Steps taken to improve the progress and completion rate Filling up all vacancies of (TC) Block Engineer & Sr. TC (District Engineer) Funds released to SMC a/c newly operationalised Recruitment of teachers State Government has sanctioned teachers under its own quota Training to TC, Sr. TC & teachers Training to SMC under a programme called “ SAHAYOG ” Frequently monitoring at School, Block & District level. Coordination meeting with RD Deptt. for completion of Drinking Water & toilets
Impact of steps taken Sl. No. DescriptionAs on May’2011Basing on Completion rate (For )16%66% 2Completion rate (upto )79%89% 3Spillover (Upto ) The state was able to achieve the target as per Plan of Action presented on 8 th July 2011.
Impact of steps taken by end of September ’ 11 * -ve value says the State has able to achieve more than the targeted plan
Impact of steps taken by end of October ’ 11 * -ve value says the State has able to achieve more than the targeted plan
Spillover (upto ) ending Sl. No.ActivityNos. 1BRC01 2CRC24 3Primary (all type)1496 4Upper Primary (all type)829 5ACR (all type)9431 6Toilet (all type)1853
Spillover (upto ) ending Sl. No.ActivityNos. 1BRC01 2CRC23 3Primary (all type)1290 4Upper Primary (all type)732 5ACR (all type)5580 6Toilet (all type)1199
Plan of action for completing the spill over works up to
GAP
Planning to complete all spillover work Asst. Engineers monitoring frequently for progress of work Filling all vacancies of TC & Sr. TC Coordination meeting with Bankers for quick release of funds to School / SMC a/c Zone wise assignment are given to State level Engineer for close monitoring
Commitment By – all works (upto ) to be completed. Balance gap to be covered by December-2012