CONSTRUCTION AND STRUCTURES – II MAJOR PROJECT
Click your mouse once to begin. STEP-BY-STEP CONSTRUCTION In this presentation You will learn how to safely erect and dismantle a tower scaffold Consider.
1 The New Steel Erection Rule: Highlights. 2 Steel Erection Final Rule Published January 18, 2001 Implemented January 18, 2002 Includes exceptions for.
Unit 5 Steel Frame Construction
Steel Construction.
FRAMED STRUCTURE Students: Yoryelina Moreno Mairim Zapata.
Advanced Construction Technology
Erecting steel structures Setting up or dismantling cranes or hoists
Personal Mobility Lift Capstone Team Members: Jim Folgate Bill Beers Ryan Pelton David Zuercher.
Heavy Concrete Construction Formwork
Advanced Construction Technology By Professor Chris Gorse – licensed under the Creative Commons Attribution – Non-Commercial – Share Alike License
INTRODUCTION TO THE NEW SUBPART R Prepared by the U.S. Department of Labor, OSHA Office of Construction Standards and Compliance Assistance.
Subpart R Steel Erection
Assembly Instructions Additional documents needed for Assembly: GA Drawings on all Units Header Platform GA Drawings Motor Deck Platform GA Drawing Packing.
Advanced Construction Technology
[[Click on topic to view page]]
Advanced Construction Technology By Professor Chris Gorse & Ian Dickinson – licensed under the Creative Commons Attribution – Non- Commercial – Share Alike.
Design C a s t i n g E r e c t i o n F i n a l S t r u c t u r e D e s i g n C o n s t r u c t i o n P r o c e s s P r e–c a s t C o n c r e t e 3D M o.
Advanced Construction Technology By Professor Chris Gorse – licensed under the Creative Commons Attribution – Non-Commercial – Share Alike License
Safety : Scaffolds Introduction to Industrial Technology Spring 2014
Chris Gorse Advanced Construction Technology By Professor Chris Gorse & Ian Dickinson – licensed under the Creative Commons Attribution – Non- Commercial.
Rev: Section 3 Framing Operations. Rev: Learning Objectives: Section 3 Understand when fall protection must be provided Evaluate the use.
Advanced Construction Technology By Professor Chris Gorse & Ian Dickinson – licensed under the Creative Commons Attribution – Non- Commercial – Share Alike.
Group 11. Introduction Tasked to provide a “ship enclosure and adjacent building comprising one structure […] with the adjacent building running along.
Advanced Construction Technology By Professor Chris Gorse & Ian Dickinson – licensed under the Creative Commons Attribution – Non- Commercial – Share Alike.
Advanced Construction Technology By Professor Chris Gorse & Ian Dickinson – licensed under the Creative Commons Attribution – Non- Commercial – Share Alike.
Issues to be considered :foundations Professor Chris Gorse and Ian Dickinson These slides should be read in conjunction with Emmitt, S. and Gorse, C. (2010)
CWB Tunnel (North Point Section) and IEC Link HY/2009/19 Presentation on: Date: Presented by: Presentation on: 17 April 2015 Chun Wo-CRGL-MBEC Joint Venture.
Manufacturing Assembly Plan P Mechanical Spine Test Platform.
Rectangular framed structures
Chapter 19 Floors.
STEEL FRAMED STRUCTURES Steel is a material which has excellent structural properties. It has high strength in tension and compression. It is the strongest.
Harwood Grant #46J6-HT13Southwest Safety Training Alliance Inc1 Module 2 Fall Hazards Did you know? Falls from elevation account for one third of all deaths.
Barry's Introduction to Construction of Buildings, Second Edition, by Stephen Emmitt and Christopher A. Gorse. © 2006, 2010 by Stephen Emmitt and Christopher.
Barry's Advanced Construction of Buildings, Second Edition, by Stephen Emmitt and Christopher A. Gorse. © 2006, 2010 by Stephen Emmitt and Christopher.
Construction Safety Council. by David G. Allie Subpart R - Steel Erection ( ) Tiered buildings not adaptable to temporary floors - Safety.
Appendices Subpart R Steel Erection
Sustainability in Non Domestic Construction By Professor Christopher Gorse – licensed under the Creative Commons Attribution – Non-Commercial – Share Alike.
1 HVACR116 – Trade Skills Structural Drawings. 2.
Visit Gangway FromLHBIEP__0181 by Andre Coin ~ 2600 GANGWAY POSITION.
1 CV4902- Construction Methods Dr David Chew. 2 Construction Considerations Site layout plan Outline of entire construction process Details of temporary.
Floor Jacks and Stands Harkness Career Center. Floor Jacks Parts Identification.
By, David Sessions. Buildings come in many shapes and sizes The tallest buildings in the city are called skyscrapers.
Waynesburg Central High School Waynesburg, Pennsylvania Robert Owen Brennan The Pennsylvania State University Construction Management.
Day 20 PRECAST AND PRE-STRESSED CONCRETE Pre Cast concrete comprise units that are made under controlled conditions, with necessary preparations for.
Fundamentals of Structural Detailing
Working / walking on a roof
The New Steel Erection Rule Developed by S teel E rection N egotiated R ulemaking A dvisory C ommittee (SENRAC) in 2001 Occupational Safety and Health.
Infrastructure that Supports the Construction Industry In order for the construction industry to function effectively there is a large amount of infrastructure.
Figure 2.1 Sequence of site analysis. Barry's Introduction to Construction of Buildings, Second Edition, by Stephen Emmitt and Christopher A. Gorse. ©
Risk Management in the Built Environment Management of Risk in Construction By Professor Simon Burtonshaw-Gunn – licensed under the Creative Commons Attribution.
Advanced Construction Technology By Professor Chris Gorse & Ian Dickinson – licensed under the Creative Commons Attribution – Non- Commercial – Share Alike.
Steps of Addition Move your mouse over each step to see the directions.
Advanced Construction Technology By Professor Chris Gorse & Ian Dickinson – licensed under the Creative Commons Attribution – Non- Commercial – Share Alike.
Organize Project Team 1 Project is to build Crew Boat facility on Lake Washington Construction Management involves working in teams to meet owner requirements.
Sustainability in Non Domestic Construction By Professor Christopher Gorse – licensed under the Creative Commons Attribution – Non-Commercial – Share Alike.
Steel Fabrication & Erection of Belle Chasse Primary School ET-493 Final Proposal Spring 2015 Instructor: Chris Koutsougeras Advisor: Edward Rode’ Derek.
Temporary Works – P8 Project Practice.
Plan for the installation of the TAMU screen
Steel Erection 29 CFR 1926, Subpart R
Click anywhere to get started…
COLUMNS SLIDE SHOW.
Mississippi Riverbank Project (Final Presentation) May 14, 1999
Covanta Mid Atlantic Region Safety ALERT
How will you take care of your research data?
ACCESS EQUIPMENT.
Building Construction
INTRODUCTION TO THE NEW SUBPART R
Steel Erection 29 CFR 1926, Subpart R
Presentation transcript:

Advanced Construction Technology By Professor Chris Gorse & Ian Dickinson – licensed under the Creative Commons Attribution – Non- Commercial – Share Alike License

Erection of skeleton frame Chris Gorse and Ian Dickinson These slides should be read in conjunction with Emmitt, S. and Gorse, C. (2010) Barry’s Advanced Construction of Buildings. Oxford, Blackwell Publishing

Erection of skeleton frame

1. Structural members are positioned ready to be craned into position. Foundations and holding down bolts are ready to receive columns

2. Structural members lifted and bolted in position

3. Crane lifts beam and the steelfixers work on cheerypickers – Mobile Elevated Working Platforms (MEWPs) to secure the frame

Beam is fixed to column

Podger (spanner with pointed end) is used to line up bolt holes for the bolts.

4. The construction of the frame starts at one end of the site and works out

Crane holds the beam while it is located and bolted in position

5. Crane holds the beam while it is located and bolted in position

Skeleton frames and core structures The skeleton frame can also makes use of the concrete core that forms the lift shaft The lift shaft adds extra stability to the skeleton frame

Task Produce a logical schedule of the activities required to erect a steel frame.

Model Answer for Task (Steel Frame Erection) Produce a level hard standing for cranes, lorries and other lifting equipment to safely access the site and erect the frame. Check the level of concrete bases and position of holding down bolts. Place necessary packing shims to ensure the column bases are all at the same level. Work out from the most inaccessible area of the site ensuring that equipment is not trapped on site.

Lift the columns into position and while secured by the crane fix to holding down bolts. Once a bay or line of columns have been erected the beams can be lifted into position. The beams can be bolted into place with workers access in the connection on MEWP (cherry pickers). While elevated all workers should be wearing restraining harnesses.

Once the beams and columns are connected they should be checked for line and level. The process should be repeated until the whole frame is erected. The frame should be checked for line and level and finally adjusted with racking props and pulleys. Once in position the bolts to the columns should be grouted in.

Further information supporting these slides can be found in the following publication and websites. Emmitt, S. and Gorse, C. (2010) Barry’s Introduction to Construction of Buildings. Oxford, Blackwell Publishing Emmitt, S. and Gorse, C. (2010) Barry’s Advanced Construction of Buildings. Oxford, Blackwell Publishing Virtual Site (2010) Virtual Site at Leeds Met University Virtual Site Gallery (2010) Virtual Site Gallery at Leeds Met University