14 June 2007VELOEddy Jans 0 Recent VELO-installation++ activities June 14, 2007 Potmeter calibration Bake-out Cabling & Commissioning.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

Vrije Universiteit amsterdam CERN, November 27, 2000 VELO System J.F.J. van den Brand LHCb Vertex Detector System: Status Report J.F.J. van den Brand Subatomic.
9 November 2006VELOEddy Jans 0 ACDC3 VELO-testbeam Nov ‘06 November 9, 2006 preparation for transport transport Assembly Lab -> H8 testbeam (Prevessin)
7 September 2006VELOEddy Jans 0 VELO-installation September 7, 2006 installation of exit window + part I of the beam pipe logging of vacuum data what’s.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
AMS-02 tracker mechanics status of assembly and integration Inner tracker integration completion: - Assembly and cabling - Temperature and magnetic field.
14 February 2008VELO NikhefEddy Jans 0 Cooling and warm-up of the VELO under neon atmosphere conditions results (Jan 28  30) implications.
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
EA meeting, Wednesday 6 Dec 2006 TT installation, Jeroen van Tilburg 1 TT installation Installation of the TT station.
The MICE vacuum system Presented by Mark Tucker at CM-39, 26 June 2014.
LTC Extended days, 03 March’08 J.M. Jimenez, AT Vacuum Group LHC Vacuum commissioning J.M. Jimenez On behalf of AT-VAC.
Update on Ongoing Tungsten Digital HCAL Beam Tests Erik van der Kraaij CERN LCD.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
Status of NA62 straw electronics and services Peter LICHARD, Johan Morant, Vito PALLADINO.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
The LHCb VErtex LOcator Olaf Behrendt on behalf of the VELO group Novosibirsk,
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
Itzhak Tserruya, BNL, Aug. 11, Itzhak Tserruya Weizmann Institute, Israel BNL, Upgrades Meeting, Aug. 11, 2004 HBD: Infrastructure and Integration.
Training in Vacuum Technology for JUAS 2013 Students
STATUS OF HO Sudhakar Katta TIFR, Mumbai India-CMS meeting, Delhi 27 th Sept 2007.
14 October 2010Eddy Jans 0 VELO-vacuum “problem” VELO Meeting On Sunday October 3 at 10h15 a sudden increase of a factor 6 of the pressure in the beam.
Technical Board Meeting, 14/06/07 Kristján Gulbrandsen, NBI 1 Progress on and Status of the Forward Multiplicity Detector Kristján Gulbrandsen Niels Bohr.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Power Up of the First VELO Module at IP8 Eddy & Olaf on behalf of the VELO group.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
25 January 2007VELO sub-projectsEddy Jans 0 VELO-meeting January 25, 2007 Sub-projects: SX & SX connectorize cooling cables alignment procedure.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
LHCf Detectors Sampling Calorimeter W 44 r.l, 1.6λ I Scintilator x 16 Layers Position Detector Scifi x 4 (Arm#1) Scilicon Tracker x 4(Arm#2) Detector size.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
PSD upgrade: concept and plans - Why the PSD upgrade is necessary? - Concept of the PSD temperature stabilization and control - Upgrade of HV control system.
A.Henriques (JCOV meeting 31/5/2001) ATLAS Calorimeter cooling project Goal: u Definition of a common frame work for the cooling of the ATLAS calorimeter.
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
Commissioning the LHCb VErtex LOcator (VELO) Mark Tobin University of Liverpool On behalf of the LHCb VELO group July 28, 2008Vertex 2008: 17th International.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
19 December 2006Eddy Jans Annual Scientific Meeting0 The advent of the VELO introduction sensors mechanics vacuum motion cooling PU-modules installation.
Mitglied der Helmholtz-Gemeinschaft Status of day-one experiment commissioning at COSY Huagen Xu Goa, Mar
Upgrade activities DT-LHCb coordination meeting 14 March 2016.
Plans for the UT Installation LHCb infrastructure workshop February Burkhard Schmidt for the UT group.
ELENA installation progress F. Butin / ELENA collaboration.
Installation of the T600 at Fermilab
VELO-installation meeting CERN, January 17, 2006
BA6 – crab cavity activities in EYETS
Installation of an Instrument on a CERN machine
Gas System Commissioning
on behalf of the RF group
LHC Experimental Vacuum Systems Status October ‘07
News from Projects Lau Gatignon / EN-EA Input from F.Butin, Q.Bouirek
XFEL Vacuum System Commissioning
BEPCII RF POWER SOURCE AND INPUT COUPLER
ACS news Circulator TCU: control tests in progress All cavity racks
Module 3 Domestic Heating/MMA Welding
LHCb comprehensive review, Paula Collins
RPC Detector Control System
VELO-meeting January 25, 2007 Sub-projects: SX & SX
UXC55 ME Muon Endcap On Detector Layout
VELO RICH 1 INSTALLATION PLATFORM BALCONY BALCONY
RPC Detector Control System
Presentation transcript:

14 June 2007VELOEddy Jans 0 Recent VELO-installation++ activities June 14, 2007 Potmeter calibration Bake-out Cabling & Commissioning

14 June 2007VELOEddy Jans 1 Potmeter calibration Fred Schimmel has written PVSS-code to do the job: buitengebied: simultaneously XA: 28  2 mm XC: -28  -2 mm step , default  =2 mm binnengebied: XC=-10; XA= 10  -4.5 mm, step , default  =1 mm XA=10; XC= -10  4.5 mm, step , default  =1 mm y-calibrationXA=2, XC=-2, Y= -4.5  4.5  -4.5 mm step , default  =0.5 mm (See next talk by HdV) Limits, steps, etc. OK ??

14 June 2007VELOEddy Jans 2 Bakeout of VELO-tank & LHCb-beampipe Everything (=beam pipe, neon injection line, flanges of VELO-tank, 2 ion getter pumps) equipped with heaters, isolation and thermocouples by AT-VAC.

14 June 2007VELOEddy Jans 3

14 June 2007VELOEddy Jans 4

14 June 2007VELOEddy Jans 5 Neon injection system on balcony Bake out campaign: from 14h00 on Wednesday June 6 till 17h00 on Tuesday June 12

14 June 2007VELOEddy Jans 6 Temperature profile 120 o C 150 o C Test bakeout RF-boxes Bakeout RF-boxes 100 o C VELO cooldown

14 June 2007VELOEddy Jans 7 Pressure profile VELO to 120 o C VELO to 150 o C Bakeout RF-boxes unvoluntary air injection (see plots HdV) startup of ion getter pumps VELO to 100 o C beambeam det.det. VELO cooldown

14 June 2007VELOEddy Jans 8 System is presently being vented with ultra-pure Neon. Bypass valve may NOT be opened, i.e. NO movements allowed. System will be kept “locked”, i.e. no neon supply and no balancing of pressures in beam and detector volumes. End pressures: 5x10 -10, 2x VELO-detector: 3x10 -8 mbar

14 June 2007VELOEddy Jans 9 Cabling & Commissioning All HAPTAS temperature cables are connectorized by PdG + JS. Connectorizing of analog cables by INEO in D3 is ongoing, till end July. HV is almost finished LV has not started yet First crate with TELL1’s installed in D3 and configured. First crate with control boards installed on P1. Control + readout of one VELO-slice this week. Then readout of a dummy module with full DAQ-chain.

14 June 2007VELOEddy Jans 10 What’s next, apart from everything else ?? finish one detector half completely perform turn-over test with 2 cranes organize transport from Meyrin  IP8 + through shaft prepare area (extra platform, store cables, clean, etc.) open VELO-tank install fitting frame measure remove fitting frame install detector half flush with dry air (how ?) and measure IV-curves or evacuate, measure IV-curves, vent with Neon finish PLC-coding motion system ELOG has moved to the following CERN Web-site