Maryland Avenue and Arkwright Street Nick Fischer, EIT Ramsey County Jerry Auge, PE Project Manager Ramsey County April 29, 2013
Maryland Ave Reconstruction
Presentation Topics Project Outline Proposed Improvements Construction Phasing Project Cost Acquisition Update Schedule
Purposed Improvements Improve Safety within the Corridor – Adding Left Turn Lanes on Maryland Avenue – Increase Lane Width to 11 feet Improve Radii at Intersection of Arkwright St. Consolidate Driveway Access near Arkwright St. Improve Pedestrian Facilities at Intersection
Existing Maryland Ave at Arkwright St. Roadway width 40 feet Four lane section Lane width 10 ft No designated left turn lanes at Arkwright St. 30 mph
Proposed Maryland Ave at Arkwright St. Roadway width 44 feet Four lane roadway 2 foot curb and gutter 11’ left turn lane 11’ thru lanes 5’ sidewalk 5’ boulevard 30 mph
Manhole Reconstructs & Gas Main Abandoned Gas Main
Project Phasing Road Open to Traffic – Two Way Traffic – One Way Traffic – Longer Construction Schedule Road Closed in Phases – 3 Phases – Shorter Construction Schedule
Project Phasing Build Under Traffic One Way Traffic Expensive Traffic Control Temporary Signal Back In Trucks Temporary Roadway Temporary Closures Utilities 5 weeks per side ( 10 weeks total) Road elevation change Extra construction cost $100,000
Project Phasing Road Closure Better Roadway Construction Shorter Construction Time Remove Gas Main No Temporary Signal Raising Intersection Reconstruct Manholes Bus Route Move to Clark St 3 wks, 3wks, 1 wk 7 weeks total
Phase 1 Closure Phase 2 Closure Phase 3 Intersection Closure
Closed Intersection Closed Maryland Ave Detour
Project Costs Federal Funding $1,363,300 County State Aid Funding $1,350,000 City Funding$1,050,000 Total Project Costs $3,963,300
Property Acquisition Update Total of 31 Parcels – 26 Property has Settled – 1 Properties Tentatively Settled – 4 Properties Unsettled
Project Schedule ROW acquired May 20, 2013 Project ApprovalsMay 2013 Advertise ProjectJune 2013 Utility RelocationsJuly 2013 Start ConstructionAugust 2013 End Construction October 2013
Maryland Avenue and Arkwright Street Nick Fischer, EIT Ramsey County Jerry Auge, PE Project Manager Ramsey County April 29, 2013