Mars Climate Orbiter Team Magna Corp: Tim Toba Mohamed Sahil Nyema Johnson Abner Yemaneab University of Minnesota.

Slides:



Advertisements
Similar presentations
Brian Killough NASA NASA Future Missions Summary CGMS-38 Meeting Delhi, India November 8-12, 2010.
Advertisements

Preliminary management plan for PACE SDT What are the Goals of PACE? The goals of the PACE mission are: 1-Extend key climate data records on ocean color.
GODDARD CONTRACTOR ASSOCIATION (GCA) MEETING PROCUREMENT UPDATE 1/30/14.
Polar Highly Elliptical / Molniya Orbit Science (PHEMOS) Mission Phase 0/A Studies Mid-Term Review Meetings January 12-14th, 2011.
Webpages.charter.net/rtoba/magnacorp “A proud past and a promising future”
Mars Exploration By Jacob Stinar. Water on Mars.
Metric Prefixes.
Modern Exploration Mars Pathfinder  “NASA’s Mars Pathfinder mission – the first spacecraft to land on Mars in more than 20 years and the first ever to.
SPACECRAFT ACCIDENTS: EXAMINING THE PAST, IMPROVING THE FUTURE Overview and Challenger Case Study Bryan Palaszewski working with the Digital Learning Network.
What are some spinoffs that we benefit from on Earth? How has Alabama contributed to the space industry? What was the first manned mission on the moon?
System Software Integration Testing Mars Polar Lander Steven Ford SYSM /05/12.
High Altitude Scientific Ballooning (Near Space Engineering)
Engineering Means having to deal with failure Missions to Mars as an example of try, try, try again…
Summary Description of Previous Studies Study NameDateSummary Description Exploration Office Case Studies NASA's Office of Exploration did four.
2001: "Crawl, Walk, Run and Fly!" start simple, build on learning, and ultimately make aerospace history by sending student built hardware, representing.
Bits and Pieces. Spacecraft Systems Propulsion –Already discussed Communications Science instruments Power.
The Solar System Chapter 6 COPY DOWN THE LEARNING GOALS ON PG SKIP 5 LINES BETWEEN EACH!
University of Toronto Department of Computer Science CSC444 Lec02 1 Lecture 2: Examples of Poor Engineering “Software Forensics” Case Studies Mars Pathfinder.
Chapter IV Science and Technology. I. Federal Government’s Policy and Support 1.Federal investment in science and technology has played a critical role.
All rights reserved © Altec ExoMars 2018 Rover Operations Control Centre Planned Organization of ROCC Operations I. Musso.
NMP EO-1 TECHNOLOGY WORKSHOP Section 2 Meeting Objectives.
IMARS History and Phase II Overview Presented to MEPAG 13 May 2014 L. May, NASA HQ NOTE ADDED BY JPL WEBMASTER: This content has not been approved or adopted.
System Integration Testing Requirements Mars Polar Lander Steven Ford SYSM /11/12.
Commercial Space Vehicles Lessons Learned Needs Workshop Bette Siegel, Ph.D. ESMD Bette Siegel, Ph.D. ESMD September 18, 2006.
NASA’s Mars Climate Orbiter Mishap. References Official investigation report IEEE Spectrum investigation report Official report on project management.
Key Ideas Describe characteristics of the universe in terms of time, distance, and organization. Identify the visible and nonvisible parts of the electromagnetic.
LIFE: Traceability Matrix Team Members JPL: P. Tsou, I. Kanik NASA Ames: C. McKay UoW: D. Brownlee Mission Cost Since formal costing is yet to be performed,
MAVEN MARS ATMOSPHERE AND VOLATILE EVOLUTION.
System Engineering Experiences Harold Sasnowitz, IEEE Life Senior Member.
1 Chapter 1 The Product. 2 What is Software?  Pressman Instruction (computer programs) Data Structures Documents  Sommerville Software is computer programs.
What happened to the Mars Climate Explorer in September 1999? By Leslie Palomino.
MATT Report Feb. 20, Philip Christensen (Chair) Lars Borg (ND-SAG Co-Chair) Wendy Calvin (MSO SAG Chair) Mike Carr Dave Des Marais (ND-SAG Co-Chair)
PREDECISIONAL FOR PLANNING AND DISCUSSION PURPOSES ONLY 1 Humans to the Martian System Preliminary Summary of Strategic Knowledge Gaps P-SAG (jointly sponsored.
ST5 PDR June 19-20, 2001 NMP 2-1 EW M ILLENNIUM P ROGRA NNMM Program Overview Dr. Christopher Stevens Jet Propulsion Laboratory, California Institute of.
Science Team Objectives K. Jezek and J. Richter-Menge Science Team Co-leads.
Interlude  Viking mission operations ended in the early 1980s  Viking missions gave scientists the most complete picture of Mars to date. What does this.
Idaho Near Space Engineering – Idaho RISE – Brandy Holmes Project Manager David Atkinson Electrical &Computer Engineering Idaho RISE Faculty Coordinator.
DAILY fizziks CHALLENGE 2.The United States officially uses the English System, not the Metric System, primarily for measurement. Besides the U.S., the.
1 Climate Absolute Radiance and Refractivity Observatory (CLARREO) Welcome David Young Project Scientist CLARREO Mission Formulation Team NASA Langley.
1 Science Definition Team Meeting National Aerospace Institute Hampton, VA Dec 1-3, 2015.
Spacecraft Dimensions 1.06 meters (3.5 feet) tall by 3.6 meters (12 feet) wide. Spacecraft Weight Total: 576 kg (1,270 pounds) Lander: 290 kg (639 pounds)
WHAT ARE SATELLITES AND SPACE PROBES? Objective: Explain how artificial satellites and space probes are used to explore space. Key Terms: Satellite orbit.
By Maia :). Mission Profile page 1  Mars 3 was launched towards Mars from a Tyazheliy Sputnik Earth orbiting platform. A mid-course correction.
JWST Mission CDR Northrop Grumman Space Systems Redondo Beach (CA) April 10-16, 2010.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
National Aeronautics and Space Administration February 27, 2013 Defining Potential HEOMD Instruments for Mars 2020 A Work in Progress... NOTE ADDED BY.
Missions to Mars Julie A. Rathbun Lowell Observatory.
Two IT Projects that were successful & Two failure projects.
Mars Climate Orbiter. FOR IMMEDIATE RELEASE September 23, 1999 NASA'S MARS CLIMATE ORBITER BELIEVED TO BE LOST NASA's Mars Climate Orbiter is believed.
1 J. Ranson NASA’s Earth Observing System Terra Mission Update Jon Ranson, Terra Project Scientist Si-Chee Tsay, Terra Deputy Project Scientist NASA’s.
Apollo was a three-part spacecraft: 1. Command Module (CM)- held the crew's quarters and flight control section 2. Service module (SM)- for the propulsion.
PROPOSED STRATEGIC PLANNING PROCESS DECEMBER 3, 2014 Port of Port Angeles.
Standards Certification Education & Training Publishing Conferences & Exhibits Communication necessary to achieve LowE valve sealing compliance Presented.
1 Advanced Computer Programming Project Management: Basics Copyright © Texas Education Agency, 2013.
Conversions using Unit Rates Joanne Smithies Our Lady & St. Gerards RCP.
The Future of Human Spaceflight *** A Journey to Mars
Failure of Process / Failure of Mission
Perijove 2: engine issues
Please copy your homework into your assignment book
Status of the Planning Working Group’s (PWG) Efforts
Failure of Process / Failure of Mission
Data Integrity Leadership Institute
Curious about Curiosity?
Unit Conversions.
Scale of things : Big and Small
Space Communications Architecture Application Portfolio
Up and At ‘Em The Importance of Clear Communications
EagleSat 2 – Mission and Development Overview
Apollo and Beyond cont..
Visions and Voyages: The Planetary Decadal Survey
Presentation transcript:

Mars Climate Orbiter Team Magna Corp: Tim Toba Mohamed Sahil Nyema Johnson Abner Yemaneab University of Minnesota

Agenda Team Magna Corp. Introduction – Mohamed Sahil Scope – Mohamed Sahil Time Management – Abner Yemaneab Cost Management – Nyema Johnson Project Management – Tim Toba Questions?

Introduction NASA started Mars Surveyor Program in Mars Climate Orbiter was launched on Dec. 11, Mars Polar Lander was launched on Jan. 3, 1999.

Scope Management of the Mars Climate Orbiter

Scope Develop and launch two spacecrafts to Mars during the 1998 Mars transfer opportunity. Development cost was estimated at $183.9 Million. Collect and return to Earth, science data resulting from the water and remote investigations of the Martian environment by the Lander.

Scope Orbiter should act as a relay station for five years. Assist in data transmission to and from the Mars Polar Lander. Provide detailed information about the atmospheric temperature, dust, water vapor, and clouds on Mars. Provide valuable information about the amount of carbon dioxide (CO2) in Mars.

Scope

A second spacecraft Mars Polar Lander will be launched. Perform daily recording of the sound and images of Mars for one Martian year (687 days). The Purpose of the mission is to gather atmospheric data of each of the seasons on Mars. The mission's projected end date is December 1, 2004.

Scope

Time Management of the Mars Climate Orbiter

Feb 7, 1994: Program Started. May 1, 1995: Project Manager Named.  JPL names John B. McNamee manager of the newly-formed Mars Surveyor '98 Project. May 8, 1995: Instrument Proposals Solicited. Oct 20, 1995: Instruments Selected. Dec 1, 1995: Project Scientist Named.  Richard Zurek Jan 4, 1997: Orbiter Design Reviewed. Aug 1, Sep 30, 1998: Orbiter Assembled and Tested. Feb 1, 1998: Lander and Orbiter Renamed. Dec 11, 1998: Orbiter Launched. Pre-Launch Launch & Cruise 02/07/94 12/11/98 09/23/99 12/01/2004 Orbiting

Dec 11, 1998: Lander Leaves Earth. Dec 11, Sept 11, 1999: Mars Orbiter Interplanetary Cruise. Feb 3, 1999: New Management.  Richard A. Cook is the MSOP project manager. September 1999, the spacecraft was to fire its main engine to achieve an elliptical orbit around Mars. Sept. 23, 1999: The Mars Climate Orbiter mission was lost when it entered the Martian atmosphere on a lower than expected trajectory. Pre-Launch Launch & Cruise 02/07/94 12/11/98 09/23/99 12/01/2004 Orbiting

Faster, Better, Cheaper Costs were reduced and program scope — including both content and the infusion of new technology — increased at the same time. The the focus on cost and schedule reduction increased risk beyond acceptable levels on some NASA projects.

Mission Success First Schedule Recommendations: Number One Priority Should be Mission Success over Cost and Schedule. “bottoms up” budget and schedule should be developed. The team should take ownership of the schedule There should be adequate schedule slack available to solve problems. Check if mission success has been compromised as a result of schedule?

Cost Management of the Mars Climate Orbiter

Cost A total of $327.6 million was allocated for the Mars ’98 Project (which included the Mars Climate Orbiter and the Mars Polar Lander)  $193.1 million for spacecraft development,  $91.7 million for launch, and  $42.8 million for mission operations $80M of the $193.1M went toward the building of the MCO spacecraft $5M of the $42.8M used to operations the MCO

Cost $35.5M went toward the launching of the MCO Mission cost of the MCO totaled $120.5M (36.8% of the total budget allotted to both missions) The Independent Assessment Team charge with investigating the failure of the spacecrafts concluded that the ’98 Mars Project was at least 30% under-funded.

Project Management of the Mars Climate Orbiter

Project Management JPL/Mr. John McNamee Project Manager for MCO and MPL HQ/SD/Mr. Steven Brody MCO Program Executive NASA Headquarters MSFC/DA01/Mr. Drew Smith Special Assistant to Center Director George C. Marshall Space Flight Center HQ/SR/Dr. Charles Holmes Program Executive for Science Operations NASA Headquarters HQ/QE/Mr. Michael Card Program Manager NASA Headquarters

Project Management Existing Processes and Requirements NASA has significant infrastructure of processes and requirements in place to enable robust program and project management, beginning with the capstone document: NASA Procedures and Guidelines Many of these clearly have a direct bearing on mission success.

Project Management So What Went Wrong? Heart of Mission’s Navigation Mishap Due to a conversion error in which commands to the spacecraft were sent in English units rather than metric units Unofficially, the problem had been detected but due to politics between the development team and JPL, a fix was never deployed

Project Management The official report cited the following “contributing factors” to the loss of the spacecraft  undetected errors in ground-based models of the spacecraft the  operational navigational team was not fully informed on the details of the way that Mars Climate Orbiter was pointed in space  a final, optional engine firing to raise the spacecraft’s path relative to Mars before its arrival was considered but not performed

Project Management Summary  One Technical Problem failed conversion of unit  Many Process and Social Problems No review (e.g. verification), insufficient training, informal processes in place, formal processes ignored  Led to a destroyed spacecraft