Coronado Elementary School Project Status Update 05/13/14
Construction Manager:Cary Talbott (SGI) Project Engineer:Marcus Blackmon (Amanco) Inspector of Record:Kris Gilbert Architect of Record:Sisi Meng (WLC Architects) General Contractor: Lathrop Construction Associates
View: Southeast. Project Architect Rendering. Building A (2 Story Administrative Building). Main Drop-off. l
Project Architect Rendering of Playground (Conceptual)
The Coronado E.S. Reconstruction Project consists of 64,738 square feet of new classroom, administrative, multipurpose, kindergarten and support facilities. The Project also includes extensive site work, a bio-swale, site furnishings, covered walkways, State-of-the-Art Technologies, and a myriad of upgrades that will greatly enhance WCCUSD Student’s learning experience.
Project Duration:510 (Calendar Days) Notice To Proceed Date: January 6, 2014 Completion Date:May 31, 2015 Percent Complete: 13% Base Contract Amount:$26,974,910.00
View: Northeast. Activity: Clear & Grub; Demo. Coronado Elementary School Project View: Northeast. Activity: Clear & Grub: Demo.
View: Southwest. Activity: Mass Grading Coronado Elementary School Project View: Southwest. Activity: Mass Grading.
View: Eat. Activity: Lime Treat Soil for Building Pads only. Coronado Elementary School Project View: Eat. Activity: Lime Treat Soil for Building Pads only.
View: Northeast. Activity: Building Pad A (East) Layout. Coronado Elementary School Project View: Northeast. Activity: Building Pad A (East) Layout.
View : East. Building A. Activity : Excavate Trenches for Footings. Coronado Elementary School Project View: East. Building A. Activity: Excavate Trenches for Footings.
View: East. Building K (Kindergarten). Activity: Footing Placement Coronado Elementary School Project View: East. Building K (Kindergarten). Activity: Footing Placement
View: West. Building A. Activity: Preparation for Slab on Grade by placing vapor barrier and rebar. Coronado Elementary School Project View: West. Building A. Activity: Preparation for Slab on Grade by placing vapor barrier and rebar.
View: South. Building M (multipurpose room). Activity: Slab on Grade. Coronado Elementary School Project View: South. Building M (multipurpose room). Activity: Slab on Grade.
. Coronado Elementary School Project View: North. Building C (classrooms). Activity: Slab on Grade.
View: Southeast. Building M (multipurpose room). Activity: Structural Steel Erection. Coronado Elementary School Project View: Southeast. Building M (multipurpose room). Activity: Structural Steel Erection.