The Challenges of Programming Construction Projects and Delay Analysis By Keith Kirkwood BSc FRICS, FCIArb, FCInstCES Chief Executive Bennington Green.

Slides:



Advertisements
Similar presentations
Precedence Diagramming
Advertisements

Network Diagramming Network Analysis  The common term for network analysis is PERT  PERT stands for Program Evaluation and Review Technique  The word.
Advanced Project Management - CPH
Project Scheduling Prof. Jiang Zhibin Dept. of IE, SJTU.
Eleanor Roosevelt High School
Project Scheduling: Networks, Duration estimation, and Critical Path.
MGMT 483 Week 8 Scheduling.
5/4/20151 NETWORK SCHEDULING TECHNIQUES. 5/4/20152 Network Diagrams  PMI defines the scheduling process as: “the identification of the project objectives.
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Projects: Critical Paths Dr. Ron Lembke Operations Management.
BSBPMG503A Manage Project Time 6.5 Develop Schedule The process of analysing activity sequences, durations, resource requirements and schedule constraints.
AMERICAN SPORTS BUILDERS ASSOCIATION CRITICAL PATH METHOD SCHEDULING FOR SUCCESS December 6-8, 2008 New Orleans, Louisiana Presented By: Bill Pronevitch.
Importance of Project Schedules
Project Time Management
Software Project Management
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
Where We Are Now. Where We Are Now Developing the Project Plan The Project Network A flow chart that graphically depicts the sequence, interdependencies,
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr.
Time Planning and Con trol Precedence Diagram.  Precedence Diagramming  An important extension to the original activity-on-node concept appeared around.
Time Management Week 7 - Learning Objectives You should be able to: n List and describe the processes, activities, inputs, and outputs in time management.
Abeer Bin Humaid. Project management is “the application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements”
Amin Salari, CCM, PMP, LEED AP – Lundgren Management
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Software Project Management Task Estimating and Scheduling
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
EGNR 300 Project Management Planning & Scheduling ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport,
Network Planning Methods Example PERT & CPM
MS project Abeer Bin Humaid. What is project management? Project management is “the application of knowledge, skills, tools, and techniques to project.
© Construction Management Association of America. Do Not Duplicate or Reproduce. Standards of Practice Course CPM Scheduling Lab.
PROJECT SCHEDULING By Deepika chaudhary. Project Scheduling Scheduling means estimation of time and resources required to complete activities and organise.
Network Planning Techniques Program Evaluation & Review Technique (PERT): Developed to manage the Polaris missile project Many tasks pushed the boundaries.
1 DELIVERABLES OF DESIGN REVIEW 1 Statement of problem/need Customer needs Product Design Specifications (PDS) Design targets Project plan TOOLS USED TO.
PMP, CAPM, PgMP, PMI-SP, PMI-RMP, OPM3 and PMBOK are registered marks of Project Management Institute, Inc Inov8Solutions Inc – Quality Educational Services.
Advanced Project Management Project Time Management Ghazala Amin.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8.
Applied Software Project Management PROJECT SCHEDULES Applied Software Project Management 2:16:07 AM 1.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Planning and Budgeting Recall the four stages Project Definition and Conceptualization Project Planning and Budgeting Project Execution and Control.
Project Management Software Application PRM 705 Lecture 5 Mian Wasim Irshad.
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
1 EASTERN MEDITERRANEAN UNIVERSITY FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING CIVL 493 Construction Management Assoc. Prof. Dr. Ibrahim YITMEN.
CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
CON 2001 & CVE 4070 Construction Engineering Tool #1 - Construction Scheduling Prof. Ralph V. Locurcio, PE.
Reference: Figure 6.2. PMBOK® Guide, 5 h Ed Reference: Figure 6.2. PMBOK® Guide, 5 h Ed.
Mastering Digital Media Project Management November 22, 2007 By: Nagehan & Ahmad.
The Network Diagram. When to Do What?  Carrying out one activity after the other may result in project completion, but it will take the longest possible.
Chapter 16 – Project Management
Project Management MGT 30725
Project Management: PERT/CPM
Project Planning & Scheduling
Project Management (PERT/CPM) PREPARED BY CH. AVINASH
Project Planning & Scheduling
Project Planning and Scheduling
Project scheduling Chapter 10 Copyright ©2016 Pearson Education, Inc.
Chapter 6: Project Time Management
Projects: Critical Paths
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Scheduling Basics Activity on Node Precedence Diagrams
Project Time Management
Project Scheduling: Lagging, Crashing and Activity Networks
Project Time Management
In-Class Scheduling Exercise
Project Time Management
Project Time Management
Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

The Challenges of Programming Construction Projects and Delay Analysis By Keith Kirkwood BSc FRICS, FCIArb, FCInstCES Chief Executive Bennington Green Ltd

Topics Covered 1.A history of Time in Construction Projects 2.How Construction Projects Programmed 3.Understanding links in Construction Programmes 4.Cause and Effect 5.Choice of Delay Method

Project Management

Great Pyramid of Giza

Taj Mahal - India

Joseph Priestly & William Playfair 1786 William Playfair ‘Commercial and Political Atlas’ 1765 Joseph Priestley’s ‘Chart of Biography’ plotted some 2000 famous lifetimes on a time scaled chart

Karol Adamiecki & Henry Gantt

The early basic Gantt chart was a simple "fill in the bar" method to show how much of the project was complete Basic Gantt Chart

As the use of Gantt grew in the early 1900’s the double bar Gantt Chart grew in popularity. Basic Gantt Chart Double Bar

The basic Milestone chart shows only important project events or milestones Milestone Chart

Hoover Dam - USA

PERT chart for a project 5 milestones (10 through 50) 6 activities (A through F). The project has two critical paths: activities B and C, or A, D, and F – giving a minimum project time of 7 months with fast tracking. Activity E is sub-critical, and has a float of 1 month. PERT Diagram

Trident Missile Project - USA

Excavate 2 days Concrete 2 days Brickwork 6 days Coping 2 days Design 5 days Order Concrete 4 days Order Bricks 10 days Activity on Line / PERT Diagram Event No Float Start Finish

Simple four activities all Critical Excavate Concrete Brickwork Coping Activity Description ES LS Dur Float EF LF Activity Link Activity on Node Diagram

Excavate Concrete Brickwork Coping Design Order Concrete Order Bricks Activity on Node Diagram Critical Path shown in Red

Primavera Chart

Hong Kong Airport

London Olympics

Employer Defines scope / Set contractual Terms Contractor analyses risk and use CPM programme then looks at: 1.Pruning critical path activities 2.“Fast tracking" (performing more activities in parallel) 3.“Crashing the critical path" (shortening the durations of critical path activities by adding resources) 4.Re-programming non critical activities to save cost 5.Resource balancing Only then should they price the project. Produce contract programme after award. How Construction Projects Are Programmed

The normal sequential relationship of one activity following another. Activity B cannot start until activity A has finished. Activity A Activity B Links in construction Projects Finish - to - Start

‘d’ implies a normal lag relationship between activities A and B; that is, B cannot start until ‘d’ days have elapsed after activity A has finished. Activity A Activity B d Links in construction Projects Lagged Finish-to-Start

Activity B cannot start until activity A has started or perhaps, more accurately, activity B can start at the same time as activity A but not before it. Activity A Activity B Links in construction Projects Start-to-Start

‘ d’ indicates a start-to- start relationship with the delay imposed showing that activity B cannot start until the period ‘d’ has elapsed after activity A has started. Activity A Activity B d Links in construction Projects Lagged Start-to-Start

A finish-to-finish relationship, activity B cannot finish until activity A has finished. It implies that B can finish at the same time as A, but not before it. Activity A Activity B Links in construction Projects Finish-to-Finish

A finish-to-finish relationship but with a delay, ie activity B cannot finish until ‘d’ days have elapsed after activity A has finished. Activity A Activity B d Links in construction Projects Lagged Finish-to-Finish

There may be occasions where a lag is required both on the start and finish of related activities. Activity B cannot start until ‘d’ days after activity A has started and activity B cannot finish until ‘t’ days after activity A has finished. Activity A Activity B t d Links in construction Projects Lagged Start and Finish

The arrangement in which the successor activity is allowed to start chronologically before the predecessor activity has been completed. Activity B cannot start until 4 days before activity A is planned to finish. Activity A Activity B -4 Links in construction Projects Negative lag

Most project management software allows the planner to specify that an activity must start or must finish on a specific date. Using the software in this way restricts the ability of the programme to react dynamically to change on the project. Effectively setting milestones. Such programme settings are referred to as constraints Links in construction Projects Must Start / Must Finish

1.Errors in original programme 2.Contractor proposed programme changes 3.Changed Conditions 4.Employer Changes 5.Contractor Changes 6.Design Errors or required design changes 7.Circumstances not envisaged at time of tender How Delay Arises

1.What has caused the delay? 2.What is the extent of the delay caused? 3.What programme items were effected? 4.What are the effects of the delay on the programmed items? 5.Who is responsible for the delay under the Contract? 6.Employer Delay Event or Contractor Delay Event Cause and Effect

1.The relevant conditions of contract 2.The objective of reaching a fair and reasonable conclusion economically and proportionately 3.The nature and timing of the causative events 4.The value of the dispute 5.The time available 6.The records available 7.The programme information available 8.He programmers skill level and familiarity with the project 9.The timing of the analysis in relation to the completion of the works Choice of Delay Analysis Method

Thank You