Overview of ERCOT Outage Coordination Woody Rickerson Director Grid Coordination January 2015.

Slides:



Advertisements
Similar presentations
2 Draft of proposed metrics for the WEQ BPS to conduct analysis and evaluation of the Parallel Flow Visualization pilot project. (PFV Pilot)
Advertisements

Interchange Distribution Calculator Working Group (IDCWG) Update IDCWG October 12 th, 2011.
January 9, 2013 BAL-001-TRE-1 Primary Frequency Response Update for Texas RE RSC.
Outage Cost Study Market Analysis and Design Outage Coordination Improvement Task Force 3/23/2015.
Western Regulation Usage and Pilot Program Results 1.
Outage Coordination Process and New Equipment 1. Introduction This presentation is intended to increase knowledge of outage coordination and NOMCR submittal.
9/13/2007 Nodal COMS Extracts & Reports Market Requirements Review SDAWG Jackie Ashbaugh ERCOT ***NOTE: All information contained in this presentation.
Discussion: Use of RAPs in system operations Kris Dixit 1.
Outage Coordination Overview D.W. Rickerson ERCOT Outage Supervisor 12/1/2008.
ERCOT OCITF 3/23/ ISO Comparison – NEISO Alex Lee (ERCOT) Lee Blaede (NEISO) ERCOT OCITF 3/23/2015.
Small Signal Stability Analysis Study: study prepared by Powertech Labs Inc. for ERCOT Vance Beauregard AEP 9 April 2002.
Transmission Customer Meeting May 28, :00 – 10:00 Lake Natoma Inn 1.
ERCOT Reliability Operations Subcommittee Meeting June 10, 2010 Austin, Texas AEP-Texas: Load Projections/Forecasting and Steady State Base Cases.
ERCOT PUBLIC 4/21/ Loss of Load Probability Assessment for NERC April, 2015.
1 TSP Nodal Engagement Market Participant Call ERCOT August 04, 2010.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
Lead from the front Texas Nodal 1 Resource Entity Owned Transmission Asset Data Collection Feb 27, 2009 Kick Off Meeting.
PRR 568 – Settlement Timeline PRR 638 – Invoice Timeline PRR 599 – Mismatch Notification COPS January 2006 Updates.
NPRR 365 Change in Resource Outage Approvals from 8 to 45 or 90 Days Woody Rickerson Director Grid Coordination
CRR Auction Scope John Moseley. To outline aspects of the CRR market process to assure that these proposed CRR market protocols (as interpreted by ERCOT.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
Lead from the front Texas Nodal 1 Texas Nodal Energy Management System Requirement Documents December 5, 2006 Jay Dondeti EMS Project.
Constraint Management Plans (CMPs) An Ops Planning Perspective Nitika Mago Operations Planning, ERCOT.
EDS 2 Early Delivery Systems Review and Request for Approval May 2007 John Webb.
March 20, 2008 TPTF CIM Update Raj Chudgar Program Director for Market Redesign.
January 21, 2010 Security Constrained Economic Dispatch Resmi Surendran.
ISO Comparison – CAISO Alex Lee (ERCOT)
Lead from the front Texas Nodal 1 TPTF Update for TAC March 8, 2007 Trip Doggett.
MIG TF Voting Items Market Participant Notification Period (Transmission outage) – =1 Year Interconnection Date for Protocol Considerations – First Interconnection.
Transmission Outage Process April Purpose In compliance with the Protocols and the Electric Reliability Council of Texas (ERCOT) Operating Guides,
March 6, 2012 ERCOT Public ERCOT CRR Update Matt Mereness ERCOT Manager Day-Ahead Market and CRR Auction.
Generation Adequacy Task Force Update to WMS November 18, 2009.
AEP Corpus Christi TDC Advance Outage Scheduling Initiative.
CRR Model Building Process Bradley Bell CRR Engineer.
ERCOT, Market Analysis 2013 Annual Constraint Competitiveness Test (CCT) Study Results – Update for 8/27/12 CMWG 8/27/2012 ERCOT Public.
Network Model Management System (NMMS)
Project Funding Report November 1, Business Integration Update – Agenda –Project Portfolio Updatep Revision Request Funding Reconciliation.
CMWG Update to WMS Report of CMWG Meetings of &
1 Market Trials Outage Scheduling Weekly Update June 11, 2010.
Bob Wittmeyer MIG TF Charter Examine and investigate the reliability, and market, impacts as well as the interconnection processes/procedures.
Outage Planning Subcommittee Mark Wilson. Outage Planning Subcommittee Created to address Market Participant concerns with existing rules and procedures.
Economic Outage Evaluation Woody Rickerson ERCOT Outage Coordination Supervisor
ERCOT Guideline for Interim Updates to the Network Operations Model Excerpted from the “Modeling Expectations” whitepaper D.W. Rickerson.
February 3, 2011 TAC ERCOT Planning Go-Live Update Jay Teixeira Manager, Model Administration.
Scheduling and Operating Transmission Devices in the Nodal Environment.
Model load frequency Discussion John Adams January 5, 2010 Nodal Advisory Task Force.
1 TSP Nodal Engagement Market Participant Call ERCOT June 16, 2010.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Operational Planning Jason Smith. Operational Planning Goals –What Ops Planning is –What Ops Planning is not –What rules we operate under –Limitations.
ERCOT Monthly Operational Overview (January 2015) ERCOT Public February 15, 2015.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
August 24, 2007 ERCOT Regional Planning Group Meeting CREZ Transmission Optimization Study Warren Lasher System Assessment.
1 Market Trials Open Market Participant Call Weekly Kick Off Aug 09, 2010.
Transition Plan Network Operations Model Change Requests 5/26/2010.
Retail Workshop ERCOT Nodal Update October 06, 2010.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
Project Funding Review February 7, Background ERCOT has a $15M project budget in 2013 (same as 2012) –To allow for new additions to the.
Planning the Networked Grid Transmission Planning J.E.(Jeff) Billinton Manager, Regional Transmission - North Building the Networked Electricity Grid –
Congestion Management Work Group 2008 Overview CMWG Marguerite Wagner, Reliant Energy Inc.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved. EIPC Roll-Up Powerflow Model Zach Smith Director,
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
Texas Nodal Program ERCOT Readiness & Transition (ERT) Supplemental Information TPTF January 12, 2009 Kevin Frankeny.
RELIABILITY AND OPERATIONS SUBCOMMITTEE Report to TAC Austin, TX December 1, 2011 Kenneth A. Donohoo, P.E. Chairperson Oncor Electric Delivery Company.
ME 3.0 to ME 5.0 ME3.0 review scheduled during the Joint NDSWG/NATF meeting in July. There were approximately 180 comments on the ME3.0 paper. Deadline.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Market Trials Update NATF March 2,
ERCOT CRR Update to CMWG
Exit Capacity Release Methodology Statement
Presentation transcript:

Overview of ERCOT Outage Coordination Woody Rickerson Director Grid Coordination January 2015

ERCOT processes approximately 115,000 outages annually 15 dedicated Outage Coordination ftes Two peak outage seasons Two off seasons Peak for 2014 on Nov. 11 – 3481 outages on system March through May Oct. through Mid – Dec.

Some outages are analyzed multiple times Late arriving outages may only be studied once before being handed off to Real- Time

Outage Submission Timelines App Approval Target Day To Start Outage TD +45 TD + 30 A TD+9 TD+4 TD+3 TD+1 Approval TD + 90 TD day A 4-day 9-day 45-day 3-d Resource Outages automatically accepted Resource Outages Require Approval Transmission Outages Resource Outages 4

Real Time 12 months in advance, rolling annual outage plan to be submitted days in advance NOMCRs due for Operations Model (NOMCRs) 90-day timeline 45-day timeline (Resource) time 4-day 3-day 9-day timeline CRR Snapshot Interim Update NOMCRs Transmission Outages Operational Model Changes CRR Models Outage Coordination Timelines Tri-annual Planning Model Updates 9 Resource Outages

No Reliability Problems Reliability Problems CIM-derived EMS case containing Date specific Topology Load Forecast Starting Gen. Pattern Contingency file Wind Scenarios Previously Approved or Accepted Resource and Transmission Outages Outages Awaiting ERCOT Approval Reject Approve Order of Receipt Coordinate Outages Modify Gen Pattern Outage Coordination Study Process 10

When Reliability meets Economics Approximately 75 “High Cost” Outages were identified during the Outage Approval Process in 2014 Questionnaire: A statement of why the work is required. Is there a switching solution to reduce market impact? A statement of what has been done to reduce the length of Outage. Are you working extended hours? If not, can you submit it daily? Is this outage scheduled during a reduced load season? If not, please explain the reason. Can the outage be scheduled during a resource outage that would reduce market impact.

High Cost Outages High Cost Outages are subjectively determined by the amount of generation that has changed from an optimal dispatch to resolve reliability violations. Including 10 in the Rio Grande Valley area (Ajo to Rio Hondo, Lon Hill to North Edinburg, etc.) and 14 in the Houston Import area (Singleton to Tomball, etc.)

High Cost Outages