Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction
Project Location
Existing Bridge o 3-Span Concrete Tee Beam o 123 Feet Long o 28 Feet Wide
Approach Looking Southeast
Profile Looking Southwest
Design Parameters o National Highway Route o 2500 vehicles per day (23% Trucks) o Major truck route between Great Falls and Billings o US Air Force Missile Route o Grain Elevator in Moccasin o BNSF Railroad Crossing o Accident cluster at bridge
New Bridge Requirements o New width = 40 feet o Increased railroad lateral clearance o Increased railroad vertical clearance o Avoid existing foundations (timber piles) o Minimize grade raise to catch slopes on existing approaches – avoid sliver fills and new R\W o Minimize traffic disruptions
What are our options? o New Bridge on Offset Alignment o New Bridge on same alignment using On-site Detour o New Bridge on same alignment using Phase Construction o New Bridge on same alignment using Off-site detour and ABC
Could Accelerated Construction work here?? o How long can we shut down bridge site? o How quickly can we build a new bridge? o How much building can be completed before with existing bridge in place? o Is there a reasonable detour route?
Possible detour route o Secondary Highways – wide shoulders / flat slopes o Similar detour length for thru-traffic o Detour through town of Hobson – school crossing o At-grade RR crossing in Hobson o Many local detours possible (County Roads)
o Contacts with o Town of Hobson - Mayor o Hobson School o County Commissioners o Trucking Industry – grain elevator o Air Force Base o BNSF Railroad o Road User Cost Calculations o Preliminary ABC Ideas o Contract Time Estimates o Local Events ABC Planning Efforts
– Hay Days – Utica Montana
What can we accelerate? What portion of construction takes the most time? o Foundation construction – 4 days/shaft or 4 piles/day o Drilled Shaft testing – 14 days before testing / longer if problems are encountered o Forming bent caps – 3 days each o Curing bent caps – 15 days per project o Deck forming – 20 days up to 300 feet o Deck curing and sealing – 28 days Allowing for some overlap……80 days for major items
Potential Solutions o Foundations o What can we do while traffic is on existing bridge? o What foundation types will work? o Forming and curing bent caps o What cast-in-place can be done while traffic is on existing bridge? o Precast end and intermediate caps? o Deck forming and curing o Full-depth precast deck panels o Partial-depth o Stay-in-place Forms
o What could be completed before detouring traffic o What would be accelerated while traffic is on detour route o What work could be done after traffic is moved back on new bridge Divided Work Into Stages
Work Prior to Detouring Traffic Drilled 4 shafts outside the bridge limits and behind the existing intermediate bents.
Cast struts/crash wall on top of and between shafts
Cast walls on top of struts
Traffic on Detour Day 1 o Removed span 2 deck and beams o Removed span 3 deck
Day 2 o Removed span 3 beams o Removed bent 3 and 4 o Removed span 1 deck
Day 3 o Bent 4 – drove piles, formed and placed cap o Bent 3 – Set cap and placed closure o Removed span 1 beams o Removed bents 1 and 2
Precast Pier Cap
Day 4 o Bent 2 – Set cap o Bent 1 – drove piles
Day 5 o Bent 2 – placed closure o Bent 4 –formed and placed cap
Day 6 o Span 3 – Set girders and deck panels
Day 7 o Sunday – no work Day 8 o Span 2 – Set girders and deck panels
Day 9 o Span 1 – Set girders and half the deck panels Day 10 o Span 1 – Set remaining deck panels o Began forming closure pours
Day 11 o Bents 1 & 4 – Formed and placed backwalls o Formed deck panel closure pours Day 12 o Continued forming deck panel closure pours Day 13 and 14 o Saturday and Sunday – No work Day 15 o Adjusted deck grades o Prepare for deck closure pours
Day 16 and 17 o UHPC Closure Pours
Day 18 and 19 o Removing form work and grinding joints o Fill low spots
Day 20 and 21 o Weekend no bridge work – building approach fills Day 22 o More grinding and approach fills Day 23 o Tying barrier steel o Test run with slip form Day 24 o Approach work Day 25 o Slip formed barriers o Final grading along RR tracks
Day 26 and 27 o More grading work o Approach rails Day 28 o Finished approach rails Day 29 o Opened to Traffic One day ahead of schedule (incentive/disincentive deadline)
Now lets see that in fast motion
Lessons Learned o Project scheduling was intensive o Design details are critical – things need to fit o Allow adequate tolerance on precast elements o UHPC is difficult to grind – reduce exposed area to minimize grinding o Have an Engineer on site during construction of critical elements – be prepared to make decisions
Questions?? Project Contact: Jeff Olsen