Developing a Flexible Capital Improvements Plan That Serves as a Long-Term Funding Stream VSBA Conference Williamsburg, Virginia November 16, 2006.

Slides:



Advertisements
Similar presentations
School Closure/Consolidation Composition of School Closure Committee (SCC) Closure/Consolidation Criteria Timelines.
Advertisements

Recent Bond Accomplishments. Bordeaux Elementary Remodel.
AASBO Legislative Update Chuck Essigs 53 rd Annual Conference July 2006.
Summary of $475 million Bond Issue and Capital Financing Options Practiced By the State System of Higher Education in Oklahoma Practiced By the State System.
REFERENDUM 2014 Building Maintenance. Referendum 2014 Focused on providing a safe and healthy learning environment for students Fiscally responsible:
 Mechanical  Electrical  Safety/Security  Video surveillance  Fire safety  Access control  Enhanced Programming  Roofing/Structural/Site Work.
Detroit Public Schools FY 2005 Adopted Budget June 30, 2004.
Capital Grant Allocation Wind Up By: Financial Analysis and Accountability Branch Date: September 2010.
Once again the State adopted a budget without realistically solving its own major deficit problem. “Mid-Year Triggers” is the latest catch phrase for.
Overview of Property Assessed Clean Energy (PACE) Program San Antonio Office of Environmental Policy December 16, 2009.
Copyright 2004 Foreman Architects Engineers School Security From Common Sense to High Tech.
The coming storm: Managing Roanoke’s Stormwater Infrastructure Challenges Solutions for Roanoke’s future.
Proposed Budget Presentation APRIL 21, 2015.
Superintendent’s Recommendations for District Improvement Related to Facility Needs VICTORIA PUBLIC SCHOOLS.
SCHOOL DISTRICT OF LEE COUNTY TENTATIVE BUDGET HEARING JULY 29, 2010 SCHOOL DISTRICT OF LEE COUNTY TENTATIVE BUDGET HEARING JULY 29, 2010.
Fairfax County Public Schools Capital Improvement Plan FACILITIES & TRANSPORTATION August 7, 2013.
Missoula County Public Schools Overview of Planning January 2014.
Berkeley County School District FY General Fund Draft Budget Public Hearing Presentation June 25, 2013 Dr. Rodney Thompson, Superintendent Archie.
Manteca Unified School District 45 Day Revise Sept 9, 2003.
Budget Goals From our 2010/11 Budget: “High levels of student achievement” “Reduced gaps in student achievement” This means our goal is to maximize resources.
RFP# 99FY12 Ashlawn ES/Williamsburg ES June 8, 2012.
$18 million bond Construction of new Junior High campus Construction of safety improvements at Elementary School campus  Storm Shelter  Fire Safety.
A presentation of The New Georgian Heights Alternative Elementary School for Columbus City Schools Board of Education 2 February 2010.
1 Superintendent’s Proposed Budget Fiscal Year 2009 February 11, 2008.
Proposed New School District Does it make sense for Draper?
11 School Board Monitoring Report: Capacity Update Arlington Public Schools April 29, 2010.
TOWN OF NORTH EAST NEW TOWN HALL AND HIGHWAY FACILITY September 2015.
VSBA Conference November 17, Roanoke County Public Schools Roanoke, Virginia Mr. Drew Barrineau, CPA, School Board Member
LOCAL OPTION SALES TAX FOR EDUCATION APPROVED BY THE BOARD OF TRUSTEES SEPTEMBER 29, 2015.
LOCAL OPTION SALES TAX FOR EDUCATION TIMELINE AND PROPOSED PLANS AS OF MAY 26, 2015 *THE DISTRICT CONTINUES TO SEEK INPUT/SUGGESTIONS FROM BOARD MEMBERS,
Maintenance & Operations Replacement Levy and School Improvements Bond Election Day: February 9, 2016.
5-year Capital Improvement Plan FY2015 Capital Budget.
A Blue Print for Collecting School Facilities Data.
New Market Skills Center Draft 10 Year Major Projects Capital Plan Administrative Council December 2, /02/20111.
FY08 PARKING PERMIT FEE PROPOSAL November 20, 2006.
1 West Contra Costa Unified School District January 31, Second Interim Financial Report.
FEBRUARY 22, 2016 FY 2017 County Administrator’s Recommended Budget.
September 15, 2008 Budget Workshop Spending Authority.
Making Our Facilities Better Board of Directors Update – Wednesday, July 24, 2013.
MODERNIZATIONS “The First Five” Golden West Elementary Lathrop Elementary Lincoln Elementary Sequoia Elementary Shasta Elementary December 8, 2015.
Riley County – USD 378 Community Forum 2 23november2015 Riley County School District.
MODERNIZATIONS MEASURE G OVERSIGHT COMMITTEE September 8, 2015.
SMITHVILLE R-II SCHOOL DISTRICT Tradition of Excellence The Power of One … One Community … One Future! November 4, 2014 SMITHVILLE R-II SCHOOL DISTRICT.
District Local Planning Committee Orientation Part 2 Trimble County Schools Kentucky Department of Education Division of District Support - District Facilities.
Indianapolis Public Public Hearing – Proposed 2014 Budget Thursday, August 15, 2013 Transportation Corporation.
Wahoo Public School District Facility Planning Update April 18, 2016.
LOCAL OPTION SALES TAX FOR EDUCATION APPROVED BY THE BOARD OF TRUSTEES SEPTEMBER 29, 2015.
1.  Quick Overview of the History and Need  What is Planned for the Fire Department  What is Planned for the Police Department  Financial Details.
FY 2016 Budget Workshop June 11, 2015 Brian Maxwell, City Manager Dan Buckley, Deputy City Manager Mike Loftin, Finance Director 1.
LOCAL OPTION SALES TAX FOR EDUCATION APPROVED BY THE BOARD OF TRUSTEES SEPTEMBER 29, 2015.
Review of 2016–2021 Strategic Budget Plan Development Process and 2016 Budget Assumptions Financial Administration and Audit Committee April 14,
Harness the Power of your Operating Budget to Enhance your Learning Environment MASBO Winer Conference – Jackson, MS.
White Pigeon Community Schools
Consolidated Central Office Building
Dedham Public Schools proposed FY14 operating budget
Dr. Joseph Meloche Superintendent of Schools Mrs
BUDGET TOWN HALL MEETING
Cave Spring High School Community Meeting
OSPI Capital Budget School Facilities & Organization
Capital Outlay Workshop
Capital Improvement Plans
Roanoke County Public Schools Budget
Recent Bond Accomplishments
Master Facilities Committee Evaluation and Identification
Chimacum District Facility & Program Plan
New Market Skills Center Draft 10 Year Major Projects Capital Plan
Presented by: Mrs. Phyllis Alpaugh, Superintendent of Schools &
Pine Valley Central School Proposed Budget April 16, 2019
Roanoke County Public Schools Budget
FY Capital Improvement Program Draft
Presentation transcript:

Developing a Flexible Capital Improvements Plan That Serves as a Long-Term Funding Stream VSBA Conference Williamsburg, Virginia November 16, 2006

INTRODUCTION Mrs. Marion Roark, School Board Member Mr. Drew Barrineau, School Board Member Roanoke County Public Schools DEVELOPING A FACILITIES IMPROVEMENT PLAN Mr. Richard Flora, Retired Director of Facilities Roanoke County Public Schools DEVELOPING A CAPITAL FINANCING PLAN Mrs. Penny Hodge, Assistant Superintendent of Finance Roanoke County Public Schools CLOSING Mr. Drew Barrineau, School Board Member Roanoke County Public Schools

Introduction Mr. Drew Barrineau, School Board Member Roanoke County Public Schools

Who we are………. Enrollment approx. 15,000 students 30 schools Approximately 2,300 employees $127,000,000 annual budget

Insufficient resources on both sides Need to renovate a school each year while addressing deferred maintenance issues County needs new public safety center and jail Why did we develop plan?

Permanent, self-funding source of revenue Deferred maintenance issues No tax increase Plan must address….

Consider BOS partners in K-12 Win-win for both sides – not competing for same capital dollars Timetable allows both sides to make capital decisions Both boards can accomplish more together than apart Relationship with BOS

Developing a Facilities Improvement Plan Mr. Richard Flora, Retired Director of Facilities Roanoke County Public Schools

Facility Study Evaluation of Needs Recommendations for Improvements Components of a Facilities Improvement Plan

Inventories school facilities for the following: - Capacity, enrollments and average class sizes - Program provisions and functional issues - Building sizes, ages and construction types - Site conditions, including circulation - Exterior and interior building components - Mechanical, plumbing and fire protection - Electrical and lighting systems Identifies deficiencies in each school Provides an estimate of the costs to remedy the deficiencies Makes recommendations to the School Board Goals of a Facility Study

Factors in Determining Deficiencies Projected Enrollments Pupil/Teacher Ratio Site Circulation Safety and Security Heating, Ventilation, Air Conditioning & Electrical Pre-K & Special Ed. Programs

Projected Enrollments Rationale for determining the projected enrollments: Elementary school enrollments were derived from utilizing the school’s current enrollment figures, historical enrollment data and the current growth pattern. Middle school enrollments were calculated by utilizing the current enrollment figures from each elementary school feeder for the 3rd, 4th, and 5th grades. High school enrollments were calculated by utilizing the current enrollment figures from each middle school feeder for the 6th, 7th, 8th, and 9th grades. Determining Deficiencies

Pupil/Teacher Ratio All facilities were sized to accommodate students with a pupil/teacher ratio of 20/1 for grades K-5 and 16/1 for Pre-K. For Grades 6-12, a pupil/teacher ratio of 25/1 was calculated. A 20/1 ratio is currently being used through the second grade. This ratio will effect the operating capacity of each school facility by approximately 20 percent. Determining Deficiencies

Site Circulation Separation of bus, car, and pedestrian traffic was reviewed for both safety and convenience. Bus loading and unloading should occur in an area where cars are prohibited. The area should be large enough to accept all buses without interfering with car or pedestrian traffic. Identification and location of the school’s main entrance and proximity to parking areas was reviewed. Visitors and staff should not have to cross car or bus traffic to enter the building. Determining Deficiencies

Safety and Security Administrative offices should be able to closely monitor the main entrance and control entry. All exterior doors should be able to be locked, utilizing an acceptable hardware, from the outside without the use of an interior restraining device. Acceptable lighting levels, spacial definition of areas, and surveillance systems should be included in any major renovation or addition. Determining Deficiencies

HVAC and Electrical Heating, Ventilation, Air Conditioning and Electrical systems were evaluated by the school’s maintenance department. The criteria used to determine the HVAC and electrical components condition was based on the age of the particular component and compared to typical life cycle expectancies. Those components which have exceeded their functional life and are, therefore, prone to failure were identified.. Determining Deficiencies

Pre-K and Special Ed. Pre-K and self-contained Special Ed. programs were included in the prototypical space programs. Pre-K classrooms were evaluated at every elementary school to determine if classroom space will exist based on the projected enrollments. Pre-K classrooms are larger and have different amenities than a typical classroom. Each elementary school may require an addition or renovation in order to accommodate the additional Pre-K classrooms. The number and locations of existing or proposed self-contained special ed. programs was provided by the Special Ed. Department. Determining Deficiencies

Facility Study Evaluation of Needs Recommendations for Improvements Components of a Facilities Improvement Plan

Prototype Space Programs Elementary School Small Medium Large Middle School High School

MOUNTAIN VIEW ELEMENTARY NEEDS OVERVIEW: HVAC improvements or replacements Widen or replace existing narrow corridors Add corridors to classrooms where none currently exist Expand administrative area to include guidance and nurse Additional classrooms Upgrade of kitchen equipment Additional general storage Expand media center to include office and storage Address ADA concerns Re-key school and add video cameras for safety and security Improve general lighting Improve vehicular circulation. Add new energy efficient windows

Priority Criteria for Evaluation of Needs for Facilities Improvements SCENARIO ONE Reflects a score based on a criteria applying a 20/1 pupil teacher ratio through all grades. Uses the prototype school at the elementary, middle and high school levels. The needs were given weight based on the current value placed on each instructional area.

SCENARIO TWO Reflects a score based on the criteria applying a 20/1 pupil teacher ratio in elementary schools and a 25/1 pupil teacher ratio in middle and high schools. The prototype for all schools was also used in this scenario. The needs were given weight based on the current value placed on each instructional area. Priority Criteria for Evaluation of Needs for Facilities Improvements

SCENARIO THREE Reflects a score based on the criteria applying a 20/1 pupil teacher ratio in elementary schools and a 25/1 pupil teacher ratio in middle and high schools. The prototype for all schools was not used in this scenario. The needs were given weight based on the current value placed on each instructional area. Priority Criteria for Evaluation of Needs for Facilities Improvements

Facility Study Evaluation of Needs Recommendations for Improvements Components of a Facilities Improvement Plan

Recommendations for Facilities Improvements “SCENARIO-THREE” was used to determine the priority for facilities improvements. This scenario best reflects the immediate needs using the most realistic criteria. A pupil teacher ratio of 20/1 in elementary schools is already becoming a reality. It is expected that the progress made to date will be sustained in the future. Because of current funding challenges, moving to a 20/1 pupil teacher ratio in the secondary schools will, most likely, not become a reality until some future date. Although using prototype schools is desirable, it makes more sense to apply the prototype concept to the renovation process and not as a part of the evaluation process. Conceptual designs and the cost estimates were provided with this study integrated the “prototypical school” as a factor in the elements of this report.

Developing a Capital Financing Plan Mrs. Penny Hodge, Assistant Superintendent of Finance Roanoke County Public Schools

Phase 1 - $48 million (began in 1997) New high school New elem school Renovate 3 schools Phase 2 - $23 million (began in 2002) Renovate 3 schools Stadium renovations Phase 3 - $65 millionDebt capacity exhausted Background

30 schools in Roanoke County 8 built/renovated in Phase 1 or 2 22 schools remaining with capital needs 75% of schools > 30 years old County government needs growing $28M Public Safety Facility planned What we were facing in 2005…..

Our concept hinges upon….. Annual commitment of set amount of new money Use of year end balances Complimentary school and county financial policies

Past practices that helped… In budgeting …….revenue sharing allocation In year end ………rollover of year end surplus

Board Commitment SB will set aside $300,000 of new money each year for capital needs BOS will set aside $300,000 of new money each year for capital needs = $600,000 incremental new money every year for School and County capital needs

Policies Needed Establish School and County Capital Reserves Use of School and County Year End Balances

Reserves Created Combined Debt Payment Reserve School Major Capital Reserve School Minor Capital Reserve County Major Capital Reserve County Minor Capital Reserve

Combined Debt Payment Reserve Began with $2M annual contribution in 1996 (to build new high school) Add new $600,000 from county & schools each year (beginning in ) Plus debt drop-off over time Plus economic development incentive drop- off over time Results in incrementally growing reserve

This is how it grows…… $2,000, $2,600, $3,200, projected $3,800,000

School Major Capital Reserve Use for projects on annually adopted CIP Land as it becomes available Fund with 2/3 of YE balance Plus state construction grants Pay cash for smaller projects Supplement borrowing for larger projects

School Minor Capital Reserve Use for smaller capital projects (<$500,000) and one-time needs Fund with 1/3 of YE balance (up to $1M) Plus sale of land and equipment Can be used for A&E to get CIP projects planned Can also be used for CIP projects

County Major Capital Reserve Use for major projects on County CIP Fund with YE revenues in excess of budget after meeting Unappropriated Balance Policy limits

County Minor Capital Reserve Use for minor county capital projects Fund with YE expenditure savings

What can we fund now? $10M Schools$20M County $10M Schools$10M County $10M Schools $10M Schools $10M County Future funding pattern of 2 years schools and 1 year county projects.

Success is based upon… Properly timed bond issues Available cash accumulated in Major/Minor reserves No tax increases needed Funds $40M for schools and $40M for county over next 5 years Ensures funding for future School Boards

Awards VML 2006 Achievement Award VGFOA 2006 Innovations in Finance Award

Taking the Next Step Increase the new funds each year beyond $600,000 because: Rising construction costs Reality hits To keep on same or better CIP path for copies of slides

Questions Roanoke County Public Schools