IT-3872 Refurbishment of the piping of the chilled water circuit of the Proton Synchrotron Alexandre Broche EN-CV-PJ
Introduction 21 October 2012IT Bidder’s Conference Technical Contacts: Alexandre Broche EN-CV Projects Team Michele Battistin EN-CV Commercial Contacts: Bjorn Jenssen FP-PI Ivo Lobmaier FP-PI
Agenda 3IT Bidder’s Conference1 October :00 – 09:30Introduction to CERN and of the Technical Specification(A. Broche) 09:30 – 12:30Visit of the existing installation(A. Broche) 12:30 – 13:30Lunch break 14:00 – 14:40Presentation of commercial documents(B. Jenssen) 14:40 – 15:00Relations with host states(TBD) 15:00 – 15:15Coffee break 15:15 – 15:45VAT and customs(T. Wegelius) 15:45 – 16:15Questions – Answers(A. Broche) 16:15 – 17:00Closing of the conference and return to reception
Introduction to CERN and the technical specification Alexandre Broche EN-CV-PJ
Overview 5 Introduction to CERN Documents –P&ID’s, specification, annexes Important points Questions and answers 1 October 2012IT Bidder’s Conference
CERN 61 October 2012IT Bidder’s Conference 20 Member states Particle accelerators and experiments
The CERN Sites 71 October 2012IT Bidder’s Conference Project location: buildings 150, 351, 354, 355 Meyrin, Switzerland EN-CV – Bldg. 35 FP-PI – Bldg. 5
Tender Documents and Drawings 81 October 2012IT Bidder’s Conference DocumentDescription IT-3872Technical specification Annex 1Technical Prescriptions for Piping and Accessories Annex 2Technical Prescriptions for Instrumentation Annex 3Technical Prescriptions for Electricity Annex 4Technical Prescriptions for Identification Annex 5Technical Prescriptions for Testing, Inspecting, and Commissioning the Hydraulic Installation Annex 6Portfolio of photos
Tender Documents and Drawings 91 October 2012IT Bidder’s Conference ReferenceNumber / Title 1CV Chilled water general distribution P&ID 2CV CV CV CV CV CV CV CV
101 October 2012IT Bidder’s Conference Work Package 1 –Supply to the synchrotron loop and ventilation rooms ( and 355-R-012) Work Package 2 –Distribution pipeline in Building 150 Work Package 3- Building 354 Work Package 4- Tunnel Linac ventilation Work Package 5- Heat exchangers in Building 351 The Scope
111 October 2012IT Bidder’s Conference
The Schedule 121 October 2012IT Bidder’s Conference Progress MilestonePlanned Dates Delivery of the documents as per § January 2013 Start of the Work Package 1 06 May 2013 Completion of Work Package 126 July 2013 Start of the Work Package 2 06 May 2013 Completion of Work Package 226 July 2013 Start of the Work Package 308 April 2013 Completion of Work Package 328 June 2013 Start of the Work Package 422 July 2013 Completion of Work Package 4 20 September 2013 Start of the Work Package 522 July 2013 Completion of Work Package 5 20 September 2013
Particular Notes 131 October 2012IT Bidder’s Conference Design and Build project from existing installations Each work package has specificities It is of primary importance to respect the schedule and CERN Specific rules: “Working on CERN site”
Questions and answers 141 October 2012IT Bidder’s Conference Questions ?