Welcome to the Jurisdiction of Unit-1 R.S.R.D.C. Ltd., Ajmer
ORGANISATION CHART OF RSRDC UNIT-1, AJMER RE Rakesh Kr. Jain AAO Sh. Shiv Kr. Sharma ARE Sh. Brijesh Kr. Mathur ARE Sh. N.K. Tak ARE. Sh. Avinash Kumar ARE Sh. J.P. Kansal ARE Sh. Harsh Rai J.En. (Elect.) Sh. O.P. Sharma
Financial Work Load in Unit Rs. in Lacs. S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – I Sh. Brijesh Mathur 1 Parking space at G/F & F/F, Office chamber on S/F and Auditorium on 3rd floor at BSER, Ajmer B.S.E.R., Ajmer 1400.00 288.76 1111.24 2 1st floor & 2nd floor over old answer book at BSER, Ajmer Total 106.00 1506.00 49.34 338.10 56.66 1167.90
Financial Work Load in Unit Rs. in Lacs. Financial Work Load in Unit S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – II Sh. N.K. Tak 1 Urban Hatt Bazar, Ajmer Industries Deptt. 190.00 113.68 76.32 2 LSQ at GRP Campus, Nareli, Ajmer (Part-IV) Police Deptt. 434.72 334.18 100.54 3 USQ+LSQ at 11th RAC Battalion, Nareli, Ajmer (Part-I & II) 555.25 378.25 177.00 4 Company Store & Office for 11th RAC Battalion Nareli, Ajmer 21.00 7.90 13.10 5 1st floor on computer centre (Arya Bhatt Bhawan) at MDSU Ajmer M.D.S.U., Ajmer 79.40 53.01 26.39 6 Women Hostel at MDSU Ajmer 180.91 7.62 173.29 7 Academic Staff College (Guest House) at MDSU Ajmer Total 75.00 1536.28 11.05 905.69 63.95 630.59
Financial Work Load in Unit Rs. in Lacs. S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – III Sh. Avinash Kumar 1 Part of Academic Building and Workshop at Govt. Mahila Engg. College, Ajmer Principal Women Engg., Ajmer 257.00 253.02 3.98 2 Compound wall at Mahila Engg. College, Ajmer 12.00 7.00 5.00 3 Internal Road at Mahila Engg. College, Ajmer 35.89 6.55 29.34 4 Canteen Cum Guest House at Engg. College, Ajmer Engg. College Society, Ajmer 42.00 25.90 16.10 5 USQ + LSQ at GRP Campus, Nareli, Ajmer (Part-I, II, III & V) Police Deptt. 1138.56 875.16 263.40 6 2ndfloor on Management block at MDSU, Ajmer MDSU, Ajmer 81.83 53.19 28.64
Principal Foof Craft Institute S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – III Sh. Avinash Kumar 7. Social Science Block at M.D.S.U., Ajmer (Development Work) MDSU Ajmer 305.52 223.86 81.66 8 (A) App. Road and Parking Shed at Management Block at MDSU, Ajmer 48.22 31.36 16.86 (B) C.C. Interlocking paver block at Bharti niwas at MDSU, Ajmer (C) Laying & Jointing Pipeline UG Tank to Girls Hostel at M.D.S.U., Ajmer (D) Tube Well submersible pump set laying & jointing GI Pipe. 9 10 Environmental Sc. Building at MDSU, Ajmer Dormetory on 1st Floor at Food Craft Institute at Ajmer M.D.S.U., Ajmer Principal Foof Craft Institute Total 238.62 38.00 2197.64 0.00 1476.04 721.6
Financial Work Load in Unit Rs. in Lacs. S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – IV Sh. J.P. Kansal 1 Ad.Trainee at PTS Kishangarh. Police Deptt. 150.00 130.06 19.14 2 Hostel Building for Trainee at PTS., Kishangarh 100.00 54.79 45.21 3 Adm. Block at RPL Hadirani Battalion, Ajmer 125.00 31.30 93.70 4 Adm. Buidling for Police Outpost at Shastri Nagar, Ajmer 11.00 9.17 1.83 5 Adm. Building for Police out post at Gandhi Nagar, Kishangarh 6.00 5.00
6 Adm. Building for police out post at Saket Nagar, Beawar Police Deptt. 11.00 5.55 5.45 Adm. Building for Police Police Deptt. out post at Kasai Mohalla, Beawar 2.27 8.73 8 Adm. Building for Zone officer for CID office, Ajmer 31.50 1.40 30.10 9 30 Mens Barracks at PTS, Kishangarh Total 17.00 467.50 5.76 246.30 11.24 221.20
Financial Work Load in Unit Rs. in Lacs. S. No. Name of Work Client Deptt. A& F Sanction Expenditure till date Balance Work ARE – V Sh. Harsh Rai 1 100 men barrack at RPLHadirani Battalion (Part-I ) Police Deptt. 100.00 2.91 97.09 2 100 Men Barrack at RPL Hadirani Battalion, Ajmer (Part-II) Total 200.00 0.58 3.49 99.42 196.51
Bharat Vidhya Adhayan Sankul at M.D.S.U., Ajmer Important Works Completed during last 5 years Bharat Vidhya Adhayan Sankul at M.D.S.U., Ajmer Completion Cost – Rs. 1.10 Crs. Foundation Stone laid by Hon’ble Minister for Higher Education Rajasthan State Sh. Ghanshyam Tiwari in March, 07 Inaugurated by Prof. Sukhdev Thorat Chairman UGC on 12.10.09
Boy’s Hostel at M.D.S.U., Ajmer Important Works Completed during last 5 years Boy’s Hostel at M.D.S.U., Ajmer Completion Cost – Rs. 1.65 Crs. Foundation Stone laid by Hon’ble Minister for Higher Education Rajasthan State Sh. Ghanshyam Tiwari in March, 07
Girls Hostel at M.D.S.U., Ajmer Important Works Completed during last 5 years Girls Hostel at M.D.S.U., Ajmer Completion Cost – Rs. 1.40 Crs. Completion Cost – Rs. 1.65 Crs. Foundation Stone laid by Hon’ble Minister for Higher Education & PWD Rajasthan State Sh. Lalit Kishor Chaturvedi on 24.09.1998 Inaugurated by Honble Mininster for Higher Education Rajasthan State Govt. Sh. Ghanshyam Tiwari on 21.08.2006
Social Science Block at M.D.S.U., Ajmer Important Works Completed during last 5 years Social Science Block at M.D.S.U., Ajmer Completion Cost – Rs. 3.05 Crs. Foundation Stone laid by Hon’ble Minister for Mahilla Bal Vikas & JanJati Kashetrya Vikas, Rajasthan State Sh. Kankmal Katara on 01.06.2005. Inaugurated by Honble Mininster for Higher Education Rajasthan State Govt. Sh. Ghanshyam Tiwari on 10.08.2006.
Yoga Centre at M.D.S.U., Ajmer Important Works Completed during last 5 years Yoga Centre at M.D.S.U., Ajmer Completion Cost – Rs. 0.63 Crs. Foundation Stone laid by Hon’ble Minister for Higher Education & PWD Rajasthan State Sh. Lalit Kishor Chaturvedi on 24.09.1998 Inaugurated by Honble Mininster for Higher Education Rajasthan State Govt. Sh. Ghanshyam Tiwari on 29.06.2007.
Women Engineering College at Ajmer Important Works Completed during last 5 years Women Engineering College at Ajmer Completion Cost – Rs. 2.57 Crs. Foundation Stone laid by Hon’ble Chief Minister Govt. of Rajasthan Smt. Vasundhra Raje on 30.04.07 Handed Over in November, 2009
Women Engineering College at Ajmer Important Works Completed during last 5 years Women Engineering College at Ajmer Completion Cost – Rs. 2.57 Crs. Foundation Stone laid by Hon’ble Chief Minister Govt. of Rajasthan Smt. Vasundhra Raje on 30.04.07 Handed Over in November, 2009
Management Block at M.D.S.U., Ajmer Important Works Completed during last 5 years Management Block at M.D.S.U., Ajmer Completion Cost – Rs. 1.97 Crs. Inaugurated by Honble Mininster for Industries Rajasthan State Govt. Sh. Rajendra Pareek on 17.09.09.
New Answer Book Halls at 1st Floor & 2nd Floor in B.S.E.R., Ajmer Important Works Completed during last 5 years New Answer Book Halls at 1st Floor & 2nd Floor in B.S.E.R., Ajmer Completion Cost – Rs. 2.15 Crs. Handed Over in November, 2009
Engineering College, Ajmer Important Works Completed during last 5 years Engineering College, Ajmer Completion Cost – Rs. 5.40 Crs. Inaugurated by Honble Chief Mininster Govt. of Rajasthan Smt.Vasundhra Raje on 25.01.08.
POLICE HOUSING SCHEME (ONGOING WORK AT GRP CAMPUS) No. of Quarters : 304 Nos. (L.S.Q.-292 + U.S.Q.-12) Total Cost : 15.73 Crores Location : G.R.P. Campus, Nareli, Ajmer Date of Start : February, 2008 / October, 2008 Stipulated Date of Completion : January, 2009 / September, 2009 Expenditure till Date : 12.09 Crores Likely Completion date : March, 2010 Bottlenecks if any : (i) Sanction for Development works not given. (ii) Water supply connection in campus is to be carried out by PHED. For which Six Months period required. (iii) 60 Nos Qtrs. (L.S.Q.) taken in Phase-II
POLICE HOUSING SCHEME (ONGOING WORK AT GRP CAMPUS)
(ONGOING WORK AT RAC,NARELI CAMPUS) POLICE HOUSING SCHEME (ONGOING WORK AT RAC,NARELI CAMPUS) No. of Quarters : 108 Nos. (L.S.Q.-104 + U.S.Q.-4) Total Cost : 5.55 Crores Location : R.A.C. Campus, Nareli, Ajmer Date of Start : February, 2008 / October, 2008 Stipulated Date of Completion : January, 2009 / September, 2009 Expenditure till Date : 3.78 Crores Likely Completion date : March, 2010 Bottlenecks if any : (i) 56 L.S.Q. taken in Phase-II work in month of October, 2008 therefore, campus may be ready for handing over by March, 2010.
Name of Work:- Various Works in M.D.S. University, Ajmer Construction of First Floor at Computer Centre Total Cost : 0.54/0.79 Crore Location : M.D.S. University, Campus Date of Start : September, 2008 Stipulated Date of Completion : April, 2009 Expenditure till Date : 0.53 Crore Likely Completion date : March, 2010 Bottlenecks if any : Revised Sanction for additional work received in June, 2009 and delay in payment from client.
Name of Work:- Various Works in M.D.S. University, Ajmer Construction of Women Hostel Foundation Stone Lead by Hon’ble State Minister for Information Technology & Communication Govt. of India Sh. Sachin Piolet on 15th September, 2009 Total Cost : 1.81 Crores Location : M.D.S. University, Campus Date of Start : September, 2009 Stipulated Date of Completion : June, 2010 Expenditure till Date : 0.08 Crore Likely Completion date : June, 2010 Bottlenecks if any : Work started in October, 2009 due to foundation stone ceremony in September, 2009.
Name of Work:- Various Works in M.D.S. University, Ajmer Construction of Academic Staff College (Guest House) Total Cost : 0.75 Crore Location : M.D.S. University, Campus Date of Start : August, 2009 Stipulated Date of Completion : December, 2009 Expenditure till Date : 0.11 Crore Likely Completion date : March, 2010 Bottlenecks if any : Funds not released by client timely.
Name of Work:- Various Works in M.D.S. University, Ajmer Construction of Environmental Science Building Foundation Stone Lead by Hon’ble State Minister for Information Technology & Communication Govt. of India Sh. Sachin Piolet on 15th September, 2009 Total Cost : 2.39 Crores Location : M.D.S. University, Campus Date of Start : December, 2009 Stipulated Date of Completion : November, 2010 Expenditure till Date : 0.00 Crore Likely Completion date : November, 2010 Bottlenecks if any : -
Name of Work:- Various Works in Board of Sec. Edu., Rajasthan, Ajmer Construction of Parking, Office, Chamber & Auditorium Total Cost : 14.00 Crores Location : B.S.E.R. Campus Date of Start : September, 2008 Stipulated Date of Completion : August, 2011 Expenditure till Date : 2.89 Crores Likely Completion date : August, 2011 Bottlenecks if any : Work stopped on account of decision not given by client for Construction of Auditorium hence, Construction of 2rd Floor held up for Two Months.
Name of Work:- Various Works in Board of Sec. Edu., Rajasthan, Ajmer Construction of 1st & 2nd Floor on Old Answer Book Hall Total Cost : 1.06 Crores Location : B.S.E.R. Campus Date of Start : September, 2008 Stipulated Date of Completion : February, 2010 Expenditure till Date : 0.49 Crore Likely Completion date : March, 2010 Bottlenecks if any : (i) Funds not released by client timely. (ii)Work stopped by client on account of thorough passes for access of examination stationary through trucks.
Name of Work:- Various Works under Police Modernization Construction of Adm. Training Block at PTS Kishangarh Total Cost : 1.5 Crores Location : Kishangarh Date of Start : September, 2008 Stipulated Date of Completion : May, 2009 Expenditure till Date : 1.30 Crores Likely Completion date : January, 2010 Bottlenecks if any : Part sanction of Rs. 0.5 crores received in phase-II.
Name of Work:- Various Works under Police Modernization Construction of Hostel Building of Trainee at PTS Kishangarh Total Cost : 1.00 Crore Location : Kishangarh Date of Start : September, 2008 Stipulated Date of Completion : May, 2009 Expenditure till Date : 0.55 Crore Likely Completion date : January, 2010 Bottlenecks if any : Part sanction of Rs. 0.2 crores received in phase-II.
Name of Work:- Various Works under Police Modernization Construction of Adm. Building for RPL, Hadi Rani Battalion, Ajmer Total Cost : 1.25 Crores Location : Nareli, Ajmer Date of Start : January, 2009 Stipulated Date of Completion : December, 2009 Expenditure till Date : 0.31 Crore Likely Completion date : January, 2010 Bottlenecks if any : Work Started in July, 2009 due to non availability of land.
Name of Work:- Various Works under Police Modernization Construction of 100 mens barracks at RPL, Hadi Rani Battalion, Ajmer (Part-I) Total Cost : 1.00 Crore Location : Nareli, Ajmer Date of Start : January, 2009 Stipulated Date of Completion : December, 2009 Expenditure till Date : 0.03 Crore Likely Completion date : January, 2010 Bottlenecks if any : Work Started in July, 2009 due to non availability of land.
Name of Work:- Various Works under Police Modernization Construction of 100 mens barracks at RPL, Hadi Rani Battalion, Ajmer (Part-II) Total Cost : 1.00 Crore Location : Nareli, Ajmer Date of Start : January, 2009 Stipulated Date of Completion : December, 2009 Expenditure till Date : 0.006 Crore Likely Completion date : January, 2010 Bottlenecks if any : Work Started in July, 2009 due to non availability of land.
Name of Work:- Various other works in Unit-I, Ajmer Construction of Canteen cum Guest House at Engineering College, Ajmer Total Cost : 0.42 Crore Location : Ajmer Date of Start : December, 2007 Stipulated Date of Completion : July, 2008 Expenditure till Date : 0.26 Crore Likely Completion date : March, 2010 Bottlenecks if any : -
Name of Work:- Various other works in Unit-I, Ajmer Construction of Urban Hatt at Ajmer Total Cost : 1.60 / 1.90 Crores Location : Ajmer Date of Start : June, 2007 Stipulated Date of Completion : May, 2008 Expenditure till Date : 1.14 Crores Likely Completion date : March, 2010 Bottlenecks if any : Work Stopped since October, 2008 due to funds not released by client
Proposed New Works S. No. Name of Work Client Deptt. Mode Estimated Cost Actual plus / Tendered 1. Const. of Women Engineering college (Ph.-II) Principle Mahilla Engineering College, Ajmer Actual Plus 393.00 Lacs. 2. Additional Works in ITI Building and Campus at Beawar. Institute Management Committee of ITI, Beawar 60.00 Lacs.