Elements of an Adequate Proposal The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Page.

Slides:



Advertisements
Similar presentations
Comparison of Major Contract Types
Advertisements

1 AIR 2.0 Competency Training Price Analysis Techniques NCMA 20 January 2009 Sandy Scharn-Stevens & Warren Walch References and dollar thresholds reflected.
COST ANALYSIS VS. PRICE ANALYSIS Andrea ONeill Cost/Price Analyst 27 April 2011.
Closeout (Preparing for the End)
The Truth in Negotiations Act (TINA)
Contract Pricing and Pricing Strategies
Subcontracts 101 By Mitali Ravindrakumar USC Collaboration between Parties Perform Subcontractor Analysis Sponsor - Fund Project/Subcontr act Negotiate.
FAR Part 44: Subcontracting Policies & Procedures February 5, 2012.
Accounting System Requirements The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations 1 Further.
DCAA – WHO WE ARE and WHAT TO EXPECT
NCMA Training: Price Analysis for Non-Price Analysts
Provisional Billing Rates
Andrea O’Neill Cost/Price Analyst ACC-RSA. Elements of a Proposal; Proposal Example Indirect Rate Calculations Unallowable Costs; Preparing For Negotiations;
Chapter 22 Cost Control Using Standard Costing and Variance Analysis
Cost Accounting Standards Accounting 6310 Richard McDermott, Ph.D.
Basic Financial Requirements for DoD Government Contracting 2015 National SBIR/STTR Conference The views expressed in this presentation are DCAA's views.
COMMERCIAL “SOLE SOURCE” PROPOSAL ANALYSIS ROADMAP 1. Is information available within the Government? Step 1 – Information within the Government If Yes.
Introduction to Cost and Price Analysis
Contract Pricing – Certified Cost or Pricing Data
Determine the Difference between Internal and External Cost Reporting © Dale R. Geiger
Preparing the GSA Schedule Pricing Proposal
Introductions Mike Dement Multi Management Services
Standard Costing and Variance Analysis
I n t e g r i t y - S e r v i c e - E x c e l l e n c e PPNM’s/PNM’s Date: 29 Dec 2006.
February 2006 The Importance of Subcontract Management to Program Success.
Purchasing.
Mckennalong.com - Truth in Negotiations Act - Overview and Update NCMA Pikes Peak Chapter October 18, 2012 Phillip R. Seckman.
Nuts and Bolts of Government Accounting
Courses that Meet Government Contractor Needs
New NSF Awardee Checklist Requirements: WHY? November 19, 2014 joyce y. JOHNSON POST-AWARDS COORDINATOR OFFICE OF SPONSORED PROGRAMS.
1 Always Changing / Always Challenging Accounting for Government Contracts.
FAR Part 31 Contract Cost Principles and Procedures.
PwC Service Contracting DCAA Interests & Initiatives March 31, 2008.
New Time and Material Requirements Glenn Baer March 2007.
1 Test Operations Contract RFP Volume III ITO Briefing RFP NNS09ZDA008R – TEST OPERATIONS CONTRACT (TOC) Ground rules This presentation is intended to.
Submitting a Quality Offer On the GSA Language Schedule GSA Federal Supply Service.
Introduction to Procurement for Public Housing Authorities Independent Cost Estimates and Cost/Price Analyses Unit 3.
1 Contract Pricing Principles Breakout Session # WC Janie Maddox, CPCM, Fellow and Marge Rumbaugh, CPCM, Fellow Tuesday, July 12 4:00–5:15pm.
Cost Analysis Overview
1. 2 Managing Risk and Reward by Contract Type Breakout Session # 501 Beverly Arviso, CPA, Fellow, CPCM, CFCM, Arviso, Inc. Tuesday, July 31, :30-3:45.
1 DCAA 2016 Initiatives A Roadmap for 8(a) firms to Navigate the Minefield PRESENTED BY Patricia J. Mensch, CPA, CGFM, CGMA Partner Government Contract.
Small Business Insight Into the Business System Review and Audit Process Business Systems Overview.
1 Consent to Subcontract Breakout Session # D12 Name: Rita Wells Daniel Johnson Anthony Simmons Date:July 12, 2011 Time:11:15 – 12:30.
1. 2 Cost & Price Analysis Breakout Session # 312 Beverly Arviso, CPA, Fellow, CPCM, CFCM, Arviso, Inc. Melanie Burgess, CPA, CFCM, Burgess Consulting,
Presented to: By: Date: Federal Aviation Administration Ready for Cost Type Contracts - Accounting Systems and Administration Small Business Vendor Day.
2016 National SBIR/STTR Conference The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations.
Compliance with CCNA F.S..  Advertisement  Longlist  Shortlist  Request for Proposal  Scope of Services Meeting  Technical Proposal Review.
TD Government Solutions
TD Government Solutions
Comparison of Major Contract Types
ANSI/EIA-748-B Earned Value Management Systems (EVMS)
TD Government Solutions
Post Award Peer Review Briefing Slides
Consent to Subcontract
Comparison of Major Contract Types
Comparison of Major Contract Types
By Jacob Barclay and Beverly Arviso
Subcontract Management Responsibilities
DLA Aviation Cost & Price Analysis
Comparison of Major Contract Types
Cost or pricing data John Cancellara 7 March 2018.
Advice to Industry Panel – Contract Management Perspective
Comparison of Major Contract Types
Comparison of Major Contract Types
Certified Cost or Pricing Data vs
IGCE & Technical Evaluation
DLA Land and Maritime Pricing Overview
Comparison of Major Contract Types
Post Award Peer Review Briefing Slides
Presentation transcript:

Elements of an Adequate Proposal The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Page | 1

Welcome INTRODUCTIONS – Presenter Attendees  Name  Company  What Do You Hope to Learn Today? Page | 2

Today’s Discussion Price Proposal  Price Proposal Adequacy  Common proposal deficiencies Adequate Cost and Pricing Data On-line Resources Page | 3

Proposal Adequacy Contractor is responsible for providing adequate supporting data. The contractor bears the burden of proof in establishing reasonableness of proposed costs. The basis and rationale for all proposed costs should be provided as part of the proposal so that the government can place reliance on the information as current, accurate, and complete. Page | 4

FAR Part 15, Table 15-2 – Instructions for submitting cost/price proposals when certified cost or pricing data are required. DFARS Proposal Adequacy Checklist - New Requirement - Provides location of requested information or an explanation of why the requested information is not provided. How is proposal adequacy determined? Page | 5 Price Proposal Adequacy

Proposal Cost Elements Direct Labor Material Subcontracts Other direct costs (ODCs) Indirect rates Page | 6

Direct Labor Contractor should have detailed schedules of the labor rates and hours used in the proposal. An adequate proposal should include: The basis of proposed labor rates and classifications including any escalation factors:  DCAA will determine how proposed labor rates were estimated and will need to audit any data that supports these estimates.  DCAA will evaluate the basis of labor categories (labor grades) proposed and the hours assigned to each labor category. The basis of proposed labor hours, comparisons of proposed hours to experienced hours for the production of similar items; and any learning curve applications. Page | 7

Material An adequate proposal should include a consolidated priced summary of individual material quantities included in the various tasks, orders, or contract line items. In addition, the consolidated bill of material should provide:  The basis for pricing (vendor quotes, invoice prices, competitive bids, etc.)  Include raw materials, parts, components, assemblies, and services to be produced or performed by others.  Identify the item and show the source, quantity, and price. Page | 8

Price Competition  DCAA has found contractors inappropriately claiming there is adequate price competition.  Contracting officers directed to no longer limit their analysis to the FAR (c)(1)(ii) and (iii) to determine that the offered price is based on adequate competition when only one offer is received.  Contracting officers may require cost or pricing data, or other than cost or pricing data when only one offer is received. Page | 9

Subcontracts An adequate proposal includes the basis of proposed subcontract costs including the prime contractor’s price analyses of all subcontractor proposals.  Submit the subcontractor’s cost or pricing data as part of your own cost or pricing data, as well as your analyses of the subcontractor’s cost or pricing data per FAR and FAR (b)  Include data showing the degree of competition and the basis for establishing the source and price reasonableness  The prime contractor is responsible for managing its subcontracts per FAR (e)(2) Page | 10

Examples of Subcontract Analysis Procedures If sole source: performed review of subcontractor’s proposal by reviewing accounting records, supporting documentation, etc. If sole source: used procedures to determine if subcontract is “fair and reasonable” such as benchmarking, industry standards, etc. If competitive: obtained adequate competition to demonstrate “fair and reasonable” price No cost or price analysis completed/documented No documentation on attempts to perform analysis when denied access to subcontractor’s records AdequateInadequate Page | 11

Subcontract Analysis Adequate Analysis: Reduced audit time Cost savings in reduced audit support Timely audit report Inadequate Analysis: Unsupported costs Adverse audit opinion Increased audit time and support costs Negotiation delays Page | 12

Adequate or Inadequate Subcontractor’s proposed labor rate is an average of 100 manufacturing employees. The prime contractor’s cost analysis states: “We recalculated the average labor rate and considered the labor rate reasonable.” Adequate or Inadequate? Page | 13

Answer INADEQUATE Page | 14

Improvements to Consider Subcontractor’s proposed labor rate is an average of 100 manufacturing employees. In addition to a recalculation consider the following: When averaging ensure representative of function being bid Validate labor rates by employee to labor records Compare labor rates to market labor rates Document the scope of the labor rate evaluation Page | 15

Indirect Costs An adequate proposal includes the basis of the proposed indirect expense rates. Required support is at least the current year detailed operating budget and a long range forecast/strategic plan covering all the periods of performance. The operating budget should be at the department/pool level with expense item detail supporting anticipated contract performance. The budget should detail indirect expenses and show the relationship of direct labor (or other indirect expense allocation bases) to sales projections. Support also includes comparisons by year of projected overhead expenses by account to prior years’ incurred amounts. Out-year projections should be supported by the contractor’s analysis of the impact on its rates based on its long range forecast/strategic plan. Page | 16

Requirements FAR – Table 15-2 II Show trends and budgetary data to provide a basis for evaluating the reasonableness of proposed rates. Page | 17

Budgetary Data Straight-lining out-year rates for future periods with no explanation is not adequate. Support for out-year pools and bases should be made based on reasonable sales forecasts and contractor’s assumptions for changes, if any, to major cost groupings (e.g., variable, semi-variable, and fixed). Small firms with limited budgetary data can use historical costs to estimate out-year rates. However, the contractor should provide trend data with appropriate explanations to support that the historical costs are the most reasonable estimate. Page | 18

Examples of Budgetary Data Strategic planning data provided for all years of proposal’s period of performance Ensure “flat lined” rates over proposal’s period of performance are adequately assessed and supported with historical trends and data Detailed budgets provided for first few years of period of performance and strategic planning data provided for remaining years of period of performance “Flat-lined” indirect rates with no support for using the same rate each year of the period of performance No detailed budgetary data provided Projections provided for only the first year of proposal’s period of performance AdequateInadequate Page | 19

Budgetary Data Adequate Data: Better planning Efficient and timely audits More accurate cost estimates Inadequate Data: More lengthy audits Adverse audit opinion Delay in negotiation Page | 20

Adequate or Inadequate Explanation Adequate or Inadequate? Page | 21

Adequate or Inadequate INADEQUATE Page | 22

Improvements to Consider Straight lining out-years rates for lack of budgetary data is not acceptable. Consider the following: Explain differences in trended rates Explain why the rate will not change Consider an analysis of fixed, variable, and semi- variable costs Any upcoming changes Page | 23

Adequate Cost or Pricing Factual and verifiable Includes data in forming a basis for judgment All facts that can be reasonably expected to contribute to the soundness of estimates of future costs and to the validity of determination of costs already incurred Page | 24

Definition/Requirements FAR – Cost or Pricing Data All facts existing up to the time of agreement on price which prudent buyers and sellers would reasonably expect to effect price negotiations significantly. FAR Requires certification that data is current, accurate, and complete. Truth in Negotiations (TINA) (10 U.S.C. 2306(f)) Requires contractors to submit accurate, complete, and current cost or pricing data when negotiating contracts with the Government. It also provides the Government with a price reduction remedy if a contractor fails to comply and provides provisions for interest and penalties. Page | 25

Examples of Cost or Pricing Vendor quotations Purchase orders Make-or-buy decision Accounting records Information on production methods Data supporting projections of business prospects A few examples of cost or pricing data: Page | 26

Cost or Pricing Data Adequate Cost or Pricing Data: Better estimating More timely and effective audits Accurate follow-on pricing Inadequate Cost or Pricing Data: Potential for defective pricing Longer audits Poor estimating Inaccurate follow-on pricing Page | 27

Adequate or Inadequate In price proposal dated January 2013, unit 1X52 is estimated at $2,000/per unit based on: Purchase order number 124 dated January 6, 2008 Adequate or Inadequate? Page | 28

Adequate or Inadequate INADEQUATE Page | 29

Improvements to Consider While the purchase order is verifiable, it is not current. Consider the following: Current competitive quote Market pricing Adjust estimated prices for cost trends and quantity Ensure non-recurring costs are not included in unit- price Make or buy analysis Inventory on hand Cost or pricing data if over threshold Page | 30

Cost or Pricing Data Considerations Labor: Historical data - its use or nonuse Basis for escalation factors Turnover Compensation issues Changes in compensation policy Market rates to demonstrate reasonableness Historical skill mix to demonstrate basis of estimate Improvement curves Page | 31

Cost or Pricing Data Considerations Indirect Rates: Internal budgets Basis of escalation factors Changes in headcount Sales forecast Historical rates/accuracy of previous forecasts Ongoing issues (e.g., CAS) Any known accounting issues that may impact rates Page | 32

Historical Data Estimates based on historical data should consider: Learning efficiencies Prior non-recurring costs Escalating/diminishing costs Representative/Non-representative aspects of historical cost used to estimate Page | 33

Unallowable Costs Ensure proposed rates/costs exclude unallowable costs FAR GAAP Allowable per FAR Reasonable Limitations on contract Allocable CAS, if applicable Expressly Unallowable: FAR X Examples: Fines, Penalties, Entertainment, Contributions Page | 34

Recurring Deficiencies in Price Proposals  Inadequate cost or pricing data  Lack of/inadequate budgetary data  Failure to perform subcontract analysis Page 35

Wrap Up Pricing proposals should include the following:  Cost or pricing data which supports all proposed costs  Budgetary Data (or support for proposed indirect rates) for the entire period of performance  Subcontract analysis, if applicable. Page | 36

Resources DFARS   FAR   DCAA   Proposal adequacy checklist  Information for Contractors Page | 37