WEF SDC 2011 Expansion of Acton WWTP University of Guelph Team: Alexandra Chan Adam Erb Cynthia Mason Julia Veerman October 16, 2011
Outline Introduction Population Analysis Process Selection Phase 1 Design Modeling Noise & Odour Control Construction Phase 2 Design Economic Evaluation Conclusions and Recommendations
Review of Existing Facility
Problem Statement Current WWTP operating near peak capacity Need to increase capacity to accommodate projected growth in two phases Meet projected effluent criteria
ParameterCurrent (m 3 /day) Phase 1 Given (m 3 /day) Phase 2 Given (m 3 /day) Average Daily Flow (dry weather) Maximum Daily Flow (dry weather) Instantaneous Peak Flow (wet weather) Design Basis ParameterExisting Effluent Objective/Limit Proposed Effluent Objective/Limit BOD 5 (mg/L)2/5 TSS (mg/L)3/5 Total Phosphorus (mg/L)0.2/0.30.1/0.2 (Ammonia + Ammonium) Nitrogen (mg/L) Non-freezing period (May 1 to Nov 31) Freezing period (Dec 1 to April 30) 1.0/ / / /4.0 Unionized Ammonia (monthly average) (mg/L) Unionized Ammonia (any single sample) (mg/L) - -/0.1 -/ /0.08 Escherichia Coli (monthly geometric mean density) (#of organisms/100mL) 100/150
Predicted linear growth Assumed water saving devices at 10% Infiltration/Inflow at 204 L/c/d Population Analysis ParameterCurrentPhase 1 Given Phase 1 Calculated Phase 2 Given Phase 2 Calculated ADF MDF Peak
Process Selection Constraints Accommodate design flows Meet effluent discharge limits Use available land Be compatible with existing facility Criteria Cost effectiveness Integration with existing facility Environmental impact and footprint minimization
Phase 1 Design
Process Flow
Primary Clarifier
Add two rectangular clarifiers New volume 256 m 3 ADF SOR of 27.5 m 3 /m 2 /day Maximum day flow 62.5% TSS removal 40.3% BOD removal Chain & scraper sludge collector and scum removal system Primary Clarifier
Secondary Treatment
Two conventional plug flow activated ‐ sludge system with nitrification Accommodate 1275 m 3 /d required Target MLSS = 4000 mg/L SRT = 12 days Fine bubble aeration Positive displacement blower Designed for max day flow + additional feedback flow Aeration System
Two additional secondary clarifiers Limiting solid flux concept MLSS = 6620 mg/L Overflow = 31 m 3 /m 2 d Chain & scraper sludge collector and scum removal system Max day flow design Secondary Clarifier
Tertiary Treatment
85 mg/L liquid alum with 45% purity – 824 kg/d Addition point in activated sludge tank Chemical Addition
Dual media deep bed filtration Existing filters work well to meet limits Widely accepted in WWT Easily retrofit Leopold™ Type S™ Underdrain Air scour + surface wash backwash Max day flow design with one filter out of commission SLR of 7.2 m 3 /m 2 /h Filtration
UV selected as best disinfection method Trojan UV3000Plus™ system LP/HI lamp Automatic and continuous dose pacing Automated mechanical/chemical cleaning Automatic level controller Sized for peak flow UV Disinfection
Solids Handling
Sequential dual-stage digester series Add new series in parallel Methane gas collected for heating Thermophillic Stage 1 SRT 2 days Recirculation pump mixing Mesophillic Stage 2 SRT 8 days Bio-Solids Digester
Belt press drying after digester Polymer addition Increases solids concentration from ~3% to ~25% Cost-effective in disposal Reduces footprint Sludge Drying
Mass Balance
System Controls and Instrumentation Control strategy Increased control and monitoring Small relative capital cost Significant efficiency improvements Biological treatment Aeration accounts for up to 50% energy consumption Matched oxygen demand profile Intelligent feedback control for aeration, RAS, WAS
Clarifiers Monitoring Sludge pumping control mechanisms Digesters Control for feeding rates, recirculation, heating, withdrawal Tertiary Treatment Flow splitting SCADA Interfacing with SCADA for remote monitoring System Controls and Instrumentation
Hydraulic Profile
Projected peak influent concentrations and flows Proposed plant sizing Clarifier modeling based on Lessard and Beck dynamic model Activated sludge modeling completed using the IAWQ1 model Phase 1 – Model Inputs
BOD and NH3 water quality requirements met Model Shortcomings: Chemical phosphorous treatment or tertiary filtration not accounted for Phase 1 – Model Results
Currently no odour or noise issues Reduce odour and noise Buffer zone Housing potential equipment Odour and Noise Control
Completion in 24 months Best management practices: Construct in phases Protect waterways Provide training Conduct inspections Construction
Phase 2 Conceptual Design
Modify Plant B aeration basin configuration to plug flow + BNR Investigate: Membrane technology Phosphorus extraction Phase 2 Conceptual Design
Total Capital Cost Estimate = $24M Phase 1 – Capital Cost
Annual O&M Cost Estimate = $1.2M Phase 1 – O&M Cost
Total Capital Cost Estimate = $12M Phase 2 – Capital Cost
Expansion design to increase the Acton WWTP capacity Preliminary Phase 1 design Additional clarifier, disinfection, and anaerobic digestion trains CAS + nitrification Deep bed dual media filter Belt press Conceptual Phase 2 design Conclusions
Implement sewer system improvement plan Conduct more simulations Obtain more cost-specific information from manufacturers Conduct pilot tests Recommendations
Dr. Hongde Zhou, P.Eng., University of Guelph – Faculty Advisor David Arsenault, P.Eng., CH2M Hill – Consulting Advisor Rafiq Qutub, P.Eng., WEAO – SDC Sub- Committee Chair Lauren Zuravnsky, P.E., WEF – Design Competition Sub-Committee Chair Acknowledgements