" Limited Use, Unlimited Power... "1 Welcome To The Esteemed Consumers Of BESCOM In Tariff Revision FY-16 Hearing
2 Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... " BESCOM on Justification for Tariff revision – FY 16
TECHNICAL PARAMETERS 3 Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... " Parameter Details as on Sub Stations Consumers (In Lakhs) HT Line in KM LT Line in KM LT to HT Ratio No. of DTCs (In Lakhs) Energy Input in Million Units Energy Sold in Million Units Revenue Demand in Rs. Crore Revenue Collection in Rs. Crore
CONSUMER PROFILE 4 Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... " Sl No.DESCRIPTION No. of Installation as on Dec-14 in Lakhs Cons. in Mus for FY (Apr-14 to Dec- 14) 1BJ/KJ DOMESTIC Commercial IP Sets LT Industrial Water Supply Public Lighting Temporary Supply TOTAL (LT) TOTAL (HT) TOTAL (LT+ HT)
VARIOUS ONLINE SERVICES PROVIDED TO CONSUMERS 5 Online Bill Payment Online Submission of Applications a)New Connection b)Name Change c)Tariff Change d)Load change e)Meter Shifting f)Surrender Installation g)Solar Rebate h)Consumer Complaints Process Reengineering & Simplification of Forms Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
Contd… 6 Power Outage Information on Website Pushing of Bills through s for HT and LT consumers (8800 no’s of HT consumers out of number of HT consumers and around 2.5 lakhs of LT consumers out of 53 lakhs consumers bills have been sent through Mails in the month of Feb-15) More Payment Options to Consumers: a)ECS b)Online Payment (Net Banking, Cards) c)Bangalore One (Citizen Service Centre) d)Mobile one application e)Post offices Immediate Plans: a)Mobile App for BESCOM Services b)Know Your Feeder Performance Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
BILLING & COLLECTION EFFICIENCY IMPROVEMENT 7 1)Administrative Interventions: i.Meter Readers to report to Accounts wing ii.Meter Reading date reallocation a)First Fortnight Bill Serving b)Second Fortnight Disconnection & Mopping Up iii.Removal of Dummy Meter Reader Codes iv.Additional Meter Readers in Urban fast growing areas v.MBC Monitoring Team at Corporate Office vi.Slum Connections regularisation Drive Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
Contd… 8 2) Administrative Interventions: i.Capturing Meter details (Type, location etc ) through SBM (Spot Billing Machine) ii.Tagging of Floating Consumers iii.Disallowance of Part Payment Except Court Orders 3)Business Intelligence Report 4)Photo Billing & Spot Billing Collection Photo Billing: a)Instead of SBM, Android based Smart Phones are used b)GPS captures the LAT/ LONG of the consumers premises & camera captures the image of the meter read c)Through GPRS the data is pushed to the server Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
Contd… 9 Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
Contd… 10 Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
Contd… Improvements in Revenue Demand: 11 Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
Contd… 12 Spot Bill Connection: The Meter Reader on the spot collects the electricity dues and gives receipt to the consumer. 5) Cleansing of Data Base: i.Long Disconnected & Ghost installations removed ii.IP Sets & Street Lights data properly filled iii.Zero consumption installations verified and monitored RAPDRP INTEGRATION WITH: 1.Distribution Automation System ( DAS) of Bangalore 2.Smart Grid ( Pilot in one section taken up with PGCIL being consultants) Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
NEED FOR TARIFF HIKE 13
TARIFF HIKE COMPONENTS FOR FY- 16 Total deficit Rs.2062 (80 paise) FY-13- Regulatory Asset Rs.342 (13 paise) Truing up for FY- 14 Rs.840 (33 paise) Proposed gap for FY-16 Rs.881 (34 paise) 14
Regulatory Asset FY-13 Commission in Tariff Order 2014, dt , Trued up FY-13 and approved the gap of 1,152 Cr. Rs.1152 Crs Rs.525 Crs. - GoK Rs.16Crs. -absorbed FY15 tariff Rs.611Cr - Regulatory asset FY-16 Rs.342Cr - Regulatory asset + carrying cost FY-17 Rs.384Cr - Regulatory asset + carrying cost 13 paise - Consider ed for FY-16 gap 15
Why Gap occurred during FY14 true up ? 1 Increase in Power purchase cost 2 Change in consumption mix 3 Non realization of approved tariff GAP of Rs. 840 Crs ( 33 paise) 16
Increase in Power Purchase Cost (Rs. Per unit) FY-14 Note : 26 paise increase is due to variance in PP cost of FY14 Source ApprovedActual Rs./unit KPCL Hydel KPCL Thermal CGS IPPs NCE Short-term AVERAGE
Increase in power purchase cost FY-14 - Approved V/s Actual 18
Realization rate & its effect - FY-14 19
Non realization of Appd. tariff Note : 4 paise increase is due to variance in PP cost of FY14 20
Open Access details 21 Due to consumers leaving the grid, loss in revenue for BESCOM is approx. Rs.184 Crs. No. of consumersIndustrialCommercialTotal Open Access Captive Total
Breakup for 34 paise for FY-16 Rs.881 Crs (34 paise) Non realiztion of approved Tariff by the Commission for FY paise under realization Estimated increase in expenditure 16 paise 22
Estimation of Expenditure for FY-16 Expenditure Power Purchase R&M Employee A&G Depreciation Interest & finance FY-14 Actl FY-16 Prop Diff Rs./unit 23
34 paise required for FY-16 1 paise in A&G 1 paise in Depr. 2 paise in Employees Cost 4 paise in Interest and Finance 8 paise in Power Purchase cost 17 paise incr. due to under realization 16 paise incr. due to incr. in expenditure 10 paise in Non Tariff 7 paise in HT 24
Revenue inadequate to cover Operational Expenses In Rs. Crs. 25
Avg. tariff Increase v/s Actuals realised over the years (In Ps./unit) Note : A total of 170 paise/unit increased in tariff by KERC during the period from FY-09 to FY-14 but where as the actual realisation was 102 paise/unit only. 26
Comparison of various Indices from the base year
Compliance to Directives in BRIEF 28
Sl.No.DirectiveCompliance 1Power supply positionComplied 2 24X7 consumer service center Complied 3 Energy Audit & Metering of DTC’s Energy Audit feeder wise been done, However Subdivision wise Eenergy audit requires fixing of boundary meters which will be completed in next 2 months and 56% of DTCs are already metered 4HVDS HVDS works on going in 1)Tumkur taluka( total 25 feeders out of which 11 feeders are completed/Commissioned), 2)Chikkabalapura( total 6 feeders out of which 3 feeders are commissioned) and 3)Dodaballapura(total 9 feeders out of which 1 feeder is commissioned). 5NJY 1) NJY Phase-1 completed, 2) NJY phase-2 scheduled for completion in ) Phase-3 tenders are called soon 6DSM in agricultureDPR under preparation 29
Sl.No.DirectiveCompliance 7Lifeline supply to un electrified households Taken up under RGGVY12th plan and DDUGJY plan 8Prevention of electrical accidents crores Works completed for making the network safe. Further division wise action plan is in place 30
31 Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
32 Online Bill Payment Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... " Month No. of Registered Consumers Total TransactionsTotal Amount in Rs. 14-Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
33 Online Submission of Applications Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
34 Process Reengineering & Simplification of Forms Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
35 Power Outages Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
36 Know Your Feeder Performance Screen Shot Contd.. Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
37 Know Your Feeder Performance Screen Shot Contd.. Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
38 Know Your Feeder Performance Screen Shot Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "
39 BUSINESS INTELLIGENCE REPORT Bangalore Electricity Supply Company Limited " Limited Use, Unlimited Power... "