Factory Building Symposium on Lean Production January 29, 2007 Austin, Texas
Four Seasons Housing, Inc. Middlebury, IN Austin Baidas, CEO and President Level the Load
Four Seasons Housing Started:1994 Location:Middlebury, IN Home type(s):Primarily HUD Code Price point:Moderate Design:Limited customization Production:10 floors/day Market area:Northern US
Objective: Balance the Line Eliminate non-value added (NVA) activity Reduce cycle time variability › Station to station › Floor to floor
Strategy 1.Map product flow 2.Analyze data to identify causes of cycle time variability 3.Implement solutions that reduce NVA and control cycle time variability
Sources of Variation Double vs. single floor stations Variation in complexity from A to B half Tactic: Convert single floor stations to double floor stations
Then Raw Material Roof Ass’y Raw Material Mud Pit Raw Material Side Wall Jig End Wall Plumb & Tile Mud Pit Raw Material 5 Interior Walls 1A Frame 1B Post-Frame 2B Pre-Floor 2A HVAC, H 2 O, DWV 2C Decking3 Plumb, Util., Floor4 Cabinet Set 6 End, Side, Drywall & Electrical 7 Side, Drywall, Elec. 8 Marriage, Drywall & Electrical 9 Roof Set, Drywall & Electrical 10 Rough Roof, Exterior & Interior 11 Shingle, Siding & Interior 12 Sofit & Fascia 13 Mud, Dry, Prep Paint, Dry, Finish Heater Cabinet Shop Interior Walls Cabinet Tops Upper Cabinet Cabinet Shop Plumb & Tile HVAC Mezzanine
Now Interior Walls Cabinet Tops Upper Cabinet Raw Material Roof Ass’y Raw Material Mud Pit Side Wall Jig End Wall Mud Pit HVAC Mezzanine Cabinet Shop Plumb & Tile HVAC Mezzanine 2B Decking 3 Plumb, Util., Tile5 Interior Walls 6 End, Side, Drywall & Electrical 7 Side, Drywall, Elec. 8 Marriage, Drywall & Electrical 9 Roof Set, Drywall & Electrical 10 Rough Roof, Exterior & Interior 11 Shingle, Siding & Interior 12 Sofit & Fascia Paint, Dry, Finish 13 Mud, Dry, Prep Paint, Dry, Finish 13 Mud, Dry, PrepPaint, Dry, Finish 2A Floor Box Heater Raw Material 4 Cab. & Utility Set Buffer 2A Electrical 13 Mud, Dry, Prep
Future Raw Material HVAC Mezzanine Raw Material Roof Ass’y Mud Pit Raw Material Side Wall Jig End Wall 3 Decking Heater 8 Marriage, Drywall & Electrical 9 Roof Set, Drywall & Electrical 11 Shingle, Siding & Interior 12 Sofit & Fascia Paint, Dry, Finish 13 Mud, Dry, PrepPaint, Dry, Finish 13 Mud, Dry, Prep 2 Floor Box 4 Plumb Interior Walls Cabinet Tops Upper Cabinet Lower Cabinet Utility Prep. Plumb 6 Interior Wall Set 7 End, Side & Mate Wall 5 Cabinet Set, Tile & Utility Set 10 Rough Roof, Exterior & Interior
Results Reduced through-put time 27% All production within facility Eliminated NVA protection for outside floors Eliminated NVA moves Identified real-time data collection requirements Started a kaizen project list
Highlights Lean initiative driven by business objective Established lean process Identified root cause Listened to the data Workers contributed mightily
Lessons Lean cannot be forced by one person Involve employees Allow team to own the decisions Lean is a process
Going Forward Refine our lean process Conduct kaizen events to improve efficiency in departments Revise plant layout to convert to double floor stations
Lean Symposium
Manufactured Housing Research Alliance Jordan Dentz (212) x13 Factory Building Symposium on Lean Production