Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014
General ContractorBest Contracting Services, Inc. Architect of RecordGrossman Design Group Construction ManagerWillie Robinson
Contract Amount $918,600 Notice of Award06/17/14 Notice to Proceed07/21/14 Duration56 days Completion Date09/15/14
Contractor has mobilized & installed site surveillance Set up stairs & scaffolding to access roof and walls for demolition Demolition of exterior walls Removal of windows on west side of building A
Removal of Cement Plaster at Exterior Wall
Removal of Existing Window at Exterior Wall
Scaffold Installed at Rear Courtyard to Access Roof
Guardrail Installed at Lower Roof
Play Yard Equipment Protection