IBL Brazing Study April the 20 th 2012 Eric Vigeolas.

Slides:



Advertisements
Similar presentations
Euratom Mechanical operation on the TPL sector E.Delmas – December 8th /13 Disassembly and reassembly of a sector of the Toroidal Pumped Limiter.
Advertisements

Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
Alice ITS L5,6 Integration 1 End wheels and local services design – services layout on the end wheels: patch panels, routing, cooling and qualification.
Activités mécaniques 17 septembre 2013 D. Laporte F. De Matos / Y. Orain / P. Ghislain Atlas / SLHC.
P. Béné, F. Cadoux, A. Clark, D. Ferrère, C. Husi, M. Weber University of Geneva IBL General Week - 11, 12 February 2010 IBL Stave Loading Status Summary.
1 IBL Stave & loading tools University of Geneva: G.Barbier, F.Cadoux, A.Clark, D.Ferrère, C.Husi, P. Iacobucci, M. Weber The main goal for today…  Review.
Status of the AFC at RAL Tom Bradshaw John Cobb Wing Lau Matt Hills Elwyn Baynham Mike Courthold Victoria Bayliss MICE Project Board 28 th June 2011.
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
IBL Loading Activity Overview Franck, Maarten, Coralie, Didier Loading tool workshop University of Geneva, Aug 31 st 2011.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
EMCAL: project update - Italy - LNF - Frascati Fixture production Module assembly (proto) WLS fibers processing Lead procurement (proto) CT- Catania APD.
Stave # 1 Metrology Eric VIGEOLAS, WG2 July the 12th 2011.
Compressor status AWAKE Technical Board meeting 19 May 2015.
Theodore Todorov Pixel mechanics november 8th Inner detector upgrade / IBL Activities on cooling LAPP LAPP team Jacky Ballansat, Patrick.
Connectors 13/03/2013Collaboration meeting CERN - CSEM1.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
1 Mechanics news from KEK S.Tanaka (KEK) SVD/PXD meeting SVD parallel session.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
Back up stave test program status Eric VIGEOLAS Pixel week December 2000 Pre production status Assembling phase comments Geometrical control Stave Qualification.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
1 IBL Integration & Testing activities University of Geneva: G.Barbier, F.Cadoux, A.Clark, D.Ferrère, C.Husi, M. Weber  Preliminary definition of Integration.
1 H. Pernegger/CERNIBL cooling review 15/5/2012 IBL Cooling Requirements H. Pernegger.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
WG3 Insertion/Extraction Testing Program R. Vuillermet 11/04/20111.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Compressor status AWAKE Technical Board meeting 19 August 2015.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
Status of Activities at CERN
Update on Module Mounting on Staves and Stavelets 25/8/11 1.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
TOB meeting, TOB meeting 20 September 2005, Antti Onnela: TOB mechanical integration status and plans n TST-TOB-TIB integration exercise n.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
CMS Pixels upgrade CO2 cooling transfer lines Draft spec – for introduction Paola Tropea & Hans Postema 5 December 2012.
PHIN Fabrication of a photo-injector for the CTF3 accelerator and for the NEPAL test stand WP 4 of the JRA2 PHIN 1.Status of the construction of RF guns.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
M. Gilchriese - December 2000 Disk Sector Status E. Anderssen, M. Gilchriese, F. Goozen, N. Hartman, T. Johnson, F. McCormack, J. Wirth and D. Uken Lawrence.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
K.W. Glitza University of Wuppertal IBL Stave (Lessons for Upgrade)
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
October 14, 2008 C. Hauviller 1 Review of the mock-up’s C. Hauviller.
IBL – UniGe involvements UniGe Team : G. Barbier, F. Cadoux, A. Clark, S. Débieux, D. Ferrère, C. Husi, G. Iacobucci, M. Weber Other member (KEK): Y. Takubo.
Loading and QA activities Introduction, Workflow, Tooling, Tasks UniBe – UniGe regular IBL-Upgrade meeting D. Ferrère Aug, 11 th 2011.
IN2P3. Why Titanium for cooling circuits? Titanium material collect the most important criteria for cooling circuit design: Low CTE: important parameter.
ICARUS Collaboration Meeting Dec A. Scaramelli.
IBL CO 2 cooling flexible transfer integration into IDEP 24 July 2013 Jan Godlewski, Bart Verlaat, Siegfried Wenig, Nicolas Massol, Tomasz Blaszczyk 1.
Eric Vigeolas, July the 3 rd Status The IBL detector construction already started and the components assembly (flex, modules, stave loagin) will.
IRC/SAC status Venelin Kozhuharov for the SAC/IRC working group NA62 Meeting
THE LINAC4 RFQ – Experience with Design, Fabrication and Tuning C. Rossi and the RFQ Project Team GSI Review – 20 November 2013.
1 ATLAS Upgrade WP4 Face to Face meeting Sheffield 25 th August 2011 Richard French – The University of Sheffield Ian Mercer – Lancaster, Martin Gibson,
Stator Plan & Schedule Chris Booth 2nd March 2009
DT-LHCb coordination meeting 18 April 2016
UPPSALA UNIVERSITY GERSEMI
Ti/SS transitions A.Basti INFN-PISA*
Safety approval of the installed copper cooling pipes
Complementary ISTC Projects #3888, 3889p
Flexible lines production and planning
Update on the IBL vacuum flex transfer lines
SCHEDULE Nov 1st - Assembly Table Complete
UT Integration meeting UT CO2 COOLING DISTRIBUTION SYSTEM
Update on the IBL vacuum flex transfer lines
IBL activities ATLAS Meeting Milano, 14 May 2012 S. Coelli,
Status of CO2 Cooling tests at CERN for Pixel phase 1
Presentation transcript:

IBL Brazing Study April the 20 th 2012 Eric Vigeolas

Meeting Scope Update on the brazing study status Comments on the last metallurgical analysis CERN To establish the schedule for qualification completion To discuss the SR1 tooling and schedule for the detector construction AOB…

Qualification test sequence Test de traction sur 3 échantillons  Réalisé par Serge Test de compatibilité électrique  Déjà effectué Test métallographique sur les jointures de chaque type  Réalisé par stephano Sgobba (minimum de deux échantillons de chaque type) Test de choc thermique à l’azote liquide et de réchauffe rapide  Réalisé par Serge Test de cyclage en pression et en température (CO2)  Réalisé au LAPP Essais final sur une stave de production  réalisé dans le bâtiment SR1 dans les conditions nominales Defined in December Metallographic analysis done on several sample are we satisfy with the results? Should we perform more tests? (last file can be Concerning the bushing design can we consider the design as satisfying brazing requirements? Tensile test status? Thermal chocs status? How many sample can be produced and deliver to LAPP for cycles and leak check?  Define a date Do we have enough material for the ongoing CERN? We are about to start on IBL project the Stave 0 (demonstrator) program, End of may on stave will be ready in SR1 for modules testing and burning. We would like to perform on this stave a Brazing induction test to qualify the tooling and check the module survivability (End of June, Early July)

SR1 tool Vacuum Chamber made by Stave Jig Unige Support table CPPM Tube extension UniGe Tripods will be provided by CPPM to handle the tube extension Ti pipe will have a temporary fitting attached to it which will permit connection to vacuum Pump

SR1 Tool location Operators should comment the tool placement before installation  for all information or change request please contact Tool was placed in the continuity of the detector integration tool to avoid any stave rotation after pipe brazing Integration tool

Vacuum chamber removal after brazing task sequence Baseline, the stave is fixe and the chamber move to get out of the Ti pipe. The Ti pipe end with a 10 mm diameter fitting, feed through should be compatible with this dimensions Brazing configuration Remove one half of the tube extension And start extracting the vacuum chamber Remove the second half of the tube extension Connect the first half to the stave jig Complete the chamber extraction

Work organization The Stave production will be 1 Stave/Week Brazing will occur right before the stave integration into the detector Due to stave dimensions after brazing we will not have possibility to store more than one or two stave // to the integration The idea is to perform the brazing parallely to the integration with one stave in advance to not bloc the assembly sequence IBL Stave integration start End of March 2013 duration 12 weeks We will have to braze one to two stave/week during this period  need to check people availability during this period (one day or two /week )

Project Schedule for stave availability