STATUS OF CARLSBORG SEWER PROJECT Carlsborg Community Advisory Council Bob Martin June 6, 2013.

Slides:



Advertisements
Similar presentations
Orange County Board of County Commissioners Water Conserv II Operations Contract Renewal Utilities Department August 23, 2011 Utilities Department August.
Advertisements

Smart Growth Update VCARD May 23, Growth Management & Schools during 2005 Volusia County Council adopts new school impact fee. School Board of Volusia.
Wakulla County Sewer Project Eutaw Utilities Presentation April 7, 2011.
Wastewater Treatment Project Update May 15, 2013.
Calaveras County Water District Capital R&R Program Funding Options March 25,
Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
INFORMATION on RATE increase On May 6, 2008, the Clark County Water Reclamation District Board of Trustees approved a rate increase at a public hearing.
PROPOSITION 218 IMPACTS ON UTILITY USER FEES Case Study City of Dixon Sewer Rate Repeal of 2007.
1 Collection System And Wastewater Treatment Plant Sewer Update
City of Farmersville, Texas Water and Wastewater Rate Study February 2011.
1. The installations of grinder pumps and lines from residences on private property to M.D. collection lines is the final link in finishing a project.
May 30, Meeting & Outreach efforts  February 27th – Proposed Compensation Plan Distributed to Joint Admin/WWOC  March 5th – Joint Admin/WWOC Meeting.
Board of County Commissioners June 10, CPA-AA Duke Energy Florida for HCR Limestone Department of Planning and Development Geographic Resources.
City Council Meeting Lisa A. Kuss City Administrator May 8, 2012.
Presentation to CITY OF PALM COAST, FLORIDA WATER AND WASTEWATER RATE STUDY AND BOND FEASBILITY REPORT Prepared in Conjunction with the Issuance of Utility.
 Why  Project Status  Future Course Lime Sludge Biosolids Water/Wastewater System Life Cycle Raw Water Wells (12) Water Treatment Plant Storage Tanks.
Utilities Planning Group UPCOMING REQUESTS FOR PROPOSALS Larry Tunnell, PE, PG Chief Engineer.
1 Manassas Park Town Meeting 29 October Welcome This is the first Manassas Park Town Meeting Governing Body implemented this as a way to improve.
1 Detroit River International Crossing (DRIC) New International Trade Crossing (NITC) Transportation Border Working Group April 24, 2013.
CSO Strategies & Financial Management Mayor Gregory A. Ballard City of Indianapolis December 9, 2010.
Utility Extension Project
Convention Center Community Coalition 1. Time Line 2008: Feasibility Study by CS&L May 2009: Follow-Up Data April 2010: Appleton Council/Mayor Appoint.
Delta Conveyance: Update on the Planning Process and Analysis of Water Supply and Costs CCWA Board of Directors February 25, 2010.
Metropolitan Council Environmental Services A Clean Water Agency Presented to the Environment Committee March 22, 2011 Info Item: East Bethel Update Bryce.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
B-WSFWP-1 Water Supply Facilities Work Plan (WSFWP) Adoption Hearing May 19, B-WSFWP-1 Water Supply Facilities Work Plan (WSFWP) Adoption.
Sunshine Coast Regional District Development Cost Charges July 3, 2014 Infrastructure Services Committee Bob Twerdoff.
Surveying principles 1 Public Water Suppliers S. Ross Hansen P.E., L.S. Region Engineer 4/10/2014 Rural Water Certification Class.
Interstate 95 Corridor Improvement Program June 20, 2012.
Withlacoochee Regional Water Supply Authority Water Supply Plan Update - Progress Report #3 May 15 – June 18.
Marion County Utilities
TENTATIVE BUDGET PRESENTATION CITY COUNCIL PUBLIC HEARING SEPTEMBER 8, 2010.
Council Workshop, June 24, Image Date: 1/15/2014 Future WWTF No. 2 Capacity 2.0 MGD., Expandable to 6.0 MGD. Future WWTF No. 2 Capacity 2.0 MGD.,
City of Palm Coast, Florida City Council Meeting October 2, 2012.
Wastewater Treatment Plant # 2 Engineering Services Council Workshop July 8, 2014.
June 10, 2008 Board of County Commissioners B-WSFWP-1 Water Supply Facilities Work Plan (WSFWP) Transmittal Hearing.
Road Map to the Future: The Consolidation of Sewer Infrastructure in Rutherford County, NC November 16 th, 2015.
Metropolitan Council Environmental Services A Clean Water Agency Proposed Combined Sewer Overflow Changes Environment Committee March 11, 2008 Keith Buttleman.
Missoula County Commissioners and City Council formed the Missoula Valley Water Quality District (MVWQD) Missoula County Commissioners.
Water System Master Plan & Rate Study City of DeKalb, Illinois City Council Presentation May 16, 2015.
Kevin Colvett, P.E. Nashville Corrective Action Plan and Engineering Report, Phase III for Metro Water Services and the City of Brentwood, TN Presentation.
May 18, 2004 City Bond Election. MAY 2004 BOND ELECTION General Election May 18, 2004 Elections City Mayoral Election City Council Election City Bond.
Yarmouth’s Wastewater System Initiative Phase 1 Article 12 ATM 2008 $3.1 Million Design and permitting for Collection, Treatment and Disposal.
FBC Spring Conference April 21, Flip Mellinger Using the data to improve efficiency © The Florida Benchmarking Consortium.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Recycled Water Pipeline Joe Mouawad Sr. Director of Engineering September 2, 2015.
SMALL BUSINESS OPPORTUNITY FORUM Water Department 2015 Capital Program & 2016 Outlook.
1% Sales Tax Commission Board Meeting June 3, 2015.
City of Fernley, Nevada – 164 th Ave. NE, Suite 300, Redmond, WA April 18, 2007 Rate Study Findings Water and Sewer Utility Rates.
Remedial Measures Plans Response to EQC Questions June 21, 2011 Presentation to Lexington-Fayette Urban County Government Environmental Quality Committee.
1 City of Cocoa Michael Burton - President Andrew Burnham - Sr. Vice President Eric Grau - Project Consultant Presented by: Water, Sewer & Reclaimed Water.
Operating Efficiencies Costs to operate and maintain the water and sewer system have not varied significantly during the first 5 years of operation.
Presentation to CITY OF PALM COAST, FLORIDA FINANCIAL FORECAST AND CAPITAL FACILITIES FEES ANALYSIS Prepared in Conjunction With the Utility System Revenue.
Miami-Dade Water & Sewer Department Miami-Dade Water and Sewer Department |  1   Reuse, Every Drop Has Value Seminar FPL JPA.
Ordinance Amending Chapter 37 of the Orange County Code Orange County Board of County Commissioners Public Hearing April 3, 2012.
CP-TXT Amendment to the Capital Improvements Element (Annual Update) September 25, 2007.
1 Standards and Construction Specifications Manual Orange County Utilities February 13, 2007.
Strength through History & Innovation City of Beaumont Salt Mitigation Feasibility Study Summary of Findings.
CSA 7 – Boulder Creek. YOUR SANITATION FACILITY Facility Includes the Following Five Pump Stations –Total of 10 pumps 16,553 feet of collection lines.
Electrical Distribution Design Services
Solar Energy Aides City Efficiencies and Cost Savings
Kings Bluff Raw Water System Parallel Raw Water Main Project
Final Rate Study Findings
Sewer User Rate Increase PUBLIC HEARING
Utilities Department Wedgefield Water November 28, 2017.
Water Department has Six Divisions
Capital Facilities Plan
Non-Residential Customer Non- Residential - Capacity Evaluation Borough of Conshohocken Authority Customer Informational Meeting June 20, East.
CP-TXT Amendment to the Capital Improvements Element & Public School Facilities Element (Annual Update) October 2008.
CP-TXT Water Supply Facilities Work Plan Amendment
Brieana Reed-Harmel, Broadband Project Manager
Presentation transcript:

STATUS OF CARLSBORG SEWER PROJECT Carlsborg Community Advisory Council Bob Martin June 6, 2013

UPDATE SINCE LAST CCAC MEETING Conditional Approval of Facility Plan by Ecology The PUD Board has decided to withdraw from most aspects of the project. The PWTF loan has been executed and assigned to the County. Wastewater treatment and reuse in Sequim

Reasons to Consider Treatment in Sequim: Sufficient excess capacity exists at Sequim WRF. Only minor upgrades to Sequim collection system needed to accommodate Carlsborg flow. Less than 3 miles of 6” force main needed to connect. “State of the Art” facility producing Class A reclaimed water. Good record of consistently meeting permit standards. Sequim aggressively pursuing utilization of reclaimed water. Resolves siting issues in Carlsborg. Cost Savings Sufficient excess capacity exists at Sequim WRF. Only minor upgrades to Sequim collection system needed to accommodate Carlsborg flow. Less than 3 miles of 6” force main needed to connect. “State of the Art” facility producing Class A reclaimed water. Good record of consistently meeting permit standards. Sequim aggressively pursuing utilization of reclaimed water. Resolves siting issues in Carlsborg. Cost Savings

Preliminary Sequim Cost Proposal 1.Capacity Cost: Proportionate Share of depreciated cost of shared treatment facilities (Approx. $ million for 20-year Carlsborg flow projection. 2.Treatment O&M: $0.01 per gallon 3.Collection system O$M: $2.12 per foot on approx. 15,000 feet of shared sewer lines % surcharge on Treatment & Collection O&M

Present Worth – 20 Years (X $1,000) Cost ComponentFacility Plan (Carlsborg Rx) Sequim Treatment & Reuse Capital Cost – Rx and Reuse$ 5,860$ 3,460 Carlsborg Collection$ 9,719 Expansion Cost$ 0$ 532 Subtotal: Capital Cost$ 15,579$13,711 O&M Present Worth – 20 yr$ 5,750$ 4,577 Total Present Worth$21,329$18,288 Notes: 1) Assumes constant 2012 dollars and 0% discount. 2) Assumes Purchase of 20-Year Capacity in two increments.

Source: Comparison of Costs for Wastewater Management Systems Applicable to Cape Cod, Barnstable County Wastewater Cost Control Task Force, April Carlsborg – Initial Sequim WRF

UPDATE SINCE LAST CCAC MEETING Conditional Approval of Facility Plan by Ecology The PUD Board has decided to withdraw from most aspects of the project. The PWTF loan has been executed and assigned to the County. Wastewater treatment and reuse in Sequim Evaluation of conveyance route to Sequim

Sequim Conveyance Options 1.Crossing at RR Bridge 2.Old Olympic Highway 3.Directional Drilling 4.Crossing at SR 101 Bridge 5.Utility Bridge

Conveyance Options

UPDATE SINCE LAST CCAC MEETING Conditional Approval of Facility Plan by Ecology The PUD Board has decided to withdraw from most aspects of the project. The PWTF loan has been executed and assigned to the County. Wastewater treatment and reuse in Sequim Evaluation of conveyance route to Sequim Request for Proposals for Engineering Consultant

RFP WORK TASKS 1.Design the initial Carlsborg Collection System

RFP WORK TASKS 1.Design the initial Carlsborg Collection System 2.Amend the Facility Plan to reflect treatment and reuse in Sequim 3.Evaluate options and costs for expansion of the PUD Carlsborg Water system to the entire UGA

NEXT STEPS: Connection Policies and Costs – Priority Inter-local Agreement between County and City of Sequim Design Conveyance system to Sequim Construction – completion by end of 2015

Project Timeline