Southwest LRT Project Craig Lamothe, AICP Senior Project Manager 2011 MN State Planning Conference September 29, 2011.

Slides:



Advertisements
Similar presentations
Client logo MnDOT - ACEC/MN Annual Conference Creating Multimodal Connections Facilitator Patrick Watz, AECOM March 5, 2013.
Advertisements

Improvements to Project Development and Program Management of New Starts Projects FY 2008 Proposed Effective April 30, 2006.
TBITE 05/15/ Heather Sobush, Senior Planner Christopher Cochran, Senior Planner
FTA’s Small Starts Program Charlotte, North Carolina October 11, 2007.
CONNECT COBB Northwest Transit Corridor Alternatives Analysis Town Center Area Community Improvement District Update March 27, 2012.
Chicago Transit AuthorityJune, 2007 Chicago Transit Authority Regional South Metro Transportation Summit June 16, 2007 Matteson, Illinois.
Gilbert Road Light Rail Extension Transportation Project Advancement Agreement City Council Study Session December 4, 2014.
Capital Investment Program Listening Session Presented at APTA Annual Meeting -- 10/03/2012 RailVolution /14/
Woodward Light Rail Transit Project NAMC Detroit Transporation Symposium September 15, 2011.
Passenger Rail Development Activities AASHTO Annual Meeting October 18, 2013 Serge Phillips, MnDOT Federal Relations Manager.
Federal Transit Administration New Starts Project Development Process
BRT Workshop July 21-22, 2008 The PMOC Program and the Euclid Corridor Transportation Project1 The PMOC Program and the Euclid Corridor Transportation.
SCORT Annual Meeting Jacksonville, Florida September 20, 2010 Passenger Rail in Florida.
1 AASHTO: SCOPT/MTAP Winter Meeting METRO Update: Light Rail Operations and the Status of Future Corridors Wulf Grote, P.E. Director, Project Development.
Public Transit in Sacramento
Minnesota Department of Transportation ARRA, Greater Minnesota Transit, Airport Program Status, & Local Bridge Bonding Update House Transportation Finance.
FasTracks Moving Forward: Regional Transportation Plan (RTP) Amendment Staff Recommendation Phillip A. Washington and Team August 7, 2012.
David Armijo, CEO Hillsborough Area Regional Transit Potential Transit Enhancements With Gas Tax Funding Hillsborough County Transportation Task Force.
Case Study 3 — New Rail Starts: Seattle Monorail & LRT Britta Stein Justin Scott Wenteng Ma.
FY2007 New Starts Annual Report & Introduction To Discussions New Starts/Small Starts Listening Session and Seminar San Francisco, CA February 15-16, 2006.
Trends in Urban Transit in the U.S. – Some Comparisons Edd Hauser, P.E., PhD Nicholas J. Swartz, MPA Center for Transportation Policy Studies UNC Charlotte.
Freight Bottleneck Study Update to the Intermodal, Freight, and Safety Subcommittee of the Regional Transportation Council September 12, 2002 North Central.
Northern Lights Express High Speed Rail: MN APA Conference September 2011.
“High Speed Rail Implementation - An Update on Passenger Rail Planning Activities in Minnesota.” presented by: Minnesota Department of Transportation March.
Large Starts Issues for the Notice of Proposed Rulemaking New Starts/Small Starts Listening Session and Seminar San Francisco, CA February 15-16, 2006.
QGET -- Scenarios Analysis Quality Growth Efficiency ToolsNovember 14, 1998 November 15, 1999 Strategy Analysis Prepared for: Envision Utah Prepared by:
Moving the Most People for the Least Cost Preserving the American Dream Conference Friday, September 24, 2010.
1 Program of Projects Study The Impacts of Regional Transit Investment Forum March 21, 2013 Move LA - "LA's Got Lines"
Passenger Rail Planning Activities in Minnesota presented by: Minnesota Department of Transportation March 15, 2011.
1 Governance Council Meeting Fiscal Year 2004 LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY GATEWAY CITIES SERVICE SECTOR December 18, 2003.
The FY 2006 New Starts Report Responding to the Demand for Transit.
Public-Private Partnership Program 2015 Update 2015 American Council of Engineering Companies ACEC – Los Angeles Chapter Luncheon, July 8, 2015.
MAP-21: Impacts to New Starts and Small Starts Senate Transportation Finance and Policy Committee Mark W. Fuhrmann Program Director, New Starts February.
Citizens Advisory Committee Quarterly Update Bill Van Meter, Assistant General Manager, Planning September 19, 2012.
LYNX FY2011 and FY2012 Budget Considerations Orange County Board of County Commissioners Linda S. Watson LYNX Chief Executive Officer February 23, 2010.
AGENDA OPEN HOUSE 6:00 – 8:00 PM  Review materials  Ask questions  Provide feedback on purpose, needs, and alternatives  Sign up for list  Fill.
OPEN HOUSE #4 JUNE AGENDA OPEN HOUSE 6:00 PM  Review materials  Ask questions  Provide feedback  Sign up for list  Fill out comment.
New Starts/Small Starts and BRT: An Update APTA Bus Conference Seattle, WA May 5, 2009.
1 MetropolitanCouncil Transit CapitalImprovement ProgramOctober 22, 2008.
A Very Small Starts Proposal CAN be easier than you think Karl Otterstrom, AICP Spokane Transit, Director of Planning Spokane, WA QUALITY TRANSIT -- NOW.
New Starts/Small Starts Workshop APTA’s Legislative Conference March 14, 2007.
Northstar Commuter Rail Project Update Mark Fuhrmann, Project Director Rich Rovang, Deputy Project Director, Design and Construction Chris Weyer, Assistant.
Central Corridor LRT Review of Washington and Northern Alignments Jan Lysen and John Siqveland December 10, 2009 Image: MPR News Q.
NEW STARTS/SMALL STARTS. New Starts Eligibility  Based on the results of planning and Alternatives Analysis  At least 50% or more of the total project.
1 New Starts Dialogue Welcome to the FTA Webinar March 21, 2005 Jennifer L. Dorn FTA Administrator.
Federal Funding Challenges and Opportunities David Vozzolo Vice President National Transit Planning and Project Development.
PROJECT UPDATE PUBLIC OPEN HOUSE #5 MARCH 12 4:00 PM – 6:00 PM Northern Service Center.
New Starts/Small Starts Program APTA Legislative Conference Washington, DC March 12, 2008.
Metropolitan Council 1 Twin Cities Region Transportation Policy Plan Nacho Diaz Metropolitan Council Evaluating Economic and Community Impacts of Transit.
Los Angeles County Metropolitan Transportation Authority FY16 Budget Development: Preliminary Capital Program Board Staff Briefing February 12, 2015 The.
North Metro Competitive Procurement RTD Board FasTracks Monitoring Committee October 8, 2013.
Regional Transit Framework Study Regional Council September 24, 2008.
Metropolitan Council Transit Capital Improvement Program October 10, 2007.
RTD FasTracks Projects for the DRCOG 2040 RTP (Baseline Report) FasTracks Monitoring Committee July 8, 2014.
2014 Annual Program Evaluation (APE) Status Update April 1, 2014.
TRANSIT SYSTEMS PLANNING Module 3, Lesson 4. Learning Objectives Define systems planning Understand the steps required for plan selection and the key.
Southeast Rail Extension FasTracks Monitoring Committee July 14, 2015.
Southeast Rail Extension Update RTD Board of Directors FasTracks Monitoring Committee March 3, 2015.
2015 Annual Program Evaluation (APE) Status Update July 14, 2015.
Update: Reports to DRCOG RTD Baseline Report to DRCOG on FasTracks RTD SB 208 Report to DRCOG Planning & Development Committee June 3, 2014.
2017 Annual Program Evaluation Update
Future Construction FasTracks Corridors Federal Funding Analysis
Southwest LRT Project Craig Lamothe, AICP Senior Project Manager
Transit Systems Planning
D Line Project Overview
I-85 Corridor Light Rail Transit Feasibility Study
Durham and Orange Transit Plan Funding Needs
2014 Annual Program Evaluation (APE) Status Update
Chicago Transit Authority
Presentation transcript:

Southwest LRT Project Craig Lamothe, AICP Senior Project Manager 2011 MN State Planning Conference September 29, 2011

1)Twin Cities Transit System Profile 2)Previous Regional New Starts Projects a)Hiawatha LRT b)Northstar Commuter Rail c)Central Corridor LRT 3)Federal New Starts Program Primer 4)Southwest LRT Project a)Alternative Analysis Phase Recap b)Preliminary Engineering Phase Preview 2 Today’s Topics

3 Twin Cities Ridership

4 Metro Transit Ridership (2010)

5 Peer Comparison: 2009 System Ridership

6 Peer Comparison: Ridership per Capita

Buses –Artic Buses: 163 –Standard 40’ Buses: 735 –Hybrid Buses: 97 Light Rail –27 cars Commuter Rail –18 Passenger Cars –6 Locomotives 7 Metro Transit Fleet

Transitway System

12 miles 19 Stations Project Cost: $715.3 million 2011 Annual Operating Budget: $26.7 million Avg. Weekday Ridership (Aug ‘11): 35, Total Annual Ridership: 10,500,000 9 Hiawatha LRT (Blue Line)

40 miles 6 stations Project Cost: $320 million 2011 Annual Operating Budget: $17.0 million Avg. Weekday Ridership (Aug. ‘11) 2, Total Annual Ridership: 710, Northstar Commuter Rail

11 miles 18 new stations $957 million 2015 Est. Operating budget: $25.4 million Projected weekday ridership: Over 40,000 by Central Corridor LRT (Green Line)

12 New Starts Overview Full Funding Grant Agreement Alternatives Analysis Final Design Commitment of Non-Federal Funding, Construction Plans, ROW Acquisition, Before-After Data Collection Plan, FTA Evaluation for FFGA, Begin Negotiations Proj Mgmt Over-sight Construction Preliminary Engineering Complete NEPA Process Refinement of Financial Plan Preliminary Engineering Complete NEPA Process Refinement of Financial Plan Select LPA, MPO Action PMP FTA Decision on entry into PE FTA Decision on entry into FD Systems Planning

Evaluate the mode and alignment options for a particular corridor Benefits, costs and impacts of transportation options Complete with the selection of the locally preferred alternative (LPA) and adoption of the LPA into the region’s long range transportation plan 13 Alternatives Analysis (AA) Phase

Consider design options to refine LPA and complete the NEPA process Hone the estimates of project cost, benefits, impacts and schedule Finalize management plans Demonstrate technical capabilities to develop the project Commit local funding sources 14 Preliminary Engineering (PE) Phase

Prepare final construction plans, contract packages, detailed specifications and bid documents 15 Final Design (FD) Phase

16 New Starts Evaluation Process

17 Peer “New Starts” Projects Orlando, FL Honolulu, HI New York, NY St. Paul- Minneapolis P N Pending FFGA New FFGA E Existing FFGA July 2011 Status San Francisco Houston, TX Denver, CO Salt Lake City, UT Dallas, TX Seattle, WA E E E N. Virginia-Dulles, VA E E N P Hartford, CT E E P Sacramento, CA P P San Jose, CA N N Portland, OR P P E E E

18 Peer “New Starts” PE Projects Vancouver, WA Portland, OR Sacramento, CA Los Angeles, CA Honolulu, HI Houston, TX Charlotte, NC Pawtucket, RI San Jose, CA Salt Lake City, UT Minneapolis,- St. Paul, MN September 2011 Status

Alternatives Analysis LPA Selected LPA Amended into TPP MC requests to Enter PE FTA approves Entry into PE 19 SWLRT: Historical Timeline Nov. 4, 2009 May 26, 2010 Aug. 31, 2010 Sept. 2, 2011

Transit Technology Review Identification of Alignments and Stations Initial Set of Alternatives –No Build –Enhanced Bus –Build Alternatives (BRT & LRT) 20 SWLRT: AA Phase

15 miles 17 new stations Est. Project Cost: $1.25 billion 21 SWLRT: Locally Preferred Alternative (LPA)

22 SWLRT: Project Budget $30.6M in Local Funds Committed to Date $625 million $375 million $125 million

23 SWLRT: Anticipated Schedule Preliminary Engineering Final Design Construction Revenue Operations

Procurement of Engineering Services Complete 30% Design Procurement of Environmental Services Complete Final Environmental Impact Statement Establishment of a Project Office Secure Municipal Consent from 5 Cities 24 SWLRT: PE Phase

Mark Fuhrmann, Program Director – New Starts Rail Projects Chris Weyer, Project Director - Southwest LRT For Further Information and Updates 25