A REVIEW OF THE REMEDIATION ALTERNATIVES FOR BENZENE CONTAMINATION AT THE PESTER REFINERY COMPANY SUPERFUND SITE Jonathan M. Diller, P.E., CFM for University.

Slides:



Advertisements
Similar presentations
Dion Novak, EPA Region 5 RPM
Advertisements

Former NAS Moffett Field
Fultz Landfill Site Remediation Ohio by Simon Taylor.
By Chris Ford and James Hughes ( ) ( )
Cytec Statement of Basis and Permit Modification July 16, 2012 Public Hearing Ohio Environmental Protection Agency.
U.S. Environmental Protection Agency Technical Assistance Services for Communities 2012 Review of Preliminary Phase II Groundwater Report J. Stuart Wiswall,
J-Field Edgewood Aberdeen Proving Ground. Description From 1940 to 1970s, the Army disposed of chemical agents, high explosives and chemical wastes. APG.
BoRit Superfund Site Timeline
John Lynch, P.E. Palisade Software Miami Users Conference October 25,
PROPOSED REGIONAL GROUNDWATER REMEDIAL ACTION ROOSEVELT IRRIGATION DISTRICT June 11, 2010.
AHMET UCANOK JOHN E. ELVIS Pump and Treat of Contaminated Groundwater at the United Chrome Superfund Site Corvallis, Oregon.
Stave Lake Water Supply & Treatment Project. Existing Water Supply System Norrish Creek Cannell Lake 19 Groundwater Wells.
Environmental Geotechnology Presentation Site OT-16B, Shaw Air Force Base, South Carolina, USA By Oliver Edwards And Alaric Shenton.
Hazardous waste. Threatens human health or the environment in some way because it is –toxic –chemically active –corrosive –flammable –or some combination.
+ Water Quality & Human Health: From Arsenic Exposure to Biological Response Understanding how contaminants move through the environment UNC Superfund.
Federal Mogul Department for Environmental Protection Kentucky Division of Waste Management February 10, 2015 Presented by Chris Jung To Protect and Enhance.
Presented by: Jonathan Silvester Oliver Kiernan. Maxey Flat Site Located in Fleming County, Kentucky Low level Nuclear Disposal Facility o Isolate waste.
Sydney Olympic Park Environmental Geotechnology By Lucien Power and Thomas Watson.
“GAS MART” petroleum facility in Florida By: Ernest Twum-Barimah Zhengzhong Fang (John) Zhengzhong Fang (John)
B ROWN W OOD P RESERVING S UPERFUND S ITE Live Oak, Florida U.S. Environmental Protection Agency Lisa Moore Daniel Stern.
Presentation to the Hillcrest Community Meeting Conclusions Regarding Groundwater Contamination February 24, 2011 George Rice 1.
1 Kent S. Sorenson, Jr. Ryan A. Wymore Enhanced Bioremediation for Treatment of Chlorinated Solvent Residual Source Areas – Case Study and Implications.
EnviroSense, Inc. An Overview of Environmental Factors in Developing Brownfields Sites in Massachusetts Presented By: Eric S. Wood, P.Hg., PG, LSP President.
1 Risk Assessment Develop Objectives And Goals Develop and Screen Cleanup Alternatives Select Final Cleanup Alternative Communicate Decisions to the Public.
Human Health Effects of Hydraulic Fracturing Fluid BTEX Components in Drinking Water Ashley Andersen, Nicole Fenton, Alex Friedman, Kevin Jackson, Alec.
Arsenic Trioxide and the Summitville Mine Superfund Sites Frances L. Costanzi, P.E - EPA RPM.
McCoy Field Proposed Keith Middle School Site EPA Proposes Approval of McCoy Field Cleanup Plan.
Overview of USGS Groundwater Quality Assessment Activities and Related Data in Alabama 2011 Alabama Water Resources Conference September 9, 2011, Perdido.
Landia Superfund Site: Green Remediation and Green Infrastructure Support Sustainable Development Douglas Reid-Green, BASF Corporation.
Update on the Superfund Program: U.S. Tour de Table NATO SPS Pilot Study Prevention and Remediation in Selected Industrial Sectors June 17-23, 2006 Ljubljana,
Fort Ord, Monterey County, California History and Closure of a Landfill on a former Military Installation and Current Superfund Site Derek S. Lieberman,
TURNING BROWNFIELDS. Definition US EPA 1997 abandoned, idled or under-used industrial and commercial facilities where expansion or redevelopment is complicated.
Spectron Superfund Site Proposed Plan Contaminated Shallow Soils U.S. EPA Region III June 26, 2003 Philadelphia, PA Robert J. Sanchez US EPA - Remedial.
History and Cleanup at Chemical Commodities, Inc. Jeff Field US EPA Region 7 1.
1 The Use of Institutional Controls Under the RCRA Corrective Action Program.
Bioremediation-From the Lab to the Field
Former DuPont Barksdale Works Project Update December 14, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center.
Monitored Natural Attenuation and Risk-Based Corrective Action at Underground Storage Tanks Sites Mike Trombetta Department of Environmental Quality Environmental.
SITE STATUS UPDATE TOP STOP PETROLEUM RELEASE SITE GUNNISION, UTAH Morgan Atkinson – Division of Environmental Response and Remediation, Project Manager.
Review of Current Conditions Report and Work Plan for Area 1 Presented by The Great Plains/Rocky Mountain Technical Outreach Services for Communities.
DNAPL Recovery System July 2010 Progress Meeting McCormick & Baxter Superfund Site Portland, Oregon.
Area I Burn Pit Santa Susana Field Laboratory RCRA Facility Investigation Work Plan February 19, 2008 Laura Rainey, P.G. Senior Engineering Geologist California.
Providing Safe Waterfowl Feeding Habitat in Toxic Floodplains
Tulsa Fuel & Manufacturing Superfund Site Remedial Design and Cleanup Plans September 2014.
Hazardous Waste Management Legislation RCRA – Resource Conservation and Recovery Act Regulate management and disposal of wastes currently being produced.
The Resource Conservation and Recovery Act of 1976 and 1989 (RCRA) Alex Chenault Period 4.
ESAC Meeting December 1, pm LOS REALES LANDFILL UPDATE Entrance Facility Rodeo Wash Erosion Control Structure Scale House Drainage and other Stormwater.
1 FORMER COS COB POWER PLANT From Characterization to Redevelopment Brownfields2006 November 14, 2006.
Environmental Site Assessments Hazardous Materials/ Regulated Substances Categorical Exclusion Training Class.
The Dalles, Industrial Certification Northwest Aluminum Company The Dalles, Oregon Douglas C. MacCourt Ater Wynne LLP US German Bilateral Working.
GEORGIA PACIFIC WEST PROPOSED INTERIM ACTION Public Meeting & Open House – July 12, 2011.
Former Spellman Engineering Site Project Update Meeting March 18, 2008 William C. Denman, P.E. Remedial Project Manager (404)
The Woodlawn Landfill Site A Case Study in the Values and Methods of Ecological Revitalization.
1 ICs at the WDI Superfund Site Brownfields 2004 St. Louis, MO Sarah Mueller U.S. Environmental Protection Agency Office of Regional Counsel Region 9,
Sustainability Week BUS& 201 Business Law Shana Chung December 3, 2014.
Proposed Plan for No Further Action
Sustainable Remediation Case Studies
Cover Slide TCEQ logo.
THE SUPERFUND PROCESS Assessment and Listing
Pollinator Protection in Region 4
ASSESSMENT OF CORRECTIVE MEASURES PUBLIC MEETING
East Hennepin Avenue Site
U.S. Environmental Protection Agency
Chemical Metals Industries, Inc. (CMI)
Area C Location 1.
The Stringfellow Acid Pits
RINGWOOD MINES/LANDFILL SITE PUBLIC MEETING December 6, 2016
UNC Superfund Research Program
Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) Purpose To address the hazards to human health and the environment presented.
Chemical Metals Industries, Inc. (CMI)
Presentation transcript:

A REVIEW OF THE REMEDIATION ALTERNATIVES FOR BENZENE CONTAMINATION AT THE PESTER REFINERY COMPANY SUPERFUND SITE Jonathan M. Diller, P.E., CFM for University of Florida SWS 6262 – December 2012

 Former Refinery Burn Pond  RCRA investigation began in  Remedial action began in 1992 with an interceptor trench.  The trench was located between the pond and the nearby river - the West Branch Walnut Creek.

 Contaminants of Concern:  The 1992 ROD listed 11 compounds as COCs for the burn pond soils -10 aromatics and barium.  The 1998 ROD listed 18 compounds as COCs for groundwater - 13 organics and 5 inorganics.

 10 of the COCs for groundwater were not listed as COCs for the soils.  In 1998 the burn pond and the soils beneath were classified as one operational unit (OU1) and the groundwater as another (OU2).  It was decided to take no remedial action on the groundwater (OU2): not even collecting detailed groundwater monitoring data.

 The ROD of 1995 merged OU1 and OU2 into one operational unit.  It set forth the requirement for establishing a groundwater monitoring program.  Data collection began in  This data showed that benzene was a contaminant that consistently exceeded its MCL.

 Benzene is a known carcinogen.  Benzene has been shown to be most harmful when inhaled or ingested.  Benzene has a low maximum contaminant level (MCL) of 5 parts per billion.

 This data indicates that there is a need to address the benzene contamination in the groundwater.  The pond soils have been excavated and solidified and a cap placed over the old pond.  It may not be necessary to address the contaminated pond and soils as a source but this will need to be monitored.

 The source of the benzene is not understood. It was never identified as a contaminant in the soil.  This leaves treatment of the groundwater as the only option to address the contamination.  So what are the groundwater treatment options?

 One option is pump and treat.  This option would require a substantial capital and ongoing operations and maintenance cost.  The necessary duration of remediation activities is uncertain.

 A minimum anticipated capital cost for a pump and treat system would be $225,000.  Again this would require ongoing operations and maintenance cost with an uncertain system life because the source is not known.

 Another option is passive bioremediation using poplar trees.  This option was identified by Barac, et al. in a paper regarding the containment of a BTEX plume using poplar trees.  This study showed the effectiveness of using a row of poplar trees to confine and reduce the extent of a BTEX plume.

 This approach has a much lower capital cost and practically no ongoing maintenance costs.  The estimated installation cost for a containment row of poplar trees is approximately $40,000 including design cost.  There would be no ongoing maintenance costs after the first two years.

 The row of poplar trees would be between the pond and the West Branch Walnut Creek.  Since the site itself is restricted use the groundwater contamination under the site is not a concern.  This option is a low cost potential remediation system to address the migration of benzene contaminated groundwater from the site.

SUMMARY and CONCLUSIONS  The Pester site has a long history of minimal remediation activities either required or performed.  No efforts have been made to address the source of benzene contamination in the groundwater or remediate the contamination.

 The installation of high capital cost solutions with ongoing maintenance costs is unlikely to be required.  The installation of the poplars is a relatively low capital cost alternative with practically no ongoing maintenance costs.  The solution has no decom- missioning cost if it is ineffective. You simply have a nice row of screening trees along the creek.

References Barac, T., Weyens, N., Oeyen, L., Taghavi, S., Lelie, D., Dubin, D.,... Vangronsveld, J. (2009). Field Note: Hydraulic Containment Of A Btex Plume Using Poplar Trees. International Journal of Phytoremediation, Environmental Protection Agency. (1992). EPA Superfund Record of Decision Amendment: Pester Refinery Co. (EPA ID: KSD ). (Impact factor: NA, government publication) Environmental Protection Agency. (1998). EPA Superfund Record of Decision Amendment: Pester Refinery Co. (EPA ID: KSD ). (Impact factor: NA, government publication) Environmental Protection Agency. (2005). EPA Superfund Record of Decision Amendment: Pester Refinery Co. (EPA ID: KSD ). (Impact factor: NA, government publication) Environmental Protection Agency. (2011). Site Description: Pester Refinery. (EPA ID: KSD ). (Impact factor: NA, government publication)