Update on FCPS Construction/Renovation Projects August 2009.

Slides:



Advertisements
Similar presentations
Update on FCPS Construction/Renovation Projects June 2009.
Advertisements

Update on FCPS Construction/Renovation Projects July 2009.
WEEKLY PHOTO REPORT WEEKLY PHOTO REPORT September 16 th, 2013 – October 25 th, 2013.
Update on FCPS Construction/Renovation Projects September 2009.
Update on FCPS Construction/Renovation Projects May 2009.
CURRENT WORK West Wing - Exterior: Masonry and shingles finished, fascia and soffit work ongoing - 1 st Floor: Final coat of paint, casework installed,
MARPLE NEWTOWN SCHOOL DISTRICT FACILITIES. Maintenance & Small Projects Planned for Summer 2007 New carpet at Worralls office New fencing at Worralls.
Update on FCPS Construction/Renovation Projects April 2009.
With the passage of the May 2009 NLISD Bond Election, campuses made improvements and repairs. New flooring in the elementary schools, updated kitchen.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Newark CSD Phase II Capital Improvement Project Board of Education Report August 2013.
Finance and Facilities. DuPage County, IL EAV Growth History (Five Year Average: -2.15%)
Bartholomew Consolidated School Corporation Additions and Renovations to Columbus East and North High Schools Additions and Renovations to Columbus East.
Kitchen New sandwich prep table. Kitchen New pizza prep table.
DG Inyorkern Weekly Project Summary 1/17/14. DG Inyokern 1/17/14: Percentage Overview Demolition: Pad Prep: 100% Finished and ceriified Footing & Foundation:
Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: W/S Construction Substantial Completion Date:August, 2010 Contract.
October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara.
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.
SCHEMATIC DESIGN PRESENTATION
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
TECHNICAL ASSIGNMENT #1 – NATHAN BRASKEY SUNNYVALE PLAZA [Cooper Carry, Inc.]
HIGHLAND PARK BOND WORK The final results will be AMAZING!
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Construction Update August 18, 2010 Rob Gaertner, P.E. Director of Facilities.
Architect Drawing of New Entrance. Location Location of Phase II Construction Project – Old tennis courts west of the existing building.
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
Update on FCPS Construction/Renovation Projects March 2009.
J&J CONTRACTORS’ MAJOR PHASE DRAWING GUIDE HAFB 1305 HVAC Repair Solicitation # MXRD /8/09 1. Chiller line-horizontal work 2 weeks (2 dn shift)
Capital Improvement Program for September 9, 2014.
Understanding Building Systems. Physical Layout Building Plans Architectural Plans Structural Plans Mechanical Plans Plumbing Plans Electrical Plans HVAC.
Learning, Health, and Safety Capital Project Alternates and Change Order
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Elevating the Quality of Life in the District. AFTER RENOVATION BEFORE RENOVATION.
Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Construction Foundations of Technology Construction © 2013 International Technology and Engineering Educators Association STEM  Center for Teaching and.
Salmon River CSD Capital Project Phase II Monthly Status Report March & April 2016.
Miller Driscoll Building Committee Construction Update Thursday April 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations.
WBS Experiment Infrastructure: LArTF GPP Project Status Dixon Bogert Prepared for the MicroBooNE Collaboration Meeting 11/02/12.
LIFE CYCLES OF AIKEN COUNTY PUBLIC SCHOOLS CONSTRUCTION PROJECT October 8, 2013.
White Pigeon Community Schools
Bond Oversight Committee
Bond Oversight Committee
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
School Improvement Bond Projects
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Capital Improvements Presentation
Dr. Joseph Meloche Superintendent of Schools Mrs
BURROUGHS HIGH SCHOOL PROJECT STATUS REPORT February 2017 Fast Facts
BURROUGHS HIGH SCHOOL PROJECT STATUS REPORT March 2017 Fast Facts
Minuteman Vocational Technical Regional High School Progress
Carleton College Summer 2018 Science and Campus Construction Plan
How & When to Get Permits for Work in Your Home
Minuteman Vocational Technical Regional High School Progress
2007 Bond Issue Capital Improvement Program
Value of contract: Length of contract: Contract start date:
Building & Property Committee
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
Minuteman Vocational Technical Regional High School Progress
EAST PENNSBORO AREA SCHOOL DISTRICT
Presentation transcript:

Update on FCPS Construction/Renovation Projects August 2009

Cassidy Elementary – Renovation  Architect: Tate.Hill.Jacobs: Architects  General Contractor: D.W. Wilburn, Inc.  Substantial Completion Date:August, 2010  Contract Sum:$9,061,000  Change Orders to Date (1):$2,  Current Phase:1 (On Schedule)  Estimated Completion:19% August 2009

Cassidy Elementary – Renovation Rendering of Final Façade August 2009

Cassidy Elementary – Renovation  Work Completed in Last 30 Days:  Storm sewers installed on south side and across new front parking lot.  Grading complete around new Morton Parking Lot. Concrete curbs and subgrade installed.  Grading started at sidewalks and playground. Concrete retaining walls in place.  Fire Protection water pit installed at Cassidy Rd. Gas main installed. Sanitary sewer manholes and connector piping installed.  Demolition continues with new stage opening and new openings and doorways for corridor extensions. Stairway demolition is approximately 75% complete.  Foundations for stage complete.  Music Classroom addition foundation, 1 st floor slab, 2 nd floor joist and slab installed. Masonry bearing walls and steel column/beams complete. Interior masonry partition walls on going.  Plumbing rough-ins have continued as masonry walls are installed.  Electric conduits and rough-ins continue in Admin Addition above ceiling and in masonry walls as needed. August 2009

Cassidy Elementary – Renovation  Current Work Effort (August):  Storm sewers will continue as site work allows.  New 3” domestic water main service will complete.  Site grading will complete around the playground. Sidewalk/paving work will complete at playground area.  Chimney demolition to begin the first week of September – pending confirmation that chimney swifts have vacated.  Stage concrete slab and masonry bearing walls to be complete. Roof joists for Music Rm. and Stage Addition to be in place.  HVAC ducting and piping to start in the Admin. Addition and existing building in Phase 1 area.  Sprinkler piping to start in the Admin. Addition and existing building in Phase 1 area.  Electric conduit and rough-ins to continue. August 2009

Cassidy Elementary – Renovation New Admin. Addition 2 nd Fl. New Playground Retaining Walls August 2009 Interior Gym New Stage & Music Room Addition

Russell Cave Elementary – Renovation  Architect: Pearson & Peters Architects  General Contractor: Congleton-Hacker Construction  Substantial Completion Date:August, 2010  Contract Sum:$5,001,150  Change Orders to Date (2):$12,  Current Phase:1 (On Schedule)  Estimated Completion:30% August 2009

Russell Cave Elementary – Renovation Rendering of Final Façade August 2009

Russell Cave Elementary – Renovation  Work Completed in Last 30 Days:  Exterior walls at new addition are complete, block and brick. Interior walls are complete.  Roof trusses and metal deck at new addition have been installed.  Interior of Kitchen/Cafeteria is complete.  Renovation of (4) classrooms on the south side continues.  Masonry restoration on the exterior of the original building in process.  New electric service for new addition to be complete before school begins.  Current Work Effort (August):  Interior ramp and stair in new addition will be poured.  Masonry restoration of the east wall will be completed.  Roof at new addition will be installed.  Install new ductwork in new addition and four classrooms.  Install overhead electrical rough-in and temporary power and lights in new addition and four classrooms.  Construction fence will be reinstalled around new addition before the start of school. August 2009

Russell Cave Elementary – Renovation New Addition August 2009 New Serving Line in Kitchen Interior of Cafeteria

Arlington Elementary – Renovation  Architect: RossTarrant Architects  General Contractor: W/S Construction  Substantial Completion Date:August, 2010  Contract Sum:$9,920,194  Change Orders: $36,900 (#1--Demo)  Current Phase:1 (On Schedule)  Estimated Completion:8% August 2009

Arlington Elementary – Renovation Rendering of Final Façade August 2009

Arlington Elementary – Renovation  Work Completed in Last 30 Days:  Selective demolition in existing building.  Earthwork and Site utilities are ongoing.  Building foundations are in place at the gym, kitchen and cafeteria.  Relocation of utilities and installation of manhole in Arceme are in progress.  Under slab utilities at custodial receiving and Mechanical room are in place.  Masonry and hollow metal door frames started on west wall of the gymnasium.  Current Work Effort (August):  Demolition of existing masonry at building to remain and construction of replacement wall.  Site storm sewer installation.  Underground utilities will continue.  Masonry wall construction at the addition continues.  95% complete with demolition in existing building.  Continue utility rough-in at the existing building.  Installation of temporary roof at the existing building. August 2009

Arlington Elementary – Renovation Demolition Work Earthwork & Site Utilities August 2009 Foundation WorkUnder Slab Utilities

Bryan Station Middle – Renovation  Architect: Clotfelter-Samokar Architects  General Contractor: Preston Construction Group  Substantial Completion Date:August, 2010  Contract Sum:$10,769,400  Change Orders to Date (1):$8,667  Current Phase:1A (On Schedule)  Estimated Completion:29% August 2009

Bryan Station Middle – Renovation Rendering of Final Façade August 2009

Bryan Station Middle – Renovation  Work Completed in Last 30 Days:  Cafeteria prepared for student use. Finishes and HVAC completed in this area.  Corridors barricaded from construction areas and safe egress signs put in place.  New sanitary sewer lines nearly complete.  New kitchen and kitchen dock work progressing.  Current Work Effort (August):  Installing new HVAC rooftop equipment.  Installing footers for new Music Suite addition at rear of building.  Concentrate on library renovation for turnover to owner as soon as possible.  Repair Wood gym floor. August 2009

Bryan Station Middle – Renovation Foundations for New Addition Earthwork Prep for New Addition August 2009 Concrete Poured at New DockCafé Prior to New Floor

Leestown Middle – Renovation  Architect: Lucas/Schwering Architects  General Contractor: D.W. Wilburn, Inc.  Substantial Completion Date:August, 2010  Contract Sum:$11,182,000  Change Orders to Date (1):$2,  Current Phase:1, 1a, 1b (On Schedule)  Estimated Completion:16% August 2009

Leestown Middle – Renovation Rendering of Final Façade August 2009

Leestown Middle – Renovation  Work Completed in Last 30 Days:  Phase 1demolition efforts continue.  Structural shoring at Cafeteria and in Corridor.  Kitchen foundation wall and plumbing rough-in complete.  Existing utilities have been tied back in.  Interior masonry wall erection started.  Current Work Effort (August):  Demolition in Phases 1, 1a & 1b will continue.  Floor slab for the new Kitchen will be poured.  Electrical and Plumbing rough-ins on-going.  Masonry load bearing masonry at Kitchen to start.  Erection of new Fire Walls to begin.  Masonry restoration has begun.  Erection of structural steel to begin. August 2009

Leestown Middle – Renovation Kitchen Plumbing Rough In Demo for New Café Window August 2009 Admin. Suite Demo Looking From Courtyard Demo Admin. Suite

Lafayette High Stadium – Replacement  Architect: Strand & Associates  General Contractor: Judy Construction Co. (proposed)  Substantial Completion Date:Fall 2010 (est.)  Contract Sum:$4,333,000 (pending Board approval)  Change Orders to Date:$0  Current Phase:Phase 1 August 2009

Lafayette High Stadium – Replacement Existing Campus August 2009

Lafayette High Stadium – Replacement Existing Football Stadium August 2009

Lafayette High Stadium – Replacement New Football Stadium August 2009

Central Bus Garage – Adaptive Reuse  Architect: Lucas/Schwering Architects  General Contractor: James R. Leake & Sons, Inc.  Substantial Completion Date:August, 2009  Contract Sum:$2,782,000  Change Orders to Date (2):$10,  Current Phase:Construction  Estimated Completion:51% August 2009

Central Bus Garage – Adaptive Reuse Façade August 2009

Central Bus Garage – Adaptive Reuse  Work Completed in Last 30 Days:  Exterior  Bollards installed  Light pole bases have been installed  Dumpster pad completed  Exterior plumbing completed  Generator gas line installed  Waste management systems in place  Fluid storage steel erected  Interior  Mezzanine in place and elevated slab poured  Underslab plumbing in place  Slab under mezzanine has been placed  Bus lifts poured in place  Excavation complete for trench drains August 2009

Central Bus Garage – Adaptive Reuse  Current Work Effort (August):  Parking lot to be completed  Wheel stops at the bus parking to be placed  Paint booth to be complete by the 21st  Interior MEP continues August 2009

Central Bus Garage – Adaptive Reuse August 2009 New Fluid Storage Addition Bus Parking Equipment Installation

Tonight’s Agenda Items Project Agenda Item  Miles Point Way (Bus Garage)  Approval of Change Order #3 Total Cost: $18,  Henry Clay High Girls Softball Field  Approval of Bid, Proposed Contract and Revision to BG-1 Project Application WS Construction: $746,830 Total Project Cost: $898, August 2009