1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.

Slides:



Advertisements
Similar presentations
Stéphane Gabourin TE/MPE-EP 21 st March 2014 BIS & SMP changes for Run 2 SPS – Extractions – Injections – LHC.
Advertisements

Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Etienne CARLIER AB/BT/EC
12/03/2013MPP Workshop Annecy Update on Beam Failure Scenarios Jan Uythoven Thanks to: T.Baer, R.Schmidt, J.Wenninger, D.Wollmann, M.Zerlauth, other MPP.
Accelerator Schedules LHC and LHC Injectors Schedules MSWG meeting 16 January 2015 SPSC - 13 January 2015 Rende Steerenberg, BE/OP2 Rende Steerenberg,
1 MKBH Erratic Jan Uythoven On behalf of the ABT team (Viliam, Nicolas M., Etienne, Laurent, Francesco etc…..) MPP meeting 8/5/2015.
Injection test? Mike Lamont For initial discussion.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
R.Giachino / M.Albert Be/op 12 th March 2012 LHC Machine check out 1v1.
Status Report – Injection Working Group Working group to find strategy for more efficient start-up of injectors and associated facilities after long stops.
What will we do for Beam Preparation: Injection and Beam Dump Jan Uythoven Thanks to M.Barnes, E.Carlier, L.Ducimetière, B.Goddard, R.Jones, Y.Kadi, V.Kain,
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
LMC 27 November 2013 Status of LBDS LS1 activities and plans for 2014 reliability run Jan Uythoven for the many, many people working on the mentioned equipment.
Scrubbing Run: TDI, MKI and MKE interlocks Chiara Bracco, Jan Uythoven ABT/BTP Acknowledgments: T. Baer, M. Barnes, E. Carlier.
LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Dry runs and cold checkout Markus Albert, Reyes Alemany, Rossano Giachino, Delphine Jacquet, Verena Kain, Belen Salvachua Ferrando, Matteo Solfaroli Camillocci.
Running scenario 2009/10 Run through components – and then synthesis.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
Transfer Line Test preparation meeting V. Kain, R. Alemany.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Christophe Martin TE-MPE-EP 02/06/ The BIS and SMP activities during LS1 MPE Group Review, 2 June 2015 Christophe Martin, Stephane Gabourin & Nicolas.
Commissioning / Reliability Runs / Dry runs 1 Jan Uythoven, LIBD meeting on LBDS Reliability Run 04/02/2014 Nov – Dec 2013 Commissioning individual MKDs.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
LBOCM. ZerlauthMarch 06 th 2012 Acknowledgements : B.Todd, C.Martin, I.Romera, E.Carlier, J.Wenninger, C.Zamantzas, S.Redaelli et al. 1v0 MPS Commissioning.
LHC Scrubbing Run 1 Day 3 (27/06/2015) Scrubbing team 28/06/2015.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Dependability Requirements of the LBDS and their Design Implications
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC schedule.
Jan Uythoven For discussion
Saturday 21st April 00:33 Interlock during ramp on BLM HV
LHC Risk Review: Kicker Magnet Reliability
Monday 11/07: Recovery Plenty of accesses.
LHC Morning Meeting - G. Arduini
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Machine availability reaching well over 80%
Summary of Week 11: 14 – 21 March
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Summary of Week 16 G. Arduini, J. Wenninger
LHC Operations overview Week 28 – Getting back
Week 35 – Technical Stop and Restart
Tuesday 22 November 2011.
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Machine Protection System Commissioning plans
Scrubbing progress - 08/12/2012
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Daniel, Gianluca and Belen (for the Collimator team)
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Presentation transcript:

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015

LHC Commissioning Plan & ABT Powering Tests Jan & Feb  ABT commission as much as possible all system for which we don’t need to close the BIS loops Machine Checkout, about week 10 or a bit later  Commission all systems without beam for which we need the loops closed  One week will be tight, usual fight March / April  Machine Commissioning with beam Followed by scrubbing, 50 ns, scrubbing and 25 ns operation 2 Jan Uythoven ABT TCM, 13/1/2015 Latest Quotes: “Single Sector Test weekend 7/8 Feb, but might still have some delay” “First circulating beam in March” “First collisions in stable beams in May”

ABT Commissioning Based on edms documents for MPP  Injection and beam dumping system: updated version to be released before end of January 2015  MKQA system and AC dipole: a lot smaller, but missing procedures. To be written down as well. 3 Jan Uythoven ABT TCM, 13/1/2015

Tests without beam – Loops open System Commissioning  MKI HV conditioning, soft start etc.  LBDS settings, IPOC and XPOC references, BETS etc.  TCDQ movement, interlocking…  HV performance MKQA, AC-dipole Testing of connections to outside world  Beam Interlock System – with BIS team  Vacuum System  SPS extraction interlocking  Etc. For a large part already done, end of January check against updated commissioning procedures and perform the outstanding tests before Machine Checkout period 4 Jan Uythoven ABT TCM, 13/1/2015

Tests without beam, BIS loops closed During week of Machine Checkout  A week will be short for this, however the most important tests should really be done before taking first circulating beams. Pressure will be there to postpone to postpone these tests.  Will require dedicated time for injection and beam dump as we need the loops ‘for us’  Planning to be organised by OP (RG) Check against commissioning procedures list  SPS extraction vs. LHC injection BIS  LHC BIS arming sequences  BETS interlocks, energy tracking checks  Etc. 5 Jan Uythoven ABT TCM, 13/1/2015

Tests with beam, Injection Time estimate of tests with beams has been made and discussed within coordination team Time estimate is 7.5 days of 24 hours of injection work up to first stable beams 11 days of 24 hours including setting up of injection during intensity ramp/up and 25 ns To be done in March and April and following months for intensity ramp up 6 Jan Uythoven ABT TCM, 13/1/2015

Tests with beam, Beam Dump For beam dumping system, incl. TCDQ, estimated commissioning time with beam 8 full days of 24 hours Not much additional work after initial set-up and tests with beam To be done in March and April 7 Jan Uythoven ABT TCM, 13/1/2015

Conclusions LHC is about to start-up Now: transition from individual equipment (experts) tests to integration tests with the rest of the LHC MPP check Procedures to be finished by the end of this month and check inventory of tests outstanding  System tests, stand-alone  Integration tests, but BIS loops open  Machine checkout tests with BIS loops closed  Tests with beam, mainly March and April: many days of ABT work! A lot work to come. Hands and brains needed ! 8 Jan Uythoven ABT TCM, 13/1/2015