Sept. 30, 2004 NIKHEF-1 Hans de Vries Status NIKHEF Mechanics Secondary vacuum box Bellows Vacuum system CO 2 cooling: Bart Verlaat.

Slides:



Advertisements
Similar presentations
EDR-1 December 16/17, 2002 Hans de Vries - 1 Status RF foil RF/vacuum foil  Purpose  Production methods used  Deformations: static - overpressure 
Advertisements

1 Ann Van Lysebetten CO 2 cooling experience in the LHCb Vertex Locator Vertex 2007 Lake Placid 24/09/2007.
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Vrije Universiteit amsterdam CERN, November 27, 2000 VELO System J.F.J. van den Brand LHCb Vertex Detector System: Status Report J.F.J. van den Brand Subatomic.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
Heinz Grote1 Presentation to NSCX WENDELSTEIN 7-X Assembly Max-Planck- Institut für Plasmaphysik KKS-Nr.: 1-AD Dok-Kennz.: -Txxxx.0 Heinz Grote October.
Progress and Plan for Superconducting RF Cavity RF Group.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
AMS-02 tracker mechanics status of construction, assembly, integration Production: - Ladder integration - Installation on planes Inner tracker assembly:
Theodore Todorov Pixel mechanics november 8th Inner detector upgrade / IBL Activities on cooling LAPP LAPP team Jacky Ballansat, Patrick.
Mechanical design, analysis and integration of pre-alignment systems for CLIC M.Anastasopoulos / BE-ABP-SU.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
Gasoline fuel supply systems Function: store, transport, Pressurize and filter gasoline going to carburetor or fuel injection system.
Dec. 4, 2001 CERN-1 Hans de Vries VELO Mechanics  RF/vacuum foil  Rectangular bellow  Wake field suppressors  Cabling Summary & Outlook VELO mechanical.
Status overview of the cooling 31 August 2015 Bart Verlaat, Raphael Dumps 1.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
INSTRUCTION DISCONNECTING THE ELLIPTICAL HEAD The National Institute for Nuclear Physics and High Energy Physics Kruislaan SJ Amsterdam PO Box.
EDR - Mech. 2; December 16/17, 2002 Hans de Vries - 1 Status of Vertex at NIKHEF VELO Mechanics  RF/vacuum foil  Rectangular bellow  RF measurements.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
DCP 12 May 2010 Jan Godlewski PH-DT-PO 1 DETECTOR COOLING PROJECT WP2 CO2 activities status report Jan Godlewski PH-DT-PO
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
VTCS overview 13 April 2006 NIKHEFBart Verlaat 1 NIKHEF involvement in VELO ~1 m module support CO 2 cooling detector "hood" kapton cables Vacuum vessel.
November 29, 2002 NIKHEF-1 Hans de Vries Status RF foil RF/vacuum foil  Purpose  Production methods used  Deformations: static - overpressure  Electrical.
06-November-2013 Thermo-Mechanical Tests BE-RF-PM Review of the CLIC Two-Beam Module Program Thermo-Mechanical Tests L. Kortelainen, I. Kossyvakis, R.
Matthew Cox VSSLS Workshop Barcelona Sept SLIDE 1 1 Diamond Light Source Vacuum Systems Matthew Cox
LHCb VELO Meeting LHCb VELO Cooling System Bart Verlaat (NIKHEF) 25 February 2003.
Nikhef Amsterdam Mechanical- Technology Short update on CO 2 cooling activities at Nikhef 13 October 2010.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Limits of the current VTCS Ann Van Lysebetten Bart Verlaat Martin van Beuzekom VELO upgrade meeting 14/11/2008 pix module construction kick-off 09/11/2009.
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
Beam Loss Monitor Production. IHEP (Protvino) V. Grishin, A. Koshelev, A. Larionov, V. Seleznev, M. Sleptsov, A. Sytin At IHEP manufactured: Ionization.
Vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand LHCb Vertex Detector System: Status Report J.F.J. van den Brand.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
Dec
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
CO 2 Controlling a 2-phase CO2 loop using a 2-phase accumulator
Installation of the T600 at Fermilab CSN2, September 22,
LHCb-UT and Velo Upgrade Road to a system EDR in Q June 2015 Bart Verlaat 1.
Vacuum assessment for BI equipment TE-VSC. Why do we need to assess BI components 10/6/2015 BI Beam Operational Spare Strategy Workshop No 2 2 The main.
Status of MICE RF for Step V’ (at LBNL) Derun Li Lawrence Berkeley National Laboratory December 6, 2014.
19 December 2006Eddy Jans Annual Scientific Meeting0 The advent of the VELO introduction sensors mechanics vacuum motion cooling PU-modules installation.
21 June Experiences with CO 2 cooling hardware and applied designs. Experiences from past CO 2 systems and philosophies for the.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
1 Workshop on Vacuum System Design for Synchrotron light Source ALBA - Barcelona, Sept New trends in the vacuum design and technology.
Crab Cavity Technical Coordination meeting:
Teleconf ACS – FREIA 28th March 2017
Installation of the T600 at Fermilab
Full Anode Insert Pressure Cycle Simulation Device
Sub-system integration for the VBOX
Awake Electrons Gun Introduction. - How works an electrons gun
Dielectric Oil Installations
The Budker Institute of Nuclear Physics
Flexible lines production and planning
Challenges of vacuum chambers with adjustable gap for SC undulators
ELENA electron cooler and SEM grids status
Teleconference ACS – FREIA 31st October 2017
XFEL Vacuum System Commissioning
UK RFD Pre-Series cryomodule
INSTRUCTION DISCONNECTING THE ELLIPTICAL HEAD
Coldex disinstallation
LHCb VErtex LOcator For precision measurements of CP-violation at CERN (GENEVE) HALF of DETECTOR Si strip detector Read-out electronics Secondary vacuum.
LHCb VErtex LOcator ENGINEERING DEPARTMENT
Phase II Collimators : design status
LHCb VErtex LOcator For precision measurements of CP-violation at CERN (GENEVE) HALF of DETECTOR Si strip detector Read-out electronics Secondary vacuum.
Two-beam Test-stand Design and Construction Status
Teleconference ACS – FREIA 19th June 2017
BGC Collaboration Meeting –
SC1R Cold Box PDR Assembly Sequence
Presentation transcript:

Sept. 30, 2004 NIKHEF-1 Hans de Vries Status NIKHEF Mechanics Secondary vacuum box Bellows Vacuum system CO 2 cooling: Bart Verlaat

Sept. 30, 2004 NIKHEF-2 Hans de Vries System overview Sec. vacuum box Rectangular bellow Vacuum vessel on stand

Sept. 30, 2004 NIKHEF-3 Hans de Vries Vacuum vessel Is being produced Thermo Electron Corporation Delivery: November Will be equipped with silicon insulated heaters from Watlow

Sept. 30, 2004 NIKHEF-4 Hans de Vries Center frame Accuracy and reproducibility: 2 μm; Complete opening/closing: 2 minutes

Sept. 30, 2004 NIKHEF-5 Hans de Vries Detector Lifting Device

Sept. 30, 2004 NIKHEF-6 Hans de Vries Transport trolley

Sept. 30, 2004 NIKHEF-7 Hans de Vries Detector installation rail

Sept. 30, 2004 NIKHEF-8 Hans de Vries Secondary vacuum box

Sept. 30, 2004 NIKHEF-9 Hans de Vries Secondary vacuum box (2)

Sept. 30, 2004 NIKHEF-10 Hans de Vries Measurements on box Mechanical performance –Tolerances, accuracy Vacuum performance –Leak rate Mechanical response to pressure differences Influence of torlon coating –Bake-out NEG coating (November)

Sept. 30, 2004 NIKHEF-11 Hans de Vries NEG coating The detector box in the vacuum vessel

Sept. 30, 2004 NIKHEF-12 Hans de Vries NEG coating (2) NEG coating will be tested at CERN in November

Sept. 30, 2004 NIKHEF-13 Hans de Vries Production bellows

Sept. 30, 2004 NIKHEF-14 Hans de Vries Testing of Bellows

Sept. 30, 2004 NIKHEF-15 Hans de Vries New bellows design Old camera bellows

Sept. 30, 2004 NIKHEF-16 Hans de Vries PLC programming Vacuum system SIMATIC manager step7 version V5.2+SP1 Simulation test conditions The vacuum simulator equipped with Altera EP20K200EQC240-3 chip, program language is VHDL

Sept. 30, 2004 NIKHEF-17 Hans de Vries Vacuum control cabinets

Sept. 30, 2004 NIKHEF-18 Hans de Vries Vacuum system

Sept. 30, 2004 NIKHEF-19 Hans de Vries Scheme evacuation set-up 400 l RF box Primary vacuum volume: 1700 liter Secondary vacuum volume: 500 liter Simulation volumes 1600 liter and 400 liter -Two vessels for NEG coating -Test set-up for integral leak test of bellows and RF box

Sept. 30, 2004 NIKHEF-20 Hans de Vries Membrane switches Modifications of the PS laser welded membrane - ref. vacuum separated from measuring chamber

Sept. 30, 2004 NIKHEF-21 Hans de Vries Membrane switches

Sept. 30, 2004 NIKHEF-22 Hans de Vries Valves

Sept. 30, 2004 NIKHEF-23 Hans de Vries Vacuum Test System Beam vacuum 1600 l Detector Vacuum 400 l PUMP ACP28 Venting Restrictions Membrane Switches Schakelaars MKS 120AA MKS 120AD Nupro Valves

Sept. 30, 2004 NIKHEF-24 Hans de Vries Vacuum test set-up

Sept. 30, 2004 NIKHEF-25 Hans de Vries Follow up evacuation set-up Assemble the set-up with the final parts Determine the resistance(conductance limiter) for RS 301 and RS 302 During evacuation test : registration of dP Optimize the conductance limiter with the dP Translate the result to the final experiment

Sept. 30, 2004 NIKHEF-26 Hans de Vries Venting procedure Total venting time: 90 minutes Actions membrane switches: 50 times

Sept. 30, 2004 NIKHEF-27 Hans de Vries Evacuation Total evacuation time: 300 minutes Actions membrane switches: 7 times

Sept. 30, 2004 NIKHEF-28 Hans de Vries Summary Good progress on realization components Vacuum vessel has been ordered: delivered in November New foils for secondary vacuum box have been produced New design bellows Vacuum system with membrane switches looks promising NEG coating will be tested: November