Www.sgh.com DESIGN INVESTIGATE REHABILITATE Design and Quality Assurance of CFRP Repair of Concrete Pressure Pipes Rasko Ojdrovic Murat Engindeniz Mehdi.

Slides:



Advertisements
Similar presentations
Building a Cradle-to-Grave Approach with Your Design Documentation and Data Denise D. Dion, EduQuest, Inc. and Gina To, Breathe Technologies, Inc.
Advertisements

Special Inspections
Fired And Unfired Pressure Vessels
Managing a Successful Mechanical System project Following design – what next?
Joe Killins & Associates, LLC Pipelines & Risk Based Management How Safe is Safe?
GTI’s Composite Materials (CM) Program
Subfloor Evaluation Prior to Installation Understanding the science of concrete slabs prior to installation of moisture sensitive floor covering materials.
Neptune Research Inc. Introduction For more than 25 years, Neptune Research Inc. has focused its strategic research initiatives on the development, manufacturing.
AN INTRODUCTION TO: from the leading resource for education and information in the repair industry... TECHNICAL GUIDELINE S Guideline for Using In-Situ.
Hardened Concrete Properties u Strength u compressive strength psi u tensile strength psi u flexural strength u compression >> tension.
PIPE INSPECTION AND REPAIR
CONSTRUCTION OF SOIL NAILING WALLS
Review of relevant ASTM standards and CIPP specifications.
Elements of a Good Concrete Pipe Specification David JP Matocha Technical Resource Manager Hanson Pipe & Precast.
FAA Regulatory Policy for Composite Material Control Presented at 8/8/02 FAA/NASA Workshop (Chicago, IL) Introduction – Importance of stabilizing composite.
WILLBROS A Good Job On Time Hydrostatic Testing Practices Establishing Verifiable, Traceable, and Accurate Documentation August 20, 2013 Hal Ozanne Willbros.
AN INTRODUCTION TO: from the leading resource for education and information in the repair industry... TECHNICAL GUIDELINE S Guideline for Verifying Field.
ISO Standard is based on the management model of plan – do - check – act. Today we all be discussing the elements of the standard that deal with.
AN INTRODUCTION TO: from the leading resource for education and information in the repair industry... TECHNICAL GUIDELINE S Guideline for Design, Installation,
Advanced Manufacturing Laboratory Department of Industrial Engineering Sharif University of Technology Session #19.
2013 Section Engineer’s Meeting.  Correct Type, Gauge, and Coating (Standard Drawings)  Based on Pipe Diameter, Fill Height & Soil pH  Obtain copy.
REPAIR MANUAL Dr. Mohammed Maslehuddin Research Institute
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
You Should Know Bulletin No. 135 © ACPA All Rights Reserved.
1 August 12, 2014 Surety Risk Assessment Utility Pipeline Failure Case History – Tyndall, SD Presented by: American Concrete Pipe Association Scott Hofer.
Design and Plans for Introducing Flexible End Parts Steve Krave 15 October 2013.
Road Map to a Green Tag Paperwork=Time=Money. Questionnaire If you could change any one major thing inside the Fire Community Services process what would.
Process Safety Management
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
National Energy Technology Laboratory U. S. Department of Energy Project Kickoff Presentation December 16, 2003 Ken H. Green Principal Investigator Development.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
What Do Inspectors Need To Know About BMPs? Tim Zimmerly, Terrill Lemke Los Alamos National Laboratory LA-UR
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
Mechanical Integrity Quality Assurance. Lesson Objectives  Describe How to Ensure Controls in Place for QA  Describe Standard Record for Inspection.
1 SAN DIEGO COUNTY WATER AUTHORITY PIPELINE RELINING PROGRAM Keeping the Water Flowing.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
Important informations
LSST Camera CD-3 Review Brookhaven National Laboratory, Brookhaven, NY LSST Safety Council Camera Review Bremerton, WA 2015 LSST Camera Environment,
OPS - SCC Workshop R&D Past and Present December 2, 2003 Jerry Rau - Panhandle Energy.
Nuclear Standards for Polymeric Piping Aaron Forster, NIST Engineering Laboratory NIST, MS Bureau Drive Gaithersburg, MD (301)
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
Standards, Training, and Certification in the Wastewater Industry Presented by: Bob Murphy, Sherwin Williams.
INTRODUCING S HILUV ENERGY IS OUR POWER!. W HO WE ARE ? SHILUV is a company that represents professional engineers in energy related fields of construction.
TRENCHING & EXCAVATION
Concrete Weight Coating Plant “Aladja”
INGAA Quality Management Systems White Paper Supporting Pipeline Construction.
Institute of Building Materials Research Conservations Repair and Polymer Composites RWTH Aachen University, Germany “Who`s managing the quality in the.
SWPPP: Stormwater Pollution Prevention Plan Creating/Implementing a Plan for Compliance.
Sanitary Engineering Lecture 13
CE UNIT 1  Maintenance is the act of keeping something in good condition by checking or repairing it regularly.
Use and Conduct of Safety Analysis IAEA Training Course on Safety Assessment of NPPs to Assist Decission Making Workshop Information IAEA Workshop Lecturer.
Hardened Concrete Properties
CIVI 6061-Strengthening of bridges using FRP
Materials Selection and Coatings
AND AFTER INSTALLATION Technical Director, NASSCO
CHAPTER 2 Pipeline Coatings.
Extending the life of essential sub surface assets
Flooding Walkdown Guidance
WATER MAIN REHABILITATION
Hardened Concrete Properties
4th Annual Construction Law Summit
Chip Seal Quality Assurance Guide
GUIDELINES AN INTRODUCTION TO: Material Selection TECHNICAL
Emulsion Task Force Meeting
Document Development for Metro Project: Performance-based Procurement Asphalt Overlay for Programmed Maintenance 17/01/2019.
Quality Assurance for Emulsified Asphalt Surface Treatments
Joints John Kallemeyn.
Prime Factors for Successful Preservation Treatments
AASHTO LRFD Section 12 Standards
Fiber Reinforced Polymer Systems
Presentation transcript:

DESIGN INVESTIGATE REHABILITATE Design and Quality Assurance of CFRP Repair of Concrete Pressure Pipes Rasko Ojdrovic Murat Engindeniz Mehdi Zarghamee ICRI Fall 2011 Convention, Cincinnati, OH 13 October 2011

Objective Outline the design approach and present QA requirements for repair of PCCP with CFRP liners. Introduce recent developments in the area (Draft AWWA Standard, the WaterRF Project). Highlight consequences of lack of proper QA. 2

Outline Introduction Design Criteria Draft AWWA Standard and the WaterRF Project QA Requirements (prior to, during, and after construction) Case Histories Conclusions 3

Distressed Pipe 4 PCCP

CFRP Liners No need for external access >15 year track record Draft AWWA Standard in progress 5 28 in. pipe

6 CFRP Design Approach Consider degradation level of host pipe Stand-alone versus composite design (with inner core) Use LRFD Limit StateLoads CFRP Rupture Internal pressure + External gravity loads BucklingExternal loads including Groundwater + Vacuum DebondingEmpty pipe under external loads Circumferential Design Limit StateLoads CFRP Rupture Internal pressure (Thrust, Poisson) + Temperature DebondingInternal pressure (Thrust, Poisson) + Temperature BucklingTemperature Longitudinal Design

7 The WaterRF Project Objective: Develop all necessary technical background for an LRFD-based AWWA Standard. Task 1Literature Review 2Design Requirements 3FEA of Soil-Structure Interaction 4Buckling of CFRP Liner 5Constrained Soil Modulus 6Bond Strength Test 7Hydrostatic Pressure Test 8Three-Edge Bearing Test 9Reliability Analysis Resistance Factor Adjustment Factor Time Effect Factor

8 The WaterRF Project – Analysis Determine: Load on pipe Failure pressure Shape factor, D f Rerounding coefficient, R c Debonding behavior Soil cover Bedding Backfill Rock Native Soil Account for: CFRP-pipe-soil interaction for different soils Installation condition Construction sequence Concrete cracking and CFRP debonding

9 The WaterRF Project – Testing Hydrostatic Three-Edge Bearing Bond Strength

Prior to Construction –Parties' Experience, Materials, Inspection During Construction –Testing, Installation, Independent Inspection, Curing After Construction –Inspection, Testing 10 QA Requirements

Involved Parties 11 Owner: Provides pipe design data and design loads (working and transient pressure, vacuum, live, etc.) Engineer: Designs repair, responsible for QA/QC of repairs. Manufacturer: Supplies a complete CFRP repair system. Must provide all required material data and supporting test results and installation guidance, and must license and train installers. Installer: Installs CFRP according to drawings and specifications; qualified by manufacturer and experienced in confined space installation of CFRP. Special Inspector: Engineer’s representative who monitors and documents all phases of construction for compliance with repair drawings and specifications and directs corrective actions. Testing Agency: Qualified testing laboratory independent from the Installer. Prior to Construction

Short-term 12 Laminate Qualification Engindeniz et al Characteristic Value (ASTM D7290) Design Value

Durability 13 Laminate Qualification Creep Rupture Engindeniz et al. 2011

14 T g > T max + 40 ° F Long-term water absorption <2% Curing performance documented with test data Temp. vs. % cure % cure vs. hardness NSF 61 compliance No VOC Resin Qualification Primer Tack Coat Thickened Epoxy Impregnating Resin Top Coat

Identify: Cracks Surface irregularities (waviness imperfection) Ovality (another imperfection) Quality of inner core concrete Affects: Design approach (standalone vs. composite) Surface preparation Buckling strength of CFRP liner Special details at cracks 15 Inspection of Host PCCP

Engineer’s or Owner’s representative Full time To verify all construction activities, including: 16 Independent Inspection Punctured steel cylinder Raised fabric edge During Construction

Independent Inspection 17 Condition of host pipe Surface preparation (minimum ICRI CSP3 required) Testing of mockup panels (bond strength) for onsite verification of construction quality Material storage, preparation, and application Application (details, timing) Control of air flow, temperature, and humidity Termination details Preparation of witness panels Post-installation inspection Curing (85% cure before service)

Minimum (3) 2 ft x 2 ft panels Prepared and tested by Installer (ASTM D4541) Witnessed by Inspector >200 psi required for at least 3 tests per panel –Failure mode may affect design approach! 18 Mockup Panel Testing

19 (2) Apply Primer (3) Apply Tack Coat and Thickened Epoxy (4) Impregnate Carbon Fabric (1)Prepare Surface Installation (6) Apply Top Coat (5) Lay Fabric

20 End Termination Detail Special Details Outlets Epoxy mortar

>85% cure required prior to refilling the pipeline –Proper work schedule –Curing temperature and duration (consider elevated temperature) Confirm with test data provided by Manufacturer –Temperature vs. % cure –% cure vs. hardness (Shore D or Barcol) 21 Curing

Prepared by Installer –3 panels minimum –1 layer of CFRP Witnessed by Inspector Tested by the Independent Testing Agency (ASTM D3039) Evaluated by Engineer 22 Witness Panel Testing After Construction

Constellation Energy Brandon Shores Power Plant –Lined (55) 102 in. PCCP under the switch yard (88,000 sq.ft application) in 22 days. –Lining of additional (51) 102 in. PCCP coming up. Miami-Dade Water and Sewer Authority –Ongoing CFRP repair program on more than (70) 48 in. to 96 in. PCCP. –Utility able to perform repairs by minimizing impact on community. APS Cholla Power Plant –Lined (20) 66 in. PCCP (22,000 sq.ft application) in 10 days. –Now planning additional CFRP repairs. 23 Case Histories Over 40 successful projects in the last 3 years …

24 Void in CFRP Improperly impregnated CFRP Lack of QA (by Others) Debonded CFRP

Conclusions Internal CFRP repair of pipes requires consideration of loads, limit states, and quality control procedures that are much different from those for other structures. Owners should be active participants in the repair process to ensure selection of qualified engineers, materials, installers, inspectors, and testing agencies. Manufacturers should be aware of the material qualification requirements, complete the missing data (e.g., creep, durability), and train Installers of their material. Contractors should be aware of all QA procedures for material preparation, installation, and curing. Lack of experience and quality control may lead to failure of CFRP liner. A design and installation standard is currently under development by AWWA. 25

26 Questions ? Rasko P. Ojdrovic, Ph.D., P.E. (781)