Prof. Roy Levow Session 4.  The Work Breakdown Structure  Uses for the WBS  Generating the WBS  Six Criteria to Test for Completeness in the WBS 

Slides:



Advertisements
Similar presentations
CP Chapter 4 Schedule Planning.
Advertisements

Chapter 17 Project Management McGraw-Hill/Irwin
Project Management CHAPTER SIXTEEN McGraw-Hill/Irwin Copyright © 2011 by the McGraw-Hill Companies, Inc. All rights reserved.
F O U R T H E D I T I O N Project Management © The McGraw-Hill Companies, Inc., 2003 supplement 3 DAVIS AQUILANO CHASE PowerPoint Presentation by Charlie.
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
Developing a Project Plan
Advanced Project Management - CPH
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
Defining activities – Activity list containing activity name, identifier, attributes, and brief description Sequencing activities – determining the dependencies.
Creating the Project Plan
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
Project Time Management
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Project Time Management
Importance of Project Schedules
Jeopardy Game! Scope Management Time Management Integration Management.
Effective Project Management
Class 28: Chapter 16: Project Management Class 28 Agenda –Collect Player Diary 2 and Conduct Player Audit No ed diaries – 5 PM Deadline –Discuss Grade.
Project Time Management
Project Management Chapter 3 BUSI 2106 – Operations Management.
Effective Project Management: Traditional, Agile, Extreme
HIT241 - TIME MANAGEMENT Introduction
Yarmouk University Hijjawi Faculty For Engineering Tech 1A. Al-Tamimi ©Lecture 04.
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Week 6 Project Time Processes – Part 2 C ertificate IV in Project Management.
Scheduling Sequence & Time.
Chapter 6: Project Time Management
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Lecture 5 Title: Project Time Management By: Mr Hashem Alaidaros MIS 434.
Appendix A Project Management: Process, Techniques, and Tools.
POST GRADUATE PROGRAM OF INFORMATION TECHNOLOGY
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
Welcome to Session 4 – Project Management Process Overview (continued) Instructor:Phyllis Sweeney Instructor: Phyllis Sweeney Project Management Certificate.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
1 Project Management Chapter Lecture outline Project planning Project scheduling Project control CPM/PERT Project crashing and time-cost trade-off.
Lecture 7. Review of Lecture 6 Project Scheduling: The process of defining project activities, determining their sequence, estimating their duration Scheduling.
1 L U N D S U N I V E R S I T E T P rojektledning och Projektmetodik.
Managing Project Resources. Project Resources Human Resources Project stakeholders: – Customers – Project team members – Support staff Systems analyst.
Lecture 6. Review of Lecture 5 Company strategic planning: mission and objective statements and competitive strategy. Planning Methods: Top-down, Bottom-up.
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
Geog 469 GIS Workshop Project Management.
Advanced Project Management Project Time Management Ghazala Amin.
Collecting requirements – Different methods Defining scope – Estimates for all resources Creating the WBS – Different approaches Verifying scope – Formal.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Information Systems System Analysis 421 Chapter 3 Managing the Information Systems Project.
Chapter 3 Managing the Information Systems Project
Project Time Management Ashima Wadhwa. Schedule Development – Determining start and finish dates for project activities – Without realistic dates, project.
Project Time Management
Creating the Work Breakdown Structure. INFO 638Lecture #22 WBS The goal of the project should be accomplished when all tasks in the WBS are completed.
SOFTWARE PROJECT MANAGEMENT
Chapter 4 Note: See the text itself for full citations.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
Chapter 4 MIS Project Management Lecturer Sihem Smida Sihem Smida Developing a project plan.
Introduction to Project Management Chapter 7 Managing Project Resources Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Chapter 17 Project Management McGraw-Hill/Irwin
Project Planning & Scheduling
Project Planning & Scheduling
Chapter 6: Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Project Time Management
Project Time Management
P ROJECT M ANAGEMENT Skills.
Project Time Management
Project Time Management
Importance of Project Schedules
Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
Presentation transcript:

Prof. Roy Levow Session 4

 The Work Breakdown Structure  Uses for the WBS  Generating the WBS  Six Criteria to Test for Completeness in the WBS  Approaches to Building the WBS  Representing the WBS

 “A hierarchical description of the work that must be done to complete the project as defined in the Project Overview Statement.”  Inputs  POS  Requirements Document  Terms  Activity: Chunk of work  Tasks: Smaller chunk of work. Activities are made up of tasks  Work Package: Complete description of how the tasks that make up the activity will actually be done

The process of breaking down work into a hierarchy of activities, tasks, and work packages Uses Estimate Duration Determine Resources Schedule Work

 Thought Process Tool  Architectural Design Tool  Planning Tool  Project Status Reporting Tool

 Top-Down Approach: Start with goal and continue to partition work until it has been sufficiently defined  Team Approach Variation  Subteam Approach Variation  Bottom-Up Approach: First-level tasks are identified. Then groups are formed around first-level tasks where these groups brainstorm the activities needed to complete the first-level task.

 Small Projects – Consider mindmapping  Diagram relating components radiating out from central element (Ref: Wikipedia article)Wikipedia article  Large Projects – Intermediate WBS  Adaptive and Extreme Projects – Iterative WBS

 Status/Completion is measurable  The activity is bounded  The activity has a deliverable  Time and cost are easily estimated  Activity duration is within acceptable limits  Work assignments are independent Seventh Criteria – Project manager’s judgment that the WBS is not complete

 Stopping Before Completion Criteria Are Met  Decomposing Beyond Completion of the Criteria

 Noun-type: In terms of the components of the deliverable  Physical Decomposition  Functional Decomposition  Verb-type: In terms of the actions that must be done to produce the deliverable  Design-build-test-implement  Objectives  Organizational: In terms of the units that will create the deliverable  Geographic  Departmental  Business Process

Outline  Estimating Duration  Estimating Resource Requirements  Estimating Duration as a Function of Resource Availability  Estimating Cost  Using a JPP Session to Estimate Duration, Resource Requirements, and Cost

 The difference between Duration and Work Effort

 Crashing the task – adding more resources to preserve duration  Diminishing returns  Crashpoint: adding more resources INCREASES task duration  Considerations  Not always feasible (Can nine women have a baby in one month?)  Communication overhead increases  Risk increases

 Varying skill levels  Unexpected events  Efficiency of work time  Mistakes and misunderstandings  Common cause variation

 Similarity to other activities  Historical Data  Expert Advice  Delphi Technique  Group of experts individually estimate duration  Then, average of the estimates is calculated  Do it two more times  Three-Point Technique  most optimistic estimate, most pessimistic estimate, and most likely estimate, which are then averaged  Wide-band Delphi Technique  Combination of Delphi and Three-Point techniques

“Early estimates will not be as good as later estimates.”

 Types of resources  People  Facilities  Equipment  Money  Materials

 Skills Matrices  Skills needed inventory  Skills currently on hand inventory  Skill Categories: uniform listing of skills  Skill Levels: level of expertise in a particular skill

Used to estimate resource and costs by showing the positions needed for a particular project

 Three variables influence Duration Estimate  Duration  Total amount of work (hours/days)  Percent per day that person can devote to task  Methods for Estimating Duration  Assign as a Total Work and a Constant Percent/Day  40 hours / 0.50 = 80 hours  Assign as a Duration and Total Work Effort  5 person days / 10 days = 0.5  Assign as a Duration and Percent/Day  10 days X 0.50 = 5 person days  Assign as a Profile (when using multiple resources)

 Resource Planning  Trading money for time (depends on skill level)  Part-time workers (think of ramp-up time)  Don’t overschedule resources  Cost Estimating  Order of magnitude estimate  Estimate is 25% above and 75% below final number  Budget estimate  Estimate is 10% above and 25% below final number  Definitive estimate  Estimate is 5% above and 10% below final number

 Cost Budgeting – Assign costs to tasks on the WBS  Cost Control – Two major issues  How often report of costs is needed  Depends on risk and need to spot developing problems  Use of a cost baseline to spot cost variances when you receive actual figures

Advice from the author:  Get it roughly right  Spend more effort on front-end activities than on back-end activities  Consensus is all that is needed

Outline  The Project Network Diagram  Building the Network Diagram Using the Precedence Diagramming Method  Analyzing the Initial Project Network Diagram  Using the JPP Session to Construct and Analyze the Network

 Definition: “A pictorial representation of the sequence in which the project work can be done.”  What is needed to construct diagram  Tasks  Task Duration  Earliest time to start task  Earliest expected completion date for the project

 Older than the project network diagram  Rectangular bars that show the duration by length  Placed along a timeline in sequence  Does not indicate what task needs to be done before and after a task  Does not indicate if the project planning is most effective or efficient

 Planning – Visual overview of the project that is easy to use for scheduling  Implementation – Software exists that automatically updates task dates and duration  Control – Project manager can better schedule tasks and spot variances

Early Method – Task-On-the-Arrow (TOA)

Precedence Diagramming Method (PDM)

 First, every task in the WBS has a task node

 Second, determine the sequence of tasks  Every task has at least one predecessor and at least one successor  EXCEPT  Start Task has no predecessor  End Task has no successor  Diagram the connections

Diagramming connections between tasks

Four Kinds of Task Dependencies

 Technical Constraints  Discretionary  Best-Practices  Logical  Unique  Management Constraints  Interproject Constraints  Date Constraints

 Pauses or delays between tasks  Can be intentional  Also created by constraints

 Compute two schedules  Early schedule – use Forward Pass  Late schedule – use Backward Pass Forward PassBackward Pass What’s different?

 “The longest duration path in the network diagram”  “The sequence of tasks whose early schedule and late schedule are the same”  “The sequence of tasks with zero slack or float” The Critical Path Determines the Completion Date of the Project

 First method – add up all of the path’s durations. The longest one is the critical path.

 Second method – Compute the slack time  The amount of delay (in time units) in starting a task that will not affect the project completion date  Difference between late finish and early finish of a slack time  Do not include holidays, weekends, and similar such time  Two types of slack  Free slack – amount of delay for a task without causing a delay in the early start of immediate successor task(s)  Total slack – amount of delay for a task without delaying the project completion date

 Crashing the schedule: necessary when the initial project network diagram shows a projected completion date that is later than the requested completion date.  Strategies  Examine the Critical Path to see if you can move tasks off the Critical Path  Partition tasks into parallel subtasks  Concerns  Increase in risk  More communication and coordination needed

 Padding task duration  Individual task level  Project level  Bad at the task level  BUT, good at the project level  Accounts for risk  Incentive (management reserve time not used can be the basis for bonus)