Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Hydrogen Delivery System – R&D Activities T W Bradshaw M Courthold M Hills J Rochford Daresbury Controls Group etc…
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Project Managers Report Video Conference 172 Roy Preece 11 th December 2014.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
MICE Collaboration meeting (CM20) At RAL 10 – 13 Feb 2008 AFC Magnet – Status and Progress W. Lau, Oxford University.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
Decay Solenoid – what do we have to do to make it work?
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
Hydrogen Pre-Operation Safety Review 4 th October 2011 The Hydrogen Delivery System – An Introduction M Hills.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
Spectrometer Solenoid Prep Work at RAL and LBNL Steve Virostek Lawrence Berkeley National Lab Steve Virostek Lawrence Berkeley National Lab MICE VC May.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
MICE Construction Project Update: SSs, PRY, Cavities, Tracker… 1MAP Friday Meeting – January 30, 2015 Alan Bross.
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
US Construction Project: SSs, PRY, Cavities and test program 1.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
US Project Plan for MICE Peter H. Garbincius, Mark Palmer, Alan Bross, Rich Krull Fermilab April 16, 2015.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
S A Griffiths CM42 June 2015 Electrical & Control.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Reported by Ron Prwivo for Ian Robson. Overview Response to Recommendations from the RLSR of November 2014 – very good, RF staffing remains an issue Very.
Muon Ionisation Cooling Experiment Overview
Resource Loaded Schedule and Budget Profile
Status of the MICE Construction Project
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Overall time schedule of SRF activities
Presentation transcript:

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014

2 Step IV  Updates to schedule –Spectrometer Solenoid control and instrumentation racks have arrived at DL (20 th August)  Enabling work to be completed on the build and subsequent installation of control and power racks at RAL –Spectrometer Solenoid cooler compressors and heads will be shipped very soon  West wall compressor installation is progressing well and will be ready to accommodate the compressors when they arrive –Spectrometer Solenoid vacuum equipment will arrive is the same shipment as above  Final work on the Vacuum manifold can then be done. –Extensions to the compressor hoses – order is now out and we have a shipping date  17 th November from New York so allowing a week for customs should arrive around 24 th Nov.  Installation of the lines will be done when trays have been completed. Final design work for trays almost complete.

3 Step IV  Updates to schedule –South side PRY materials delivery to RAL 2 nd March 2015  This is a change from the original dates in the dashboard but work will be carried out at the manufacturing company to mitigate the installation risk at RAL.  A full fit up of the frame and wall material will be carried out to ensure all fastener positions are correct.  Any changes required at RAL would risk severe delay.  Survey data for the floor sections currently being installed at RAL will be sent to the manufacturing company to correlate the fastener positions.  Up to the delivery of the South materials a great deal of work can be carried out to smooth the latter stages of the construction  Full test fit of the magnets with bellows  LH2 system connection, pressure and vacuum test  Process for absorber changes  Fit checks for the LiH…… –North side material delivery remain the same as previously stated 24 th March for wall materials.

4 Step IV  Dates  Construction complete – 27 th May 2015 –South PRY material installation was not on the critical path and with a better understanding of the installation process the construction complete date can be held (within a few days)  Commissioning complete – 3 rd August 2015  Data taking period – up to 10 months –More explanation on the next slide with Step 3PI/2

5 Step 3PI/2 (the Step formally know as V)

6 Step 3PI/2  Critical Path –The main item driving the critical path is the completion of the RF systems 1 and 2 in the hall at RAL –From the analysis of when the RF construction and installation can be carried out there is a lot of slack created in the schedule. –It is this slack that has been taken up fully that is giving the very latest dates for the end of Step IV data taking and then the start of de-commissioning of the Step IV arrangement. –In actual fact we would want to give ourselves some slack and so we must discuss exactly how long we are going to need to collect the data at Step IV.  Dates –End of Step IV data taking – 1 st June 2016 (slack must be gained so this date is the very latest possible) –RF System 2 delivered to RAL – 31 st August 2016 –Step IV de-commissioning complete – 8 th July 2016 –South side PRY installation complete – 16 th December 2016 –North side PRY installation complete – 10 th February 2017 –Step 3PI/2 Construction complete – 24 th March 2017 –Commissioning complete – 2 nd May 2017 –End of Step 3PI/2 Data taking – 30 th March 2018