Disraeli Bridges Rehabilitation Project Procurement City of Winnipeg Procurement City of Winnipeg Presentation June 18, 2008
Introduction City Project Procurement Team Assisted by: –Deloitte & MMM for procurement and financing –Dillon Consulting Engineers – Technical –TBA Legal Services for RFP & Agreement Fairness Auditor – will be engaged
Procurement Process Project Model – Design Build Finance Maintain (DBFM) Two Stage Procurement Process –Request For Qualification followed by Request For Proposals RFQ –The objective of the RFQ –Evaluation & selection of proponents RFP –Proposal Submission Stages –Agreement –6 month time frame –Evaluation –Break Payment
Procurement Process Contact during the procurement process Project updates and information Obtaining the RFQ document Issue of RFP
Schedule Two Stage - RFQ - Released on June 30, 2008 Submission by Sept. 2, 2008 Advise 3 proponents, Oct 2, RFP - Issued to the 3 selected proponents in October 2008 Submission by April 2009
QUESTIONS