Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to.

Slides:



Advertisements
Similar presentations
Connoizor Enabling Performance for Businesses through Software Website: Contact:
Advertisements

Presenter: Sohel Akhter, PMP, CCNA,ISMS
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
Copyright , Dennis J. Frailey CSE7315 – Software Project Management CSE7315 M30 - Version 9.01 SMU CSE 7315 Planning and Managing a Software Project.
CEU Making Project Management Work in the Real World.
Chapter 7: Project Cost Management
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Microsoft Project 2002 Sessions 5-6. Entering Tasks During this first session we will enter a set of tasks that comprise building a shed – data sheet.
Irwin/McGraw-Hill ©The McGraw-Hill Companies, 2000 Chapter 13 Progress and Performance Measurement and Evaluation.
Chapter 10: Monitoring and Controlling Change
Degree and Graduation Seminar Cost Management
Earned Value Project Management: a powerful tool for software projects
IIPM1 TIPS AND TECHNIQUES FOR PMP EXAM Tip # 1. Tense Verification - Verify the TENSE of the question before answering. International Institute of Project.
Project Management Software Tools Cheryl A. Wilhelmsen Lee Ostrom.
Project Management in Practice
P ROJECT M ANAGEMENT, PMI A PPROACH (PMP) P ROJECT C OST M ANAGEMENT Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University of.
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
This work is licensed under a Creative Commons Attribution 3.0 Unported LicenseCreative Commons Attribution 3.0 Unported License (CC-BY). Project Management.
GSET Technical Seminar Series Space Telescope Science Institute November 21, Earned Value Management: An Introduction and Short Tutorial Wayne Baggett.
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Project Monitoring and Control. Monitoring – collecting, recording, and reporting information concerning project performance that project manger and others.
Project Management Methodology Project monitoring and control.
Progress and Performance Measurement and Evaluation CHAPTER THIRTEEN Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 13: Progress and Performance Measurement and Evaluation
1 ev14a Interactive Session 4 u Tuesday, July 17 7pm to 10pm u Build a sqa plan for the dental office software u Assume a 3-person, development team, a.
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
© SYBEX Inc All Rights Reserved. Session 10 Project Control.
Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT PROJECT MANAGEMENT LESSON 5 AND 6: PROJECT PLANNING – TIME AND COST PLANNING AND MANAGEMENT.
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
EARNED VALUE MANAGEMENT (EVM)
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Budgeting the Project 4-1 Budget. 4-2 Homework #17  Overview  Approaches for gather data  Budgeting & Estimating costs  Budget uncertainty and risk.
Advanced Project Plan Tracking Lesson 15. Skills Matrix SkillsMatrix Skill Record actual start, finish, and duration values of tasks Enter actual start.
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W.
Learning PMP Formulas the Easy Way
Evaluating EVM January 13, EVM Issues and Opportunities ▪ EVM Basics ▪ EVM Issues ▪ EVM ETC and EAC Calculations ▪ EVM Cost and Schedule Value Calculations.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
Where Module 04 : Knowing Where the Project Is 1.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
EARNED VALUE MANAGEMENT & ORACLE PRIMAVERA P6 TREY MILLER, MBA, PMP ORACLE PRIMAVERA P6 EPPM CERTIFIED IMPLEMENTATION SPECIALIST GLOBAL PROJECT MANAGEMENT,
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
Schedule Control (Earned Value)
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Earned Value Management
PowerPoint Presentation by Charlie Cook THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Progress and Performance Measurement and Evaluation Chapter.
Measuring Progress HNC Project Management. Measuring Schedule Performance Break project tasks up into small work units. Work units that are too large.
Project Management Earned Value Management Demonstration
Earned Value Analysis by Miles M. Hamby, PhD Copyright©2014 Miles M
“PMP® Exam Prep” Earned Value Management
PROJECT MANAGEMENT AND CONTROL
Budget Planning.
CHAPTER:7 Project Cost Management
Earned Value Management
Earned Value Management
Project Cost Management
Work Packages / Deliverables Completed
Earned Value Management & Oracle Primavera P6
Progress and Performance Measurement and Evaluation
Project Scope Management
An Introduction to Earned Value Performance Measurement
Earned Value Measures Planned Value (PV) Earned Value (EV)
فرآيند كنترل پروژه.
Schedule and Cost Variance Problem
5. Project PLAN & cost estimation
Presentation transcript:

Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to look for patterns. When I see the correct pattern I know the formula is correct. AC = ACWP PV = BCWS EV = BCWP

Formula Memorization Trick Ok lets build this. First is to see the pattern of 2 subtractions, 3 divides, 2 subtractions CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC

Formula Memorization Trick Next see the pattern of Variance and Index. Cost, Schedule and Cost, Schedule. CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC

Formula Memorization Trick Next see the pattern of Earned Value (EV). This used to be BCWP. CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC

Formula Memorization Trick Next see the pattern of Actual Cost (AC) and Planned Value (PV) and how they alternate. Skip a line and its AC again. CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC

Formula Memorization Trick Next see the pattern of Estimated at Completion (EAC). As well as Budget at Completion (BAC) CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC

Formula Memorization Trick Not much left. Notice that CPI is divisor of EAC so find CPI skip a line and place it at the end of EAC formula. CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC ETC and VAC don’t really match to anything, you just have to know where they go.

Formula Memorization Trick This may look confusing but it worked great for me and I have had others tell me it worked for them as well. CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC

Other Formulas to Know Communication Channels: N(N-1)/2 Pert Mean: (Pessimistic + 4*Most Likely + Optimistic) / 6 Standard Deviation: (Pessimistic – Optimistic) / 6 Variance: ((Pessimistic – Optimistic) / 6) squared Present Value or PV: Future Value / (1+ rate of return) to the power of n. Where n = periods of time.