager has delegated budgetary, schedule and risk ownership responsibilities Good participation, this now works very well 16 The next step is to carry this methodology over to the international project, involving much more travel and communication – full-time job....

Summary UK activity installation is now in a largely stable state and ready for Steps II onwards Schedule planning methodology has been developed by UK project Now ready to read it across to international project Appointment of right person is making progress Top level schedule is under review to recover time Major subsystems dominate the above, but are being understood now lack of available suitable manpower and skills balance is a rapidly evolving major project risk 17