Electric Ductbank Project – Completed January 2010 New Brick Paver Sidewalk and Concrete Curb
New Princeton Elm
Steam Tunnel Replacement Project – Package 2 – Complete – Package 3 – March 2009 thru Summer 2012 Cameron Avenue McCauley Street South Columbia Street Ransom Street Pittsboro Street
Steam Tunnel Replacement Project – Package 2 – Complete – Package 3 – March 2009 thru Summer 2012 Cameron Avenue McCauley Street South Columbia Street Ransom Street Pittsboro Street TUNNEL 90% COMPLETE IN UTILITY CORRIDOR RANSOM STREET OPEN TO THRU TRAFFIC SINCE END OF JANUARY 2010 PITTSBORO STREET AND MCCAULEY STREET AREA
Phasing at Pittsboro/Carolina Inn Pittsboro Street to MH-312: Today thru Jan 2011 South Columbia Street: Summer 2010 Mid-May thru mid-Aug Temporary Steam Piping: May thru Jan 2011
Phasing at Pittsboro/Carolina Inn Pittsboro Street to Carolina Inn: Jan 2011 thru December 2011 Temporary Steam Piping: Jan 2011 thru December 2011
Phasing at Pittsboro/Carolina Inn Pittsboro Street to Carolina Inn: Jan 2012 thru June 2012
PROGRESS PHOTOS LOOKING EAST TOWARDS NEWMAN CENTER LOOKING WEST TOWARDS RANSOM STREET
PROGRESS PHOTOS LOOKING EAST TOWARDS WHITEHEAD DORMITORY TYPICAL WATERPROOFING OF TUNNEL IN UTILITY CORRIDOR
April 2010 Cogeneration Facility, New Storage Building Project Storage Building Site Start Construction mid-May 2010 Complete Construction January 2011