Mine Construction
Start of Barge Landing area. A trailer, excavator and generator. Early Barge Landing June 2007 with one trailer to start construction.
2012 Developed Area Fuel Tank Early Barge Landing July 2007 with projected development outline
Early Barge Landing August 2007 with a construction camp Fuel Tank 2012 Developed Area
Barge Landing under Construction in 2007 note the significant fill material placed in the area of tree clearing and topsoil removal Fuel Tank Construction Offices Construction Camp
Barge Landing – Container storage area raised 3m above river level with compacted fill Fuel Tank Construction Offices Construction Camp Container storage area
Barge Landing (winter 2009) – Construction Camp & Supplies Ready. Large equipment fleet used in the construction.
Helicopter dropping in first construction camp units at airstrip