Delivering Digital Services NextGen Web Service Implementation by the National Weather Service Ryan Solomon Project Manager NOAA NextGen IT Web Services Date:August 28, 2014
Project highlights OGC-compliant web services Standard formats – – NetCDF 4 Classic CF – IWXXM, IWXXM-US, WXXM Redundant high availability state of the art data centers – College Park – Boulder Experienced in delivery of operational capabilities – NCEP Central Operations 2
Project approach Build it and they will come 3 “There are many ways of going forward, but only one way of standing still.” - FDR
Project approach 4 money + iron + people + hard work = RESULTS
5
Project status Prototype serving data to the FAA to support EWD Metadata development on track Schema development progressing nws.weather.gov/schemas/ nws.weather.gov/codes/ 6
Project status (cont) IOC – June 2015 Build-out team staffing up NWS Internet Dissemination System (NIDS) Training Learning about the data sets Interfacing with subject matter experts 7
Project status (cont) Exploring options CKAN ckan.org open source data hub used by several countries including the U.S. – data.gov Boundless OpenGeo Suite boundlessgeo.com PostGIS Open standards – WCS, WFS, WMS RabbitMQ rabbitmq.com open source messaging broker feature rich persistence high availability clustering 8
Data (WFS) 9 METAR Priority 1 SPECI TAF SIGMET Priority 1 AIRMET MDCRS NCWF PIREP Priority 1 June 2015
Project schedule 10 CIP/NCWD from NIDS dev 9/16/14 CIP/NCWD from NIDS dev (OGC WCS) 11/6/14 METAR from NIDS dev 11/5/14 IOC metadata and schema records complete 12/5/14 CIP/NCWD from IDP (OGC WCS) 12/29/14 METAR from NIDS dev (OGC WFS) 1/8/15 METAR available from IDP (OGC WFS) 2/12/15 All IOC products from NIDS dev 5/4/15 All IOC products from IDP (OGC WCS/WFS) 6/30/15
Challenges (common) Transition from TAC to XML Bandwidth System resources $$ Governance Change management Parallel data feeds and data integrity 11
Challenges (project) OpenGeo NetCDF support Pub/sub approach URN namespace uniqueness Balancing user requirements with schedule – FAA, AWIPS-II, others – What we can realistically stand up by June