K. Long, 18 April, 2015 Beam-line status — red sky at night?

Slides:



Advertisements
Similar presentations
Summary of MICE 4/4/2008 shift during the ISIS machine-physics period Goals for 04 Apr08 MICE shift: 1. Radiation survey in MICE Hall with target operating,
Advertisements

MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 21 September, 2009.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MICO 1 st February 2010 Terry Hart (MOM). MICO 1 st February June 2015 Decay Solenoid DS will not be ready for Machine Physics. Matt Hills spent.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 14 September, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
MICO 9th Aug 2010J.S. GraulichSlide 1 MOM report o Last Week o Run Plan for this Week o Machine Physics Jean-Sebastien Graulich, Geneva.
M. apollonioAccel. R&D/Physics and IADR - RAL - 19/3/ Magnets Dry Run ISIS Scheduling Meeting Latest news on Target Ready to run ? Summary of: Magnets.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MOM Report. Shield Wall – Gone Before During After 2.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 26, 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting June 7, 2010.
A Tale of Two Targets … 7 th September 2009 Chris Booth The University of Sheffield.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 19, 2010.
Target Assembly and Installation Update 20 th August 2009 Paul Hodgson The University of Sheffield.
Commissioning needs: K.Long. Routine: LN2 bottle: –Needs to be sited in MICE Hall or outside vault so that routine checks of contents can be made.
CMPB Alain Blondel 14 April STATUS OF MICE.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 30, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 7 September, 2009.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
K. Long, 10 October 2015 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
M. apollonio MICE Beamline summary. - Beamline parallel session (June 1 st ): - envisaged goals (Alain) - assess readiness of the line magnet status (Ken)
MICE Target - Risk Lara Howlett University of Sheffield.
Beam line commissioning Preparations for Phase1 Kevin Tilley For Paul Drumm & the beam line group.
Plans (& ideas) for beamline commissioning The beamline Magnet field tests Source characterisation Optics (& model) commissioning K. Tilley CM18, 14/06/07.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Linda R. Coney – 24th September 2009 MOM Update Linda R. Coney 24 September, 2009.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
MOM report: 08May May08 M. Apollonio, P. Kyberd, M. Ellis, K. Long.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
Transversity Readiness and Timeline Xiaodong Jiang, March 17th, This document specifies the overall readiness for Hall A experiments E06-010/E
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
Running plan Step I.1 Basic radiation levels. I.1.1 ISIS running with beam elements on, target off, beam stop shut. Establish permanent MICE monitoring.
VC117 February 2009Jean-Sébastien GraulichSlide 1 MOM Report o Yagmur Torun ( June 15 - July 14) o J.S. Graulich ( July 13 - August 7) Jean-Sebastien Graulich,
SPOKESMAN’S UPDATE K. Long Imperial College London/STFC.
MICE VC 12/2/20091 [23/1-19/2] MOM report Hogdson Apollonio Zisman 23/1/09 12/2/09 19/2/09 Relevant Issues: - NO target since december accident  no data.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
Beamline Update Adam Dobbs, MICE CM38 Feb Contents Recent and Upcoming Activities Target Conventional magnets Decay Solenoid Proton Absorber Summary.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
MAUS Status A. Dobbs CM43 29 th October Contents MAUS Overview Infrastructure Geometry and CDB Detector Updates CKOV EMR KL TOF Tracker Global Tracking.
Target Status 27 th August 2009 Chris Booth The University of Sheffield.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
MICE Spectrometer Solenoids Step IV running
Chris Booth Sheffield 29th March 2006
Target Installation Plan
MICE Target Report Video Conference 29/11/07
Presentation transcript:

K. Long, 18 April, 2015 Beam-line status — red sky at night?

Upstream beam line: – Steel shielding removed – Q1—3, D2 re-instated – Soak test performed

Decay solenoid:

   ‘In hand’: CMacW assisting sol d team to finalise QD While some documentation exists, thorough job to generate consistent set yet to be completed M.Courthold, M.Hills Presented to and agreed by MICE Technical Board

Downstream beam line & Step I instrumentation: D2, Q4—Q9: – Water and power re- established Pressure reducing valves fitted – Need to be calibrated Magnets have been ‘dry’ for weeks Soak test OK Beam stop – Works OK Step I instrumentation: (installation) – Inside DSA complete: GVA1, BM1, TOF0, Ckov – Outside DSA: BM2, TOF1 in position KL to be positioned

D1 tested for 2h10min at 245 A and for 30min at 400 A Q1-2-3 tested at 195 A for 3h Q tested at 395 A for 6h D2 tested at 150A for 5h40m and at 120A for 30m DKsol tested at 60A for >3h temp. taken at different intervals showed stability Some MPS+MAGNET waterflow failures resulting in trips: however no evidence of water flow problems was found CONCLUSIONS –Confident the line is fine –shame no time to test D1 at 400A for longer period –DKsol tested separately at 870A –Important to sort out the fake waterflow issues Q1-2-3 D1 DKsol D2 Q Soak Test - August 26 th 2009 (MA, A.Dobbs, M.Ellis, K.Long)

BREAKDOWN of Q1-2-3 D1 DKsol D2 Q Soak Test - August 26 th 2009 In the morning (10:00 to 13:20) only DS BL was up. US BL was not powerable due to hardware intervention (soldering, M. Hughes) DS BL morning settings: D2=195A Q =395 A At 13:30 D2 was set off to reduce overall power and allow US beamline to be tested Q1-2-3 = 195 A D1=245 A  value chosen to not overcame an alleged software threshold DKsol=60A D2= 0A Q =395A We experienced some MPS and MAGNET waterflow failures which triggered interlocks. In all cases this did NOT seem to correspond to real failures rather some mis-reading from the unit. This should be understood or we can risk abrupt stops when running in Sept/Oct D1 13:40  set back to 245A 14:20: D2 set to 150 A D2,Q4,Q6 15:20  set back to previous values 15:40 Q1 Q2 Q3 D1 DK D2 Q4 Q5 Q6 Q7 Q8 Q :00 set D1 to higher value (no software threshold preventing it !)  the final configuration (30 min test) Temperature readings taken at different times after several hours showed a good stability CONCLUSION: we believe magnets are well behaving.We tested the line with all magnets at values close to their maximum. We could not power them all MAX simultaneously so We still need to understand the MPS/MGNET waterflow failures generating interlocks which do not seem to correspond to REAL events

Target Just pictures, details from C.Booth

Target build: Shaft received from TechVac (DLC coating company) Wednesday 19Aug09 Assembly of ‘Target 1’ (T1) complete Friday 21Aug09 – Installation in R78 completed Saturday 22Aug09 – 50k actuations completed Sunday 23Aug09 – Metrology of target tip position within dummy vacuum vessel Monday 24Aug09 – Installation in ISIS complete Tuesday 25Aug09 Gate valve opened ~16:30 – Target space is under the ISIS machine vacuum! Assembly of T2 complete Sunday 23Aug09 – Installation in R78 complete Tuesday 25Aug09

Modifications in synchrotron vault: Modified gate valve fitted – Including thermocouple ‘Collection pot’ and mirror system fitted Connections reversed for quick installation and removal

T1 build:

T1 installed on ISIS:

T2 build and installation in R78: Great team effort! – Great support from ISIS personnel Outstanding issues: – See C.Booth talk, but headlines: Details of controls and EPICS interfaces in MLCR installation being sorted out Debugging non-standard actuation behaviour in R78 set up Still to perform 400k actuation run in R78

Conclusions: Magnets that make up MICE Muon Mean ready for operation Target installed and being debugged Offline target installed and in commissioning phase: – Debugging non-standard actuations ‘Rehearsal’ of running full beam line scheduled for Thursday 03Sep09 For next MICE running phase: – MMB expert on call 24/7: Expert to be present to assist MOM and shift crew in setting up beam line for data taking and to shutdown beam line at the end of data taking: – Essential: e.g. one target interlock not yet established Rota to be established: – MMB expert phone obtained – MOM/shift should call MMB expert first – Goal of all this to be more efficient in set-up, operation, and shutdown than last year And finally: – MICE shutdown briefing: 12:00, 04Sep09, MICE Hall