8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC 23 June :07: Started injection cleaning with B1. 08:13: Fault on MKI B2. –MKI Beam 2 in P8 had a breakdown at 07:49 during the SoftStart process.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Friday morning Dump fill due to the trip of the RQF.A78  intervention had been just planned for the morning on the circuit Access, interventions:  RQF.A56/78,
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
04:01 Injection kicker timing problems B2  Injection pre-pulse shifted, causing BETS to inhibit beam injection. 144 bunches on TDI.  Run without ROF.A81B2.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Production running 1 pb-1Lost to Mon h2062e32EOF studies Tue h17.152e32UFO Q8.L5 Tue h e32OP request Thu h e32OP.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Wednesday September 14th
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Report Week 40 (R. Assmann & E.B. Holzer)
Summary of Week 11: 14 – 21 March
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
Summary of Week 16 G. Arduini, J. Wenninger
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Week 35 – Technical Stop and Restart
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
LHC Morning Meeting - G. Arduini
Summary Thursday h21: Stable beams fill #1303.
Monday 24 October hours of 25ns MD
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Tuesday 17/5 10: TeV - colliding. Start roman pot alignment ...
Tue/Wed 12/ :00 Probe beam back again
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Presentation transcript:

8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29 End of abort gap cleaning. Dump. Rampdown and precycle. 16:58 RF lines 7B1, 7B2 and 8B2 have an error on the LL. 17:59 RF back. Checks for the new XPOC release. 18:32 Injection. Beam 2 injection problems. Transfer line steering. MKI8 faults. TI2 BPM LSS6 interlocks. 22:20 Machine filled. Start ramp. 22:29 Beams dumped. Trips 2 RF modules, arcs detected. Ramp down and precycle. 23h31 Injection. Friday LHC morning report

Prepared beams with a special filling scheme  nominal bunches boardering the abort gap, pilot injected and kept elsewhere.  One injection with one train of 12 and one injection with two trains of 12 bunches, 50 ns spaced bunches.  Ramped to 3.5TeV collided. Switched on abort gap cleaning  tune stepping in range of 0.29 to 0.33 (vertical plane), 2 second repeat cycle, 30 steps in tune.  The initially used cleaning pulse was ~1 microsecond long, located early in the abort gap, as for cleaning at 450 GeV. An effect on the luminosity could be seen for this initial part, when switching on B1 cleaning, but not readily confirmed by wirescans done towards the end of the MD. RF voltage was reduced in different steps and observed cleaning. Summary Abort Gap Cleaning (M. Meddahi et al) LHC morning report

Length of the cleaning pulse was later increased  cover almost full abort gap (~2.5us), works well. After three hours in collisions no more effect on lumi decay when cleaning is switched on/off Recovered equal bunch length for both beams  lowering voltage to 6.5 MV (before different steps were done on both beams so bucket filling was different) Moved tune…  range symmetric about tune of 0.32, not better.  Narrowed tune range to 0.31 to 0.33, cleaning is worse.  Best cleaning was for the initial choice of 0.29 to 0.33 Long cleaning pulse  with voltage drop of 2 MV (9.5 MV to 7.5 MV) cleaning was insufficient.  For smaller voltage drops the cleaning seemed to act as a barrier. Summary Abort Gap Cleaning (M. Meddahi et al) LHC morning report

1. RF voltage changed  leak of beam into abort gap 2. Transverse damper cleans out the gap (faster than synchrotron rad.) Abort Gap Cleaning example LHC morning report Population in abort gap Beam 2Beam 1 Population in abort gap Time history filling cleaning filling cleaning

1. RF voltage changed  leak of beam into abort gap 2. Transverse damper cleans out the gap (faster than synchrotron rad.) Abort Gap Cleaning example (52 s later) LHC morning report Population in abort gap Beam 2Beam 1 Population in abort gap Time history filling cleaning filling cleaning

Abort Gap Population vs Time LHC morning report 4:15:09 PM  0 s 4:16:14 PM  + 65 s 4:16:25 PM  + 76 s

Bunch by bunch lumi data to be looked at in detail. The abort gap cleaning is operational if we want to use it, but effect on luminosity with full machine still needs to be checked in detail. Propose to test it at an end of fill for a couple of hours, using the longer cleaning pulse, at the beginning of next week. Summary Abort Gap Cleaning (M. Meddahi et al) LHC morning report

23:31 Injection. Injection problems. SPS injection oscillations. MKI8 faults. 23:55 Called kicker expert for MKI8 problem.  The problem with the MKI is that now there is a shift between the prepulse and the abort gap keeper.  Expert comes to CCC to correct the shift.  RF checked that all OK from their side. 01:44 Injection for physics.  Kicker problem solved.  Injection efficiency is affected by a BPM interlock in SPS-LSS6 for B1. SPS problems.  Injected beam dumped by losses. 03:00 Injection for physics again. Fri/Sat 7/ LHC morning report

Transient AGK (“abort gap keeper”) inhibition for injection of bucket 1 (probe beam) resulting in missing kick (beam on TDI):  Inhibition seems due to asynchronism between AGK 100MHz generation clock in LBDS and injection prepulse (end AGK window).  Shift of the AGK w.r.t the injection by -10ns improves the situation for injection of bucket 1 but induces transient inhibition on the injection of bucket (beginning of AGK window).  Roll back to original synchronisation settings.  AGK window length within tolerances (no interlock at LBDS level).  Phase offset between revolution frequency and injection prepulse w.r.t selected bucket appears to be OK (shift of the AGK results in inhibition of the bucket as foreseen) Looks like as to be a drift within one timing module.  Access needed in UA87 to identified the faulty module  In case of similar failure (kicker in faulty state after injection of probe beam in bucket 1), installation can be restarted.  If the problem occurs again for the probe in bucket 1, we have to try again until it works. Switching the MKI to standby resets the fault. MKI (beam2) problems (E. Carlier) LHC morning report

03:00 Injection for physics again. 03:51 Ramp. 04:33 Stable beams. Fill #2194. Initial luminosity: 3.2e33. 05:10 Beams dumped by trip of sector 56. MP3 investigating. Integrated lumi: 7pb-1. Ramp down and recycle. 07:41 Access to point 6 (QPS problem) and point 2 (ALICE). 08:45 QPS problem solved, pre-cycle starting  circuit breaker for whole QPS rack open – second time this happens Expect beam back around 10h00. Saturday LHC morning report

Friday pm/Sat/Sun: Physics Monday day: High pile-up MD. Tue – Thu: Physics Friday: Floating MD 25ns Ahead LHC morning report